Permit Details

Status:
Inspections Complete
Type:
Commercial Building
Address:
10000 S RITA RD
Address NEW:
10000 S RITA RD
Apply Date:
09/03/2024
Applicant:
Emmanuel Denis
Description:
A 12 ft high screen wall for a TEP Phase 1 & Phase 2 switchyard.

Permit Reviews

Permit Number - TC-COM-0924-01712
Permit Status: Inspections complete
Permit Description: A 12 ft high screen wall for a TEP Phase 1 & Phase 2 switchyard.
Start Date Submittal Complete Date Status  
09/06/2024 COMMERCIAL FENCE/WALL v.1 09/17/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-COM-0924-01712
Permit Status: Inspections complete
Permit Description: A 12 ft high screen wall for a TEP Phase 1 & Phase 2 switchyard.
Total Outstanding Activity Conditions - 2
Date Name
09/17/2024 SPECIAL INSPECTION FOR CONCRETE REINFORCING STEEL AND CONCRETE PLACEMENT IS REQUIRED.
09/17/2024 SPECIAL INSPECTION FOR MASONRY PRE-GROUT & REINFORCING STEEL AND GROUT PLACEMENT IS REQUIRED.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-COM-0924-01712
Permite Description: A 12 ft high screen wall for a TEP Phase 1 & Phase 2 switchyard.
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
11/04/2024 COT - LCBU - Excavation/Rebar/Zoning N/A Partial Pass 11/4/24: reinforcement per plan at west wall footings, reinforcement per plans at south wall at footing, reinforcement per plan east wall at footings. Pending north wall.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-COM-0924-01712
Permit Description: A 12 ft high screen wall for a TEP Phase 1 & Phase 2 switchyard.
Total Completed Inspections - 6
Date Description Inspector Results Comments
01/08/2025 COT - LCBU - Excavation/Rebar/Zoning Passed
01/07/2025 SITE - Zoning Final Passed
01/07/2025 TRSP - ROW - Final/Close-Out Passed structure on TEP property, no impact to right of way, approved
01/08/2025 COT - LCBU - Masonry Pregrout Passed
01/29/2025 ENGR Engineering Final Passed Wall is and has been completed as per the stamped plans and its requirements.
01/29/2025 COT - LCBU - Building Final Passed