Status:
Complete
Type:
Commercial Building
Address:
5943 E SPEEDWAY BL
Address NEW:
5943 E SPEEDWAY BL
Apply Date:
06/04/2024
Applicant:
Description:
Concrete slab and lighting only for the padel and pickleball courts per TD-DEV-0324-00109 REV1: Modifications to Outdoor Lighting. Provided egress site plan indicating full site occupancy and exiting.
Permit Reviews
Permit Number - TC-COM-0624-01080
Permit Status: Complete
Permit Description: Concrete slab and lighting only for the padel and pickleball courts per TD-DEV-0324-00109
REV1: Modifications to Outdoor Lighting. Provided egress site plan indicating full site occupancy and exiting.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/01/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.3 | 04/01/2025 | REQUIRES RESUBMIT |
| 05/23/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.4 | 05/27/2025 | REQUIRES RESUBMIT |
| 07/16/2024 | COMMERCIAL REVIEW - FULL v.2 | 08/16/2024 | APPROVED |
| 03/28/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 03/28/2025 | REQUIRES RESUBMIT |
| 06/04/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.5 | 06/05/2025 | APPROVED |
| 08/16/2024 | RESTAMP - COMMERCIAL v.1 | 08/20/2024 | APPROVED |
| 12/12/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/18/2024 | APPROVED |
| 03/11/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/11/2025 | REQUIRES RESUBMIT |
| 06/06/2024 | COMMERCIAL REVIEW - FULL v.1 | 07/10/2024 | REQUIRES RESUBMIT |
| 04/23/2025 | COMMERCIAL REVIEW - FULL v.1 | 05/19/2025 | APPROVED |
Conditions
Permit Number - TC-COM-0624-01080
Permit Status: Complete
Permit Description: Concrete slab and lighting only for the padel and pickleball courts per TD-DEV-0324-00109
REV1: Modifications to Outdoor Lighting. Provided egress site plan indicating full site occupancy and exiting.
| Date | Description | Comments |
|---|---|---|
| 06/06/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 08/20/2024 | Prior to Issuance: This project requires issuance of a Development Package (DP) permit prior to issuance of this permit. Prior to TCO/Final: This project requires full completion of a Development Package (DP) permit prior to Temporary C of O and/or final completion this permit. | |
| 08/16/2024 | Padel Court Screen Structure Designs must be submitted and approved prior to Final Inspection | |
| 08/15/2024 | SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED. | |
| 07/09/2024 | SPECIAL INSPECTION FOR POST-INSTALLED ANCHORS IS REQUIRED. | |
| 07/09/2024 | SPECIAL INSPECTION FOR SOILS IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0624-01080
Permite Description: Concrete slab and lighting only for the padel and pickleball courts per TD-DEV-0324-00109
REV1: Modifications to Outdoor Lighting. Provided egress site plan indicating full site occupancy and exiting.
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/20/2024 | COT - LCPL - Plumbing Final | N/A | Not Applicable | |
| 12/20/2024 | COT - LCBU - Framing | N/A | Not Applicable | |
| 02/11/2025 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 02/26/2025 | BULD - Electrical Clearance | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0624-01080
Permit Description: Concrete slab and lighting only for the padel and pickleball courts per TD-DEV-0324-00109
REV1: Modifications to Outdoor Lighting. Provided egress site plan indicating full site occupancy and exiting.
Total Completed Inspections - 10
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/20/2024 | COT - LCEL - Electrical Underground | Passed | ||
| 11/27/2024 | COT - LCBU - Excavation/Rebar/Zoning | Passed | ||
| 12/20/2024 | COT - LCEL - Grounding/Bonding | Passed | ||