Inspection Status: Partial Pass
Inspection History: COT - HCME - Mechanical Progress
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| COT - HCME - Mechanical Progress | Partial Pass | Phase Two, Areas One and Two. | ||
| 08/06/2024 | COT - HCME - Mechanical Progress | Partial Pass | Duct sealing for medium pressure, Area A. | |
| 08/06/2025 | COT - HCME - Mechanical Progress | Not Ready | ||
| 09/05/2024 | COT - HCME - Mechanical Progress | Not Ready | ||
| 09/18/2025 | COT - HCME - Mechanical Progress | Partial Pass | Above Ceiling Phase Two. | |
| 10/21/2025 | COT - HCME - Mechanical Progress | Partial Pass | TCO Level Two for Phase Two. | |
| 11/15/2024 | COT - HCME - Mechanical Progress | Partial Pass | Ductwork and registers are installed in hallways and patients rooms. | |
| 12/04/2024 | COT - HCME - Mechanical Progress | Partial Pass | overhead in area B at phase 1 | |
| 12/24/2024 | COT - HCME - Mechanical Progress | Partial Pass | Duct sealing for medium pressure, Area A. Ductwork and registers are installed in hallways and patients rooms. overhead in area B at phase 1 12/24/24: PHASE 1 OK FOR LEVEL 4 TCO. |