Permit: TC-COM-1123-02681
Permit Details
Apply Date:
11/16/2023
Applicant:
JASON GRECO
Description:
2nd Party - Proposed 9,109 square foot Early Childcare Facility with a 7,168 square foot outdoor playground.
Permit Reviews
Permit Number - TC-COM-1123-02681
Permit Status: Complete
Permit Description: 2nd Party - Proposed 9,109 square foot Early Childcare Facility with a 7,168 square foot outdoor playground.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/21/2023 | COMMERCIAL REVIEW - FULL v.2 | 01/16/2024 | REQUIRES RESUBMIT |
| 05/30/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 06/03/2025 | REQUIRES RESUBMIT |
| 04/07/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/15/2025 | REQUIRES RESUBMIT |
| 02/13/2024 | RESTAMP - COMMERCIAL v.1 | 02/26/2024 | APPROVED |
| 01/19/2024 | COMMERCIAL REVIEW - FULL v.3 | 02/13/2024 | APPROVED |
| 06/20/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/24/2025 | APPROVED |
| 06/17/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.3 | 06/18/2025 | APPROVED |
| 11/20/2023 | COMMERCIAL REVIEW - FULL v.1 | 12/15/2023 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-COM-1123-02681
Permit Status: Complete
Permit Description: 2nd Party - Proposed 9,109 square foot Early Childcare Facility with a 7,168 square foot outdoor playground.
| Date | Description | Comments |
|---|---|---|
| 12/28/2023 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. | |
| 12/28/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 11/20/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 12/28/2023 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
| 12/28/2023 | SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED. | |
| 11/21/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 12/28/2023 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. | |
| 12/28/2023 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-1123-02681
Permite Description: 2nd Party - Proposed 9,109 square foot Early Childcare Facility with a 7,168 square foot outdoor playground.
Total Outstanding Inspections - 12
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/26/2024 | COT - BULD - SWG Clearance | N/A | Re-inspection required | 12-26-24, gauge for gas pressure test at 11 psi. Test shall be at 15psi for minimum of 10 minutes. |
| 10/21/2024 | COT - HCEL - Electrical Intermediate | N/A | Partial Pass | 10-21-24: PARTIAL PASS--Electrical wiring is complete in classrooms, hallway, office area, and restrooms. Sub-panels are not installed in interior electrical closet. Okay to insulate exterior walls floor to roof deck. |
| 09/20/2024 | BULD - Electrical Clearance | N/A | Not Ready | |
| 11/26/2024 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | 11/26/2024 inspection was called in for trash enclosure. Inspected by engineer inspector. |
| 03/04/2025 | COT - HCME - Mechanical Intermediate | N/A | Partial Pass | 3-4-25, tie in exhaust in pantry room, flex in classroom, and mc cable tie in to water heater at laundry room. |
| 12/26/2024 | COT - HCPL - Gas Final | N/A | Re-inspection required | 12-26-24, gauge for gas pressure test at 11 psi. Test shall be at 15psi for minimum of 10 minutes. |
| COT - FCON - Sprinkler - Final | N/A | Not Ready | ||
| COT - FCON - Alarm - Final | N/A | Not Ready | ||
| COT - FCON - Fire - Final | N/A | Not Ready | ||
| 04/25/2025 | COT - HCBU - Building Final | N/A | Partial Pass | 4-25-25, building final approved-pending conditions & 3rd party outdoor lighting inspection. (Ok for level four TCO. EWS) |
| 04/25/2025 | COT - HCBU - TCO | N/A | Partial Pass | 4-25-25-level 2 TCO(partial pass). |
| 09/27/2024 | COT - HCEL - Outdoor Lighting | N/A | Re-inspection required | Light pole bases are not deep enough per plan. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-1123-02681
Permit Description: 2nd Party - Proposed 9,109 square foot Early Childcare Facility with a 7,168 square foot outdoor playground.
Total Completed Inspections - 29
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/08/2024 | COT - HCBU - Preslab | Passed | ||
| 09/20/2024 | COT - HCEL - Electrical Underground | Passed | 9/20/24: secondary service okay to back fill. | |
| 10/09/2024 | COT - HCBU - Framing | Passed | 10/9/24: Interior walls are properly fire-blocked, all shear wall anchors are installed, and bottom plate bolts are installed with plate washers per plan. Okay to proceed with installation of insulation and drywall. | |
| 10/23/2024 | COT - HCPL - Plumbing Intermediate | Passed | 10/23/24: plumbing rough-in is complete for DWV and hot/cold supply lines. Both systems are under water test. | |
| 10/23/2024 | COT - HCPL - Plumbing Roof Drains | Passed | 10/23/24: Roof drains are installed and under a water test with no leaks. Okay to proceed. | |
| 01/02/2025 | COT - BULD - SWG Clearance | Passed | Passed 1/2/25 CLEARANCE SWG | |
| 01/14/2025 | COT - HCBU - Roof Nailing | Passed | 1-14-25, approved. | |
| 01/14/2025 | COT - HCBU - Firewall/Fire Barrier/Firestop | Passed | 1-14-24, was previously inspected and approved. All interior walls already taped. | |
| 01/29/2025 | COT - HCME - Mechanical Above Ceiling | Passed | Above ceiling mechanical is complete. Okay to install perimeter ceiling tiles in all classrooms, staff break room, and front lobby. | |
| 01/29/2025 | COT - HCPL - Plumbing Above Ceiling | Passed | Above ceiling plumbing is complete. Okay to install perimeter ceiling tiles in all classrooms, staff break room, and front lobby. | |
| 02/04/2025 | COT - HCEL - Electrical Intermediate | Passed | ||
| 02/04/2025 | BULD - Electrical Clearance | Passed | 2/4/25: TEP ECO CLEARANCE APPROVED FOR 7396 S NEXUS RD. | |
| 03/04/2025 | COT - HCBU - Building Above Ceiling | Passed | ||
| 03/04/2025 | COT - HCBU - Excavation/Rebar/Zoning | Passed | ||
| 03/04/2025 | COT - HCEL - Grounding/Bonding | Passed | 3-4-25, approved. | |
| 03/26/2025 | COT - HCEL - Electrical Above Ceiling | Passed | ||
| 03/26/2025 | COT - HCME - Mechanical Intermediate | Passed | ||
| 03/26/2025 | COT - HCPL - Gas Final | Passed | ||
| 03/25/2025 | COT - FCON - Sprinkler - Final | Passed | ||
| 04/02/2025 | COT - HCME - Mechanical Final | Passed | 4-2-25, mechanical final approved. | |
| 04/02/2025 | COT - HCEL - Electrical Final | Passed | 4-2-25, electrical final approved. | |
| 04/09/2025 | COT - FCON - Alarm - Final | Passed | ||
| 04/09/2025 | COT - FCON - Fire - Final | Passed | ||
| 04/10/2025 | COT - HCPL - Plumbing Final | Passed | 4/10/2024 corrections were made. Chlorination report has been uploaded and in review. | |
| 04/10/2025 | TRSP - ROW - Final/Close-Out | Passed | ||
| 04/25/2025 | ENGR Engineering Final | Passed | ||
| 06/26/2025 | COT - HCBU - Building Final | Passed | ||
| 06/26/2025 | COT - HCBU - TCO | Passed | ||
| 06/26/2025 | COT - HCEL - Outdoor Lighting | Passed |