Permit: TC-COM-0825-01545
Permit Details
Status:
Fees Due
Type:
Commercial Building
Address:
3300 S PARK AV BLDG 2
Address NEW:
3300 S PARK AV BLDG 2
Apply Date:
08/18/2025
Applicant:
Description:
New flatwork (THIS WORK PHASE), Later Phase shade canopy, and shipping containers at the JTED Bridges campus
Permit Reviews
Permit Number - TC-COM-0825-01545
Permit Status: Fees due
Permit Description: New flatwork (THIS WORK PHASE), Later Phase shade canopy, and shipping containers at the JTED Bridges campus
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/18/2025 | COMMERCIAL REVIEW - FULL v.1 | 09/11/2025 | REQUIRES RESUBMIT |
| 10/27/2025 | COMMERCIAL REVIEW - FULL v.2 | 10/27/2025 | REQUIRES RESUBMIT |
| 02/23/2026 | COMMERCIAL REVIEW - FULL v.4 | 04/10/2026 | REQUIRES RESUBMIT |
| 10/27/2025 | COMMERCIAL REVIEW - FULL v.3 | 11/19/2025 | REQUIRES RESUBMIT |
| 04/23/2026 | COMMERCIAL REVIEW - FULL v.5 | 04/28/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-COM-0825-01545
Permit Status: Fees due
Permit Description: New flatwork (THIS WORK PHASE), Later Phase shade canopy, and shipping containers at the JTED Bridges campus
Total Outstanding Activity Conditions - 6
| Date | Name |
|---|---|
| 04/23/2026 | a. This approval is conditioned upon project compliance related to the complete and full review of the Encroachment Easement Agreement, Utility Joint User Agreement, and the Supplemental Declaration of Covenants, Conditions and Restrictions for the Bridges Sub-area B-IV (Block 10). As indicated on the construction document sheet G1.2, scope of work on this project phase does not include the shade canopies and shipping containers. (Project Description: New flatwork, shade canopies, & temporary installed shipping containers north of the existing JTED Building II. Shade canopies and shipping containers will be permitted separately and are shown here as reference only and for the sake of clarity for the contractor’s use. Shipping containers will be a temporary installation to be removed at the completion of Building III.) NOTE: Coordination with Tucson Water New Services will be required regarding water line and fire sprinkler crossing property line, please contact Stephen Garcia at 520-837-2207. |
| 04/24/2026 | Please contact Pima County Addressing to resolve issue. Addressing@pima.gov or 520-724-9512 |
| 04/24/2026 | An encroachment agreement is required to be recorded to qualify for the IBC exemption in Section 706.1.1. Please provide a copy of the recorded agreement including, but not limited to any or all of the following: A. Easements a. Ingress/egress b. Utility c. Emergency access B. Systems and infrastructure access and use C. Maintenance D. Unity (sales, lease, etc.) E. Indemnification F. Non-Severability |
| 04/24/2026 | UTILITY JOINT USER AGREEMENT is required prior for to Final Inspection. |
| 09/10/2025 | Post-Installed Anchor Inspection Report is required. |
| 09/10/2025 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. |
Conditions
Permit Number - TC-COM-0825-01545
Permit Status: Fees due
Permit Description: New flatwork (THIS WORK PHASE), Later Phase shade canopy, and shipping containers at the JTED Bridges campus
| Date | Description | Comments |
|---|---|---|
| 11/18/2025 | Please contact Pima County Addressing to resolve issue. Addressing@pima.gov or 520-724-9512 | |
| 08/18/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 09/10/2025 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. |