Permit: TC-COM-0923-02168
Permit Details
Apply Date:
09/07/2023
Applicant:
JR Durazo
Description:
TI Expansion to existing marijuana dispensary
Permit Reviews
Permit Number - TC-COM-0923-02168
Permit Status: Complete
Permit Description: TI Expansion to existing marijuana dispensary
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/08/2023 | COMMERCIAL REVIEW - FULL v.1 | 09/08/2023 | REQUIRES RESUBMIT |
| 03/01/2024 | COMMERCIAL REVIEW - FULL v.1 | 03/28/2024 | APPROVED |
| 11/08/2023 | COMMERCIAL REVIEW - FULL v.3 | 11/14/2023 | APPROVED |
| 03/28/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/01/2024 | REQUIRES RESUBMIT |
| 06/12/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 06/12/2024 | APPROVED |
| 09/21/2023 | COMMERCIAL REVIEW - FULL v.2 | 11/03/2023 | REQUIRES RESUBMIT |
| 04/02/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/03/2024 | APPROVED |
| 11/14/2023 | RESTAMP - COMMERCIAL v.1 | 11/15/2023 | APPROVED |
Conditions
Permit Number - TC-COM-0923-02168
Permit Status: Complete
Permit Description: TI Expansion to existing marijuana dispensary
| Date | Description | Comments |
|---|---|---|
| 11/02/2023 | AIR BALANCING/COMMISSIONING REPORT IS REQUIRED. | |
| 09/08/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 11/02/2023 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0923-02168
Permite Description: TI Expansion to existing marijuana dispensary
Total Outstanding Inspections - 5
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/27/2024 | COT - LCBU - Building Final | N/A | Partial Pass | Phase I is complete, OK to occupy progress areas. |
| 03/27/2024 | COT - LCEL - Electrical Final | N/A | Partial Pass | Phase I is complete. |
| 03/27/2024 | COT - LCME - Mechanical Final | N/A | Partial Pass | Phase I is complete. |
| 03/27/2024 | COT - LCPL - Plumbing Final | N/A | Partial Pass | Phase I is complete. |
| 03/27/2024 | ENGR Engineering Final | N/A | Partial Pass | Engineering has no issues to prevent a temporary certificate of occupancy level four for phase 1. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0923-02168
Permit Description: TI Expansion to existing marijuana dispensary
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/08/2024 | COT - LCPL - Sewer | Passed | Ok to set set dowels and cover progress areas. | |
| 01/08/2024 | COT - LCPL - Rough Soil | Passed | Ok to cover progress areas. | |
| 01/10/2024 | COT - LCBU - Preslab | Passed | Pour back area: Ok to place concrete in progress areas | |
| 03/19/2024 | BULD - Electrical Clearance | Passed | No electric clearance required. | |
| 03/26/2024 | TRSP - ROW - Final/Close-Out | Passed | ||
| 03/28/2024 | COT - FCON - Sprinkler - Final | Passed | ||
| 03/28/2024 | COT - FCON - Fire - Final | Passed | ||
| 06/10/2024 | COT - LCBU - Building Above Ceiling | Passed | ||
| 06/10/2024 | COT - LCBU - Building Final | Passed | ||
| 06/10/2024 | COT - LCEL - Electrical Final | Passed | ||
| 06/10/2024 | COT - LCME - Mechanical Final | Passed | ||
| 06/10/2024 | COT - LCPL - Plumbing Final | Passed | ||
| 06/10/2024 | ENGR Engineering Final | Passed | NA, no exterior work, interior TI only | |
| 06/10/2024 | COT - LCBU - Framing | Passed | ||
| 06/10/2024 | COT - LCEL - Electrical Above Ceiling | Passed | ||
| 06/10/2024 | COT - LCEL - Electrical Intermediate | Passed | ||
| 06/10/2024 | COT - LCME - Mechanical Above Ceiling | Passed | ||
| 06/10/2024 | COT - LCME - Mechanical Intermediate | Passed | ||
| 06/10/2024 | COT - LCPL - Plumbing Above Ceiling | Passed | ||
| 06/10/2024 | COT - LCPL - Plumbing Intermediate | Passed |