Permit: TC-COM-0626-00867
Permit Details
Apply Date:
06/11/2026
Applicant:
Description:
2. PROPOSED INSTALLATION OF THE FOLLOWING LUMEN EQUIPMENT WITHIN COMPOUND: * (1) NEW 12'-0" X 24'-0" CONCRETE PAD * (1) NEW CONCRETE SIDE WALK AND CONCRETE ENTRY PAD * (1) NEW 300 KW DIESEL GENERATOR ON NEW CONC PAD W/660 GALLON BASE FUEL TANK * (1) NEW UTILITY H-FRAME W/ A CANOPY ON NEW CONC PAD * (1) NEW 23' X 36' EQUIPMENT SHELTER ON EXISTING CONCRETE PAD * (1) NEW UTILITY H-FRAME W/ NEW UTILITY SERVICE 3. PROPOSED INSTALLATION OF NEW 1200A @ 277V/480V 3PH ELECTRICAL SERVICE.
Permit Reviews
Permit Number - TC-COM-0626-00867
Permit Status: Inspections
Permit Description: 2. PROPOSED INSTALLATION OF THE FOLLOWING
LUMEN EQUIPMENT WITHIN COMPOUND:
* (1) NEW 12'-0" X 24'-0" CONCRETE PAD
* (1) NEW CONCRETE SIDE WALK AND CONCRETE
ENTRY PAD
* (1) NEW 300 KW DIESEL GENERATOR ON NEW
CONC PAD W/660 GALLON BASE FUEL TANK
* (1) NEW UTILITY H-FRAME W/ A CANOPY ON NEW
CONC PAD
* (1) NEW 23' X 36' EQUIPMENT SHELTER ON
EXISTING CONCRETE PAD
* (1) NEW UTILITY H-FRAME W/ NEW UTILITY SERVICE
3. PROPOSED INSTALLATION OF NEW 1200A @
277V/480V 3PH ELECTRICAL SERVICE.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/05/2026 | COMMERCIAL REVIEW - FULL v.1 | 08/27/2026 | REQUIRES RESUBMIT |
| 09/15/2026 | COMMERCIAL REVIEW - FULL v.2 | 09/18/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-COM-0626-00867
Permit Status: Inspections
Permit Description: 2. PROPOSED INSTALLATION OF THE FOLLOWING
LUMEN EQUIPMENT WITHIN COMPOUND:
* (1) NEW 12'-0" X 24'-0" CONCRETE PAD
* (1) NEW CONCRETE SIDE WALK AND CONCRETE
ENTRY PAD
* (1) NEW 300 KW DIESEL GENERATOR ON NEW
CONC PAD W/660 GALLON BASE FUEL TANK
* (1) NEW UTILITY H-FRAME W/ A CANOPY ON NEW
CONC PAD
* (1) NEW 23' X 36' EQUIPMENT SHELTER ON
EXISTING CONCRETE PAD
* (1) NEW UTILITY H-FRAME W/ NEW UTILITY SERVICE
3. PROPOSED INSTALLATION OF NEW 1200A @
277V/480V 3PH ELECTRICAL SERVICE.
Total Outstanding Activity Conditions - 5
| Date | Name |
|---|---|
| 08/26/2026 | Prior to Final - Special Inspections - SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. |
| 08/26/2026 | Prior to Final - Special Inspections - SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
| 08/26/2026 | Prior to Final - Special Inspections - SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. |
| 08/26/2026 | SPECIAL INSPECTION FOR WELDING IS REQUIRED. |
| 09/17/2026 | The generator shall include a fuel catchment feature designed to contain at least 210 gallons of fuel in the event of a leak. |
Conditions
Permit Number - TC-COM-0626-00867
Permit Status: Inspections
Permit Description: 2. PROPOSED INSTALLATION OF THE FOLLOWING
LUMEN EQUIPMENT WITHIN COMPOUND:
* (1) NEW 12'-0" X 24'-0" CONCRETE PAD
* (1) NEW CONCRETE SIDE WALK AND CONCRETE
ENTRY PAD
* (1) NEW 300 KW DIESEL GENERATOR ON NEW
CONC PAD W/660 GALLON BASE FUEL TANK
* (1) NEW UTILITY H-FRAME W/ A CANOPY ON NEW
CONC PAD
* (1) NEW 23' X 36' EQUIPMENT SHELTER ON
EXISTING CONCRETE PAD
* (1) NEW UTILITY H-FRAME W/ NEW UTILITY SERVICE
3. PROPOSED INSTALLATION OF NEW 1200A @
277V/480V 3PH ELECTRICAL SERVICE.
