Permit: TC-COM-0724-01322
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
5943 E SPEEDWAY BL
Address NEW:
5943 E SPEEDWAY BL
Apply Date:
07/08/2024
Applicant:
burak bekat
Description:
RENOVATION TO EXISTING COMMERICAL BUILDING TO SUPPORT PADEL AND PICKLEBALL COURTS, INCLUDING OFFICES, WAITING AREA AND RESTROOMS.
Permit Reviews
Permit Number - TC-COM-0724-01322
Permit Status: Complete
Permit Description: RENOVATION TO EXISTING COMMERICAL BUILDING TO SUPPORT PADEL AND PICKLEBALL COURTS, INCLUDING OFFICES, WAITING AREA AND RESTROOMS.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/14/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/17/2025 | APPROVED |
| 07/11/2024 | COMMERCIAL REVIEW - FULL v.1 | 08/16/2024 | REQUIRES RESUBMIT |
| 03/11/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/12/2025 | APPROVED |
| 09/09/2024 | COMMERCIAL REVIEW - FULL v.2 | 09/16/2024 | APPROVED |
| 09/16/2024 | RESTAMP - COMMERCIAL v.1 | 09/19/2024 | APPROVED |
| 03/26/2025 | COMMERCIAL REVIEW - FULL v.1 | 03/26/2025 | REQUIRES RESUBMIT |
| 12/11/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/12/2024 | APPROVED |
Conditions
Permit Number - TC-COM-0724-01322
Permit Status: Complete
Permit Description: RENOVATION TO EXISTING COMMERICAL BUILDING TO SUPPORT PADEL AND PICKLEBALL COURTS, INCLUDING OFFICES, WAITING AREA AND RESTROOMS.
| Date | Description | Comments |
|---|---|---|
| 03/17/2025 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 09/19/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 12/11/2024 | Padel Court Designs must be submitted and approved prior to ... | |
| 03/17/2025 | Post-Installed Anchor Inspection Report is required. | |
| 03/17/2025 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. | |
| 03/17/2025 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. | |
| 03/17/2025 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0724-01322
Permite Description: RENOVATION TO EXISTING COMMERICAL BUILDING TO SUPPORT PADEL AND PICKLEBALL COURTS, INCLUDING OFFICES, WAITING AREA AND RESTROOMS.
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/23/2024 | COT - HCME - Mechanical Intermediate | N/A | Not Ready | Wanted multiple inspections added to permit. |
| 02/25/2025 | COT - LCEL - Outdoor Lighting | N/A | Not Ready | Builder had questions about procedures; no pre-con inspection. |
| 03/12/2025 | COT - FCON - Fire - Final | N/A | Re-inspection required | Exiting, occupancy type and load issues. Ok for TCO level 3 |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0724-01322
Permit Description: RENOVATION TO EXISTING COMMERICAL BUILDING TO SUPPORT PADEL AND PICKLEBALL COURTS, INCLUDING OFFICES, WAITING AREA AND RESTROOMS.
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/23/2024 | COT - HCPL - Rough Soil | Passed | ||
| 01/08/2025 | COT - HCBU - Excavation/Rebar/Zoning | Passed | ||
| 01/23/2025 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
| 01/23/2025 | COT - HCBU - Roof Nailing | Passed | ||
| 01/23/2025 | COT - HCBU - Framing | Passed | ||
| 01/23/2025 | COT - HCBU - Preslab | Passed | ||
| 01/30/2025 | COT - HCEL - Electrical Intermediate | Passed | ||
| 02/04/2025 | BULD - Electrical Clearance | Passed | INCR; no meter at this time. | |
| 02/04/2025 | COT - LCEL - Electrical Underground | Passed | ||
| 02/06/2025 | COT - HCME - Mechanical Intermediate | Passed | ||
| 02/19/2025 | COT - LCEL - Grounding/Bonding | Passed | ||
| 02/19/2025 | COT - LCEL - Electrical Above Ceiling | Passed | ||
| 02/19/2025 | COT - LCEL - Electrical Intermediate | Passed | ||
| 02/19/2025 | COT - LCEL - Electrical Progress | Passed | ||
| 02/19/2025 | COT - HCPL - Plumbing Intermediate | Passed | ||
| 02/19/2025 | COT - BULD - SWG Clearance | Passed | ||
| 02/25/2025 | TRSP - ROW - Final/Close-Out | Passed | ||
| 03/07/2025 | COT - LCPL - Plumbing Final | Passed | 3-7-25, plumbing final approved. | |
| 03/07/2025 | COT - LCEL - Electrical Final | Passed | 3-7-25, electrical final approved. | |
| 03/11/2025 | COT - LCBU - Building Final | Passed | ||
| 03/12/2025 | COT - LCME - Mechanical Final | Passed | ||
| 03/12/2025 | ENGR Engineering Final | Passed | Contractor continues to work on the landscaping needs to connect the irrigation line. Control pan Over here, yeah I have Hands and knees contractor and ask I could came back for re inspection pass the landscaping. |
|
| 03/12/2025 | COT - LCEL - Outdoor Lighting | Passed |