Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit: TC-COM-0923-02210

Parcel: 11611011A


Addresses:

280 N CARAPAN AV

Inspection Status: Partial Pass

Inspection History: COT - LCBU - Building Progress

Date Description Inspector Results Comments
01/25/2024 COT - LCBU - Building Progress Partial Pass Building #280, East side of the building; Levels #1, 2, 3 stairwells have been water proofed. Ok to stucco progress areas
02/05/2024 COT - LCBU - Building Progress Partial Pass Inspection is called in for lath. Okay to proceed progress areas. 2/5/2024
07/25/2024 COT - LCBU - Building Progress Re-inspection required Inspection is called in for lath. Okay to proceed progress areas. 2/5/2024
1/22/2024

West end add blocking where plywood meet. Shear nailing not per schedule. Add missing anchor bolts. Nail off bottom plates every 16" o.c. Add straps from headers to columns. Buildings #2 and #3. 5/2/2024

5/7/24: corrections made on west end of apartments for buildings #2 and #3.
7/25/24: through the wall metal scuppers missing throughout on all sides of building (per plan).
07/30/2024 COT - LCBU - Building Progress Re-inspection required Inspection is called in for lath. Okay to proceed progress areas. 2/5/2024
1/22/2024

West end add blocking where plywood meet. Shear nailing not per schedule. Add missing anchor bolts. Nail off bottom plates every 16" o.c. Add straps from headers to columns. Buildings #2 and #3. 5/2/2024

5/7/24: corrections made on west end of apartments for buildings #2 and #3.
7/25/24: through the wall metal scuppers missing throughout on all sides of building (per plan).
7/30/24: corrections not made
08/05/2024 COT - LCBU - Building Progress Passed