| Date | Description | Comments |
|---|---|---|
| 08/26/2026 | Submit a copy of the approved set of drawings as Factory Built Building by the state of Arizona Office of Manufactured Housing. | |
| 08/26/2026 | Pre-Issuance - Required Documents - Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 08/26/2026 | Submit a copy of the Installation Plan Approval from the State of Arizona. | |
| 08/05/2026 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 08/26/2026 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TC-COM-0626-00867
Permite Description: 2. PROPOSED INSTALLATION OF THE FOLLOWING
LUMEN EQUIPMENT WITHIN COMPOUND:
* (1) NEW 12'-0" X 24'-0" CONCRETE PAD
* (1) NEW CONCRETE SIDE WALK AND CONCRETE
ENTRY PAD
* (1) NEW 300 KW DIESEL GENERATOR ON NEW
CONC PAD W/660 GALLON BASE FUEL TANK
* (1) NEW UTILITY H-FRAME W/ A CANOPY ON NEW
CONC PAD
* (1) NEW 23' X 36' EQUIPMENT SHELTER ON
EXISTING CONCRETE PAD
* (1) NEW UTILITY H-FRAME W/ NEW UTILITY SERVICE
3. PROPOSED INSTALLATION OF NEW 1200A @
277V/480V 3PH ELECTRICAL SERVICE.
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/15/2026 | COT - LCEL - Grounding/Bonding | N/A | Partial Pass | 10/15/2026 Partial pass. Verified #2 ground. Pending ground to service equipment. |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-COM-0626-00867
Permit Description: 2. PROPOSED INSTALLATION OF THE FOLLOWING
LUMEN EQUIPMENT WITHIN COMPOUND:
* (1) NEW 12'-0" X 24'-0" CONCRETE PAD
* (1) NEW CONCRETE SIDE WALK AND CONCRETE
ENTRY PAD
* (1) NEW 300 KW DIESEL GENERATOR ON NEW
CONC PAD W/660 GALLON BASE FUEL TANK
* (1) NEW UTILITY H-FRAME W/ A CANOPY ON NEW
CONC PAD
* (1) NEW 23' X 36' EQUIPMENT SHELTER ON
EXISTING CONCRETE PAD
* (1) NEW UTILITY H-FRAME W/ NEW UTILITY SERVICE
3. PROPOSED INSTALLATION OF NEW 1200A @
277V/480V 3PH ELECTRICAL SERVICE.
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/15/2026 | COT - LCEL - Electrical Underground | Passed | 10/15/2026 X2 3” conduit at new meter location. Ran to pole box location. Same x2 3” ran to new disconnect panel location. X4 4” from disconnect to ATS (automatic transfer switch) x4 3” from generator to ATS. X3 1 1/2” for low voltage. From generator to ATS. X1 1” for starter wire. From generator to ATS. X4 3” from transfer switch to new transformer location. X3 4” from new transformer location to directly into panel. X4 4” for alarm wire from gutter box on south end to existing shelter stubbed up on east end. All schedule 40 conduit. Over drive way 48” depth. Conduit east of fencing at 36” depth. Okay to backfill all progress areas. Shading material required. Ensure caution tape is in place after first lift of compaction. |