Permit: TC-COM-0925-01647
Permit Details
Apply Date:
09/09/2025
Applicant:
Adrian Zubiran
Description:
INSTALLATION OF (7) NEW LVL 2 EV CHARGERS ON A NEW 400A MBP. LOAD CONTROLED BY PCS SOFTWARE
Permit Reviews
Permit Number - TC-COM-0925-01647
Permit Status: Complete
Permit Description: INSTALLATION OF (7) NEW LVL 2 EV CHARGERS ON A NEW 400A MBP. LOAD CONTROLED BY PCS SOFTWARE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/08/2025 | COMMERCIAL PDSD SIMPLE REVIEW v.2 | 10/08/2025 | APPROVED |
| 09/09/2025 | COMMERCIAL PDSD SIMPLE REVIEW v.1 | 09/10/2025 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-COM-0925-01647
Permit Status: Complete
Permit Description: INSTALLATION OF (7) NEW LVL 2 EV CHARGERS ON A NEW 400A MBP. LOAD CONTROLED BY PCS SOFTWARE
| Date | Description | Comments |
|---|---|---|
| 09/09/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0925-01647
Permit Description: INSTALLATION OF (7) NEW LVL 2 EV CHARGERS ON A NEW 400A MBP. LOAD CONTROLED BY PCS SOFTWARE
Total Completed Inspections - 5
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/06/2026 | BULD - Electrical Clearance | Passed | 3.6.26 Approved for incr code to TEP |
|
| 03/23/2026 | COT - LCEL - Electrical Final | Passed | 03/23/2026 Approved per plan, all breakers landed and labeled at main combiner panel for EV chargers. |
|
| 05/19/2026 | COT - LCEL - Grounding/Bonding | Passed | Approved per Raul M back in March. 5/19/2026 | |
| 05/19/2026 | COT - LCEL - Electrical Underground | Passed | Approved per Raul M back in March. 5/19/2026 | |
| 05/19/2026 | COT - LCEL - Electrical Intermediate | Passed | Approved per Raul M back in March. 5/19/2026 |