Permit: TC-COM-0723-01801
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
6612 E TANQUE VERDE RD
Address NEW:
6612 E TANQUE VERDE RD
Apply Date:
07/21/2023
Applicant:
John McColgin
Description:
Interior Tenant Improvement - Scented Leaf Tea House, T/V
Permit Reviews
Permit Number - TC-COM-0723-01801
Permit Status: Complete
Permit Description: Interior Tenant Improvement - Scented Leaf Tea House, T/V
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/31/2023 | COMMERCIAL REVIEW - FULL v.4 | 11/01/2023 | REQUIRES RESUBMIT |
| 09/05/2023 | COMMERCIAL REVIEW - FULL v.2 | 09/21/2023 | REQUIRES RESUBMIT |
| 11/13/2023 | RESTAMP - COMMERCIAL v.1 | 11/15/2023 | APPROVED |
| 09/25/2023 | COMMERCIAL REVIEW - FULL v.3 | 09/25/2023 | REQUIRES RESUBMIT |
| 11/03/2023 | COMMERCIAL REVIEW - FULL v.5 | 11/13/2023 | APPROVED |
| 07/26/2023 | COMMERCIAL REVIEW - FULL v.1 | 08/30/2023 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-COM-0723-01801
Permit Status: Complete
Permit Description: Interior Tenant Improvement - Scented Leaf Tea House, T/V
| Date | Description | Comments |
|---|---|---|
| 07/26/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0723-01801
Permite Description: Interior Tenant Improvement - Scented Leaf Tea House, T/V
Total Outstanding Inspections - 16
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/15/2024 | COT - HCBU - Building Above Ceiling | N/A | Not Applicable | |
| 03/15/2024 | COT - HCBU - CofO | N/A | Not Applicable | |
| 03/15/2024 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Not Applicable | |
| 03/15/2024 | COT - HCBU - Exterior Clips/Sheathing | N/A | Not Applicable | |
| 03/15/2024 | COT - HCBU - Roof Nailing | N/A | Not Applicable | |
| 03/15/2024 | COT - HCBU - Masonry Pregrout | N/A | Not Applicable | |
| 01/10/2024 | COT - HCEL - Electrical Intermediate | N/A | Partial Pass | 1/10/24: partial for kitchen, restroom, utility room and east wall okay to cover |
| 03/15/2024 | COT - HCME - Mechanical Above Ceiling | N/A | Not Applicable | |
| 03/15/2024 | COT - HCPL - Gas Final | N/A | Not Applicable | |
| 03/15/2024 | COT - HCPL - Plumbing Above Ceiling | N/A | Not Applicable | |
| 03/15/2024 | COT - HCPL - Gas Pressure Test | N/A | Not Applicable | |
| PDSD Heavy Commercial Building Division Pre-Construction Meeting | N/A | Requested | ||
| 03/15/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 03/15/2024 | BULD - Electrical Clearance | N/A | Not Applicable | |
| 03/15/2024 | COT - FCON - Fire - Final | N/A | Re-inspection required | Address, Fire extinguishers, occupant load sign, Places of Assembly permit. |
| 03/15/2024 | ENGR Engineering Final | N/A | Partial Pass | engineering has no issues that would prevent a temporary certificate of occupancy. A few minor items remain to be completed on development package permit. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0723-01801
Permit Description: Interior Tenant Improvement - Scented Leaf Tea House, T/V
Total Completed Inspections - 18
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/10/2024 | COT - HCPL - Plumbing Intermediate | Passed | ||
| 01/25/2024 | COT - HCBU - Firewall/Fire Barrier/Firestop | Passed | Drywall. | |
| 03/08/2024 | TRSP - ROW - Final/Close-Out | Passed | ||
| 03/11/2024 | COT - HCPL - Rough Soil | Passed | ||
| 03/15/2024 | COT - HCBU - Building Progress | Passed | ||
| 03/15/2024 | COT - HCBU - Building Final | Passed | ||
| 03/15/2024 | COT - HCBU - Framing | Passed | ||
| 03/15/2024 | COT - HCEL - Electrical Intermediate | Passed | ||
| 03/15/2024 | COT - HCEL - Electrical Final | Passed | ||
| 03/15/2024 | COT - HCEL - Electrical Progress | Passed | ||
| 03/15/2024 | COT - HCME - Mechanical Intermediate | Passed | ||
| 03/15/2024 | COT - HCME - Mechanical Final | Passed | ||
| 03/15/2024 | COT - HCME - Mechanical Progress | Passed | ||
| 03/15/2024 | COT - HCPL - Plumbing Progress | Passed | ||
| 03/15/2024 | COT - HCPL - Plumbing Final | Passed | ||
| 03/21/2024 | COT - HCBU - TCO | Passed | Level Four, Pending fire inspection approval. (Fire Approve on 03/28/2024 EStevens) | |
| 03/28/2024 | COT - FCON - Fire - Final | Passed | ||
| 05/01/2024 | ENGR Engineering Final | Passed |