Inspection Status: Partial Pass
Inspection History: COT - LCBU - Preslab
| Date |
Description |
Inspector |
Results |
Comments |
| 08/13/2026 |
COT - LCBU - Preslab |
|
Partial Pass |
8/13/2026 Partial pass pending trench drain to be completed. |
| 08/14/2026 |
COT - LCBU - Preslab |
|
Partial Pass |
8/14/2026 partial pass. Main pad approved for concrete. Pending container pad. |
| 09/23/2026 |
COT - LCBU - Preslab |
|
Canceled |
9/23/2026 canceled per contractor. |
| 09/24/2026 |
COT - LCBU - Preslab |
|
Not Ready |
9/24/2026 ensure footing carries through all the way at a minimum of 16'. Provide adobes at every 4' to ensure there is a 3" clearance from earth. Remove all loose debris from footings. |
| 09/28/2026 |
COT - LCBU - Preslab |
|
Passed |
9/28/2026 all corrections were made. Okay for concrete placement at perimeter footings for container pads. |