Permit Details

Status:
Complete
Type:
Commercial Building
Address:
280 N CARAPAN AV
Address NEW:
280 N CARAPAN AV
Apply Date:
09/14/2023
Applicant:
Cade Somers
Description:
BUILDING 3 - EMERGENCY REPAIRS to building #2 #3 #5 exterior walkways.

Permit Reviews

Permit Number - TC-COM-0923-02210
Permit Status: Complete
Permit Description: BUILDING 3 - EMERGENCY REPAIRS to building #2 #3 #5 exterior walkways.
Start Date Submittal Complete Date Status  
09/14/2023 COMMERCIAL REVIEW - FULL v.1 10/13/2023 APPROVED Review Details

Conditions

Permit Number - TC-COM-0923-02210
Permit Status: Complete
Permit Description: BUILDING 3 - EMERGENCY REPAIRS to building #2 #3 #5 exterior walkways.
Date Description Comments
10/13/2023 Current listed contractor ROC# in expired status. Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-0923-02210
Permite Description: BUILDING 3 - EMERGENCY REPAIRS to building #2 #3 #5 exterior walkways.
Total Outstanding Inspections - 3
Last Inspection Date Description Inspector Results Comments
07/25/2024 COT - LCBU - Building Final N/A Re-inspection required Inspection is called in for lath. Okay to proceed progress areas. 2/5/2024
1/22/2024

West end add blocking where plywood meet. Shear nailing not per schedule. Add missing anchor bolts. Nail off bottom plates every 16" o.c. Add straps from headers to columns. Buildings #2 and #3. 5/2/2024

5/7/24: corrections made on west end of apartments for buildings #2 and #3.
7/25/24: through the wall metal scuppers missing throughout on all sides of building (per plan).
07/30/2024 COT - LCBU - Building Progress N/A Re-inspection required Inspection is called in for lath. Okay to proceed progress areas. 2/5/2024
1/22/2024

West end add blocking where plywood meet. Shear nailing not per schedule. Add missing anchor bolts. Nail off bottom plates every 16" o.c. Add straps from headers to columns. Buildings #2 and #3. 5/2/2024

5/7/24: corrections made on west end of apartments for buildings #2 and #3.
7/25/24: through the wall metal scuppers missing throughout on all sides of building (per plan).
7/30/24: corrections not made
05/07/2024 COT - LCBU - Framing N/A Partial Pass 1/22/2024

West end add blocking where plywood meet. Shear nailing not per schedule. Add missing anchor bolts. Nail off bottom plates every 16" o.c. Add straps from headers to columns. Buildings #2 and #3. 5/2/2024

5/7/24: corrections made on west end of apartments for buildings #2 and #3.

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-0923-02210
Permit Description: BUILDING 3 - EMERGENCY REPAIRS to building #2 #3 #5 exterior walkways.
Total Completed Inspections - 3
Date Description Inspector Results Comments
08/05/2024 COT - LCBU - Building Final Passed
08/05/2024 COT - LCBU - Building Progress Passed
08/05/2024 COT - LCBU - Framing Passed

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-1_SHARED PLANS LETTER_V1.PDF DOCUMENTS VIEW