Permit: TC-COM-0626-00994
Permit Details
Apply Date:
06/30/2026
Applicant:
David Willett
Description:
1 story type VB sprinkled Community Resource Center proposed south of the existing Salvation Army Amphi Corps building. Main programmatic elements include a commercial kitchen, MPR, and client pantry.
Permit Reviews
Permit Number - TC-COM-0626-00994
Permit Status: In review
Permit Description: 1 story type VB sprinkled Community Resource Center proposed south of the existing Salvation Army Amphi Corps building. Main programmatic elements include a commercial kitchen, MPR, and client pantry.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/01/2026 | COMMERCIAL REVIEW - FULL v.1 | 07/24/2026 | REQUIRES RESUBMIT |
| 08/07/2026 | COMMERCIAL REVIEW - FULL v.2 | N/A | IN REVIEW |
Outstanding Activity Conditions
Permit Number - TC-COM-0626-00994
Permit Status: In review
Permit Description: 1 story type VB sprinkled Community Resource Center proposed south of the existing Salvation Army Amphi Corps building. Main programmatic elements include a commercial kitchen, MPR, and client pantry.
Total Outstanding Activity Conditions - 16
| Date | Name |
|---|---|
| 07/01/2026 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. |
| 07/01/2026 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. |
| 07/21/2026 | COUNTY HEALTH INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED. |
| 07/21/2026 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 07/21/2026 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. |
| 07/21/2026 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. |
| 07/21/2026 | Separate submittal to PC Industrial Wastewater Control is required for new interceptors and separators. Contact Kelsey.McMonagle@pima.gov or Adam.DeLaTorre@pima.gov for review and assessment of the proposed grease interceptor. |
| 07/21/2026 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
| 07/21/2026 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. |
| 07/21/2026 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
| 07/21/2026 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
| 07/21/2026 | SPECIAL INSPECTION FOR WELDING IS REQUIRED. |
| 07/23/2026 | AIR BALANCING REPORT IS REQUIRED. |
| 07/23/2026 | Submit the Air Leakage & Duct Tightness Test Report completed by an Approved Special Inspector prior to Final Inspections. |
| 07/23/2026 | Separate submittal to PC Industrial Wastewater Control is required for new interceptors and separators. Contact Kelsey.McMonagle@pima.gov or Adam.DeLaTorre@pima.gov for review and assessment of the proposed grease interceptor. |
| 07/23/2026 | WATER STERILIZATION REPORT IS REQUIRED. |