Permit Details

Status:
Complete
Type:
Commercial Building
Address:
9520 E 22ND ST
Address NEW:
9520 E 22ND ST
Apply Date:
08/07/2023
Applicant:
Tanja Weese
Description:
INSTALLATION OF (2) DUAL PORT CAR CHARGERS

Permit Reviews

Permit Number - TC-COM-0823-01920
Permit Status: Complete
Permit Description: INSTALLATION OF (2) DUAL PORT CAR CHARGERS
Start Date Submittal Complete Date Status  
11/22/2023 COMMERCIAL PDSD SIMPLE REVIEW v.3 11/28/2023 APPROVED Review Details
10/17/2023 COMMERCIAL PDSD SIMPLE REVIEW v.2 10/17/2023 REQUIRES RESUBMIT Review Details
08/08/2023 COMMERCIAL PDSD SIMPLE REVIEW v.1 08/08/2023 REQUIRES RESUBMIT Review Details

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-0823-01920
Permite Description: INSTALLATION OF (2) DUAL PORT CAR CHARGERS
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
09/19/2024 BULD - Electrical Clearance N/A Canceled NR, 3-phase conductors not installed to transformer - cancelled by contractor

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-0823-01920
Permit Description: INSTALLATION OF (2) DUAL PORT CAR CHARGERS
Total Completed Inspections - 5
Date Description Inspector Results Comments
08/19/2024 COT - LCEL - Grounding/Bonding Passed
08/19/2024 COT - LCEL - Electrical Underground Passed 8/19/24 - remaining underground conduits ok to backfill.
04/24/2025 BULD - Electrical Clearance Passed Approved new 600A service panel and EV Charger installation - ECO Clearance to TEP is required
04/24/2025 COT - LCEL - Electrical Final Passed
04/24/2025 COT - LCEL - Electrical Intermediate Passed