Permit: TC-COM-1122-00184
Permit Details
Apply Date:
11/28/2022
Applicant:
Description:
Full build out of suites 100 thru 160 for United Parcel Service and their sorting/distribution operations.
Permit Reviews
Permit Number - TC-COM-1122-00184
Permit Status: Complete
Permit Description: Full build out of suites 100 thru 160 for United Parcel Service and their sorting/distribution operations.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/25/2023 | COMMERCIAL REVIEW - FULL v.4 | 04/26/2023 | APPROVED |
01/12/2023 | COMMERCIAL REVIEW - FULL v.2 | 01/30/2023 | REQUIRES RESUBMIT |
02/29/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/04/2024 | APPROVED |
06/09/2023 | COMMERCIAL REVIEW - FULL v.1 | 06/13/2023 | APPROVED |
04/26/2023 | RESTAMP - COMMERCIAL v.1 | 04/27/2023 | APPROVED |
03/12/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/14/2024 | APPROVED |
12/28/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/29/2023 | APPROVED |
03/10/2023 | COMMERCIAL REVIEW - FULL v.3 | 04/07/2023 | REQUIRES RESUBMIT |
12/07/2022 | COMMERCIAL REVIEW - FULL v.1 | 01/12/2023 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-COM-1122-00184
Permit Status: Complete
Permit Description: Full build out of suites 100 thru 160 for United Parcel Service and their sorting/distribution operations.
Date | Description | Comments |
---|---|---|
04/07/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
04/27/2023 | Contractor's active Arizona Contractor's License number for specified scope of work required prior to issuance of permit. | |
04/07/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
04/07/2023 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
12/28/2023 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
03/06/2024 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. | |
03/06/2024 | CONVEROR SYSTEM FOR SORTING AND LOADING OPERATIONS Designs must be submitted and approved prior to final. | |
12/28/2023 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. | |
03/06/2024 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-1122-00184
Permite Description: Full build out of suites 100 thru 160 for United Parcel Service and their sorting/distribution operations.
Total Outstanding Inspections - 3
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/09/2024 | COT - HCBU - Firewall/Fire Barrier/Firestop | N/A | Not Applicable | |
12/06/2023 | COT - FCON - Alarm - Final | N/A | Partial Pass | Fire pump flows and tampers approved. Strobes in Supervisors office and women's bathroom changed to horn/strobe, conveyors need to shut down per fire alarm plans sequence of operations. Add notification devices under the conveyors. |
COT - FCON - Sprinkler - Final | N/A | Not Ready | Sub did not call in his sprinkler permit. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-1122-00184
Permit Description: Full build out of suites 100 thru 160 for United Parcel Service and their sorting/distribution operations.
Total Completed Inspections - 28
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/26/2023 | COT - HCPL - Plumbing Progress | Passed | 7/26/23: Underground plumbing for vehicle wash area is installed from catch drain to outside of building were grease interceptor is going to be installed. Okay to shade and backfill/compact trench. | |
08/09/2023 | COT - HCBU - Preslab | Passed | Pad for vehicle wash pit is properly dowed with rebar reinforcement, catch basin is installed, and subsoil is compacted. Okay to pour back concrete slab. | |
08/18/2023 | COT - HCPL - Plumbing Intermediate | Passed | Plumbing rough-in is complete DWV Pipes are under water pressure test. Supply water lines are under compressed air pressure test and there are no leaks on either system. Okay to cover with drywall. | |
08/29/2023 | BULD - Electrical Clearance | Passed | Suite 100 HPD, HPE, HPB, HPC, HPF. 6818 S country club. Clearance for TEP ECO. 8/29/2023 | |
08/29/2023 | COT - HCPL - Rough Soil | Passed | ||
09/18/2023 | COT - HCBU - Interior Shear Bracing | Passed | 9/18/23: Control Room and Operations Room interior shear walls are properly screwed off per plans. Okay to tape, texture, and paint walls. | |
09/18/2023 | COT - HCBU - Framing | Passed | 9/18/23: Framing for second floor mezzanine is complete. Okay to drywall both sides of walls, tape, texture, and paint. Dividing walls for vehicle repair are properly framed to below roof deck. Okay to drywall both sides of walls, tape, texture, and paint. | |
09/18/2023 | COT - HCPL - Plumbing Above Ceiling | Passed | 9/18/23: Main plumbing lines are properly installed and under water test. Fire sprinkler lines are roughed in. All on the second floor of mezzanine. Vent pipes in walls for vehicle repair area are installed through the roof and under water test. | |
09/25/2023 | COT - HCEL - Electrical Intermediate | Passed | 9/25/23: Electrical rough-in is complete on 1st floor mezzanine. Okay to insulate and sheet rock walls. | |
09/28/2023 | COT - HCPL - Gas Pressure Test | Passed | Approved gas piping and pressure test to meter location | |
11/30/2023 | COT - LCPL - Sewer | Passed | 11/15/23: oil-water separator connection to building per plan. Pending connection from Oil-water separator to manhole. 11/30/23: connection from oil-water separator to manhole per plan ok to back fill. |
|
12/06/2023 | COT - HCEL - Electrical Final | Passed | 12/4/23: passed all interior electrical. Pending rooftop. 12/5/23: passed |
|
12/18/2023 | COT - BULD - SWG Clearance | Passed | 12/18/23: SWG Clearance | |
12/18/2023 | COT - HCPL - Gas Final | Passed | ||
02/09/2024 | COT - HCME - Mechanical Final | Passed | ||
02/09/2024 | COT - HCPL - Plumbing Final | Passed | ||
02/09/2024 | COT - HCEL - Electrical Above Ceiling | Passed | ||
02/09/2024 | COT - HCME - Mechanical Above Ceiling | Passed | ||
02/09/2024 | COT - HCEL - Electrical Progress | Passed | ||
02/09/2024 | COT - HCME - Mechanical Intermediate | Passed | ||
02/09/2024 | COT - HCME - Mechanical Progress | Passed | ||
03/05/2024 | TRSP - ROW - Final/Close-Out | Passed | ||
03/05/2024 | COT - FCON - Alarm - Final | Passed | ||
03/06/2024 | COT - FCON - Sprinkler - Final | Passed | ||
03/06/2024 | COT - FCON - Fire - Final | Passed | ||
03/08/2024 | ENGR Engineering Final | Passed | ||
03/08/2024 | COT - HCBU - Building Final | Passed | 3/8/24: CofO Passed. Unsatisfied Conditions are on separate permit. | |
03/14/2024 | COT - HCBU - Building Progress | Passed |