Permit: TC-COM-0924-01712
Permit Details
Status:
Inspections Complete
Type:
Commercial Building
Address:
10000 S RITA RD
Address NEW:
10000 S RITA RD
Apply Date:
09/03/2024
Applicant:
Emmanuel Denis
Description:
A 12 ft high screen wall for a TEP Phase 1 & Phase 2 switchyard.
Permit Reviews
Permit Number - TC-COM-0924-01712
Permit Status: Inspections complete
Permit Description: A 12 ft high screen wall for a TEP Phase 1 & Phase 2 switchyard.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/06/2024 | COMMERCIAL FENCE/WALL v.1 | 09/17/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-COM-0924-01712
Permit Status: Inspections complete
Permit Description: A 12 ft high screen wall for a TEP Phase 1 & Phase 2 switchyard.
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 09/17/2024 | SPECIAL INSPECTION FOR CONCRETE REINFORCING STEEL AND CONCRETE PLACEMENT IS REQUIRED. |
| 09/17/2024 | SPECIAL INSPECTION FOR MASONRY PRE-GROUT & REINFORCING STEEL AND GROUT PLACEMENT IS REQUIRED. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-COM-0924-01712
Permite Description: A 12 ft high screen wall for a TEP Phase 1 & Phase 2 switchyard.
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/04/2024 | COT - LCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | 11/4/24: reinforcement per plan at west wall footings, reinforcement per plans at south wall at footing, reinforcement per plan east wall at footings. Pending north wall. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-COM-0924-01712
Permit Description: A 12 ft high screen wall for a TEP Phase 1 & Phase 2 switchyard.
Total Completed Inspections - 6
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/08/2025 | COT - LCBU - Excavation/Rebar/Zoning | Passed | ||
| 01/07/2025 | SITE - Zoning Final | Passed | ||
| 01/07/2025 | TRSP - ROW - Final/Close-Out | Passed | structure on TEP property, no impact to right of way, approved | |
| 01/08/2025 | COT - LCBU - Masonry Pregrout | Passed | ||
| 01/29/2025 | ENGR Engineering Final | Passed | Wall is and has been completed as per the stamped plans and its requirements. | |
| 01/29/2025 | COT - LCBU - Building Final | Passed |