Permit: TC-COM-0923-02180
Permit Details
Apply Date:
09/08/2023
Applicant:
Fernanda Fraijo
Description:
The TMC Emergency Department Addition and Renovation includes renovation of 19,984sf of the existing Emergency Department and addition of 586sf new area.
Permit Reviews
Permit Number - TC-COM-0923-02180
Permit Status: Issued
Permit Description: The TMC Emergency Department Addition and Renovation includes renovation of 19,984sf of the existing Emergency Department and addition of 586sf new area.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
11/03/2023 | COMMERCIAL REVIEW - FULL v.2 | 12/01/2023 | REQUIRES RESUBMIT |
12/24/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/26/2024 | APPROVED |
04/09/2024 | RESTAMP - COMMERCIAL v.1 | 04/11/2024 | APPROVED |
04/08/2024 | COMMERCIAL REVIEW - FULL v.5 | 04/09/2024 | APPROVED |
03/06/2024 | COMMERCIAL REVIEW - FULL v.4 | 04/05/2024 | REQUIRES RESUBMIT |
01/16/2024 | COMMERCIAL REVIEW - FULL v.3 | 02/09/2024 | REQUIRES RESUBMIT |
09/08/2023 | COMMERCIAL REVIEW - FULL v.1 | 10/09/2023 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TC-COM-0923-02180
Permit Status: Issued
Permit Description: The TMC Emergency Department Addition and Renovation includes renovation of 19,984sf of the existing Emergency Department and addition of 586sf new area.
Total Outstanding Activity Conditions - 6
Date | Name |
---|---|
01/19/2024 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. |
01/19/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
01/19/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
01/19/2024 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. |
01/19/2024 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. |
01/19/2024 | SPECIAL INSPECTION FOR WELDING IS REQUIRED. |
Conditions
Permit Number - TC-COM-0923-02180
Permit Status: Issued
Permit Description: The TMC Emergency Department Addition and Renovation includes renovation of 19,984sf of the existing Emergency Department and addition of 586sf new area.
Date | Description | Comments |
---|---|---|
12/26/2024 | AIR BALANCING REPORT IS REQUIRED. | |
09/08/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
05/09/2024 | Prior to Issuance: This project requires issuance of a Development Package (DP) permit prior to issuance of this permit. Prior to TCO/Final: This project requires full completion of a Development Package (DP) permit prior to Temporary C of O and/or final completion this permit. | |
12/26/2024 | SPECIAL INSPECTION FOR MEDICAL GASES IS REQUIRED. | |
12/26/2024 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-COM-0923-02180
Permite Description: The TMC Emergency Department Addition and Renovation includes renovation of 19,984sf of the existing Emergency Department and addition of 586sf new area.
Total Outstanding Inspections - 21
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/08/2024 | COT - HCPL - Gas Final | N/A | Not Applicable | |
11/08/2024 | BULD - Electrical Clearance | N/A | Not Applicable | |
11/08/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
11/08/2024 | COT - HCPL - Gas Pressure Test | N/A | Not Applicable | |
12/20/2024 | COT - FCON - Sprinkler - Final | N/A | Partial Pass | Phase 1 approved |
11/15/2024 | ENGR Engineering Final | N/A | Not Ready | All temporary fencing, tool boxes, equipment, etc. should be removed and construction activities completed prior to engineering final. |
12/24/2024 | COT - HCBU - Building Final | N/A | Partial Pass | 12/24/24: PHASE 1 OK FOR LEVEL 4 TCO |
12/24/2024 | COT - HCEL - Electrical Above Ceiling | N/A | Partial Pass | 11/15/24: lighting is being installed in grid ceiling throughout hallways and patient rooms. overhead in area B at phase 1 12/24/24: PHASE 1 OK FOR LEVEL 4 TCO |
12/24/2024 | COT - HCEL - Electrical Final | N/A | Partial Pass | 12/24/24: PHASE 1 OK FOR LEVEL 4 TCO |
12/24/2024 | COT - HCEL - Electrical Intermediate | N/A | Partial Pass | 12/24/24: PHASE 1 OK FOR LEVEL 4 TCO |
12/24/2024 | COT - HCEL - Electrical Progress | N/A | Partial Pass | Phase A1. Walls. Add stud by sink carrier; ok to proceed elsewhere. Panel make-up for CBC1, 2, EBA, PC1, 2, EDL and LEB. Walls of new patient rooms. 11/15/24: lighting is being installed in grid ceiling throughout hallways and patient rooms. 12/24/24: PHASE 1 OK FOR LEVEL 4 TCO |
12/24/2024 | COT - HCME - Mechanical Final | N/A | Partial Pass | 12/24/24: PHASE 1 OK FOR LEVEL 4 TCO |
12/24/2024 | COT - HCME - Mechanical Intermediate | N/A | Partial Pass | 12/24/24: PHASE 1 OK FOR LEVEL 4 TCO |
12/24/2024 | COT - HCME - Mechanical Progress | N/A | Partial Pass | Duct sealing for medium pressure, Area A. Ductwork and registers are installed in hallways and patients rooms. overhead in area B at phase 1 12/24/24: PHASE 1 OK FOR LEVEL 4 TCO. |
12/24/2024 | COT - HCPL - Medical Gas/Final | N/A | Partial Pass | 12/24/24: PHASE 1 OK FOR LEVEL 4 TCO |
12/06/2024 | COT - HCPL - Medical Gas/Test | N/A | Partial Pass | Phase One |
08/07/2024 | COT - HCPL - Plumbing Intermediate | N/A | Partial Pass | walls of Phase one. |
09/10/2024 | COT - HCPL - Plumbing Progress | N/A | Partial Pass | Phase A2. All DWV. |
12/24/2024 | COT - HCPL - Plumbing Final | N/A | Partial Pass | 12/24/24: PHASE 1 OK FOR LEVEL 4 TCO |
12/30/2024 | COT - FCON - Alarm - Final | N/A | Partial Pass | Phase 1 approved |
12/30/2024 | COT - FCON - Fire - Final | N/A | Partial Pass | Phase 1 approved for TCO level 2. |
Completed Inspections
Permit Status: Issued
Permit Number: TC-COM-0923-02180
Permit Description: The TMC Emergency Department Addition and Renovation includes renovation of 19,984sf of the existing Emergency Department and addition of 586sf new area.
Total Completed Inspections - 13
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/09/2024 | COT - HCBU - Preslab | Passed | ||
08/28/2024 | COT - HCBU - Excavation/Rebar/Zoning | Passed | ||
10/15/2024 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
10/23/2024 | COT - HCME - Mechanical Above Ceiling | Passed | ||
10/23/2024 | COT - HCBU - Building Above Ceiling | Passed | ||
10/23/2024 | COT - HCPL - Plumbing Above Ceiling | Passed | ||
10/23/2024 | COT - HCBU - Firewall/Fire Barrier/Firestop | Passed | ||
10/23/2024 | COT - HCBU - Framing | Passed | ||
11/08/2024 | COT - HCBU - Roof Nailing | Passed | ||
11/15/2024 | TRSP - ROW - Final/Close-Out | Passed | ||
12/04/2024 | COT - HCEL - Electrical Underground | Passed | Walked with super for upcoming TCO. Instructed to contact Inspection Manager. | |
12/04/2024 | COT - HCBU - Building Progress | Passed | ||
02/10/2025 | COT - FCON - Fire - Final | Passed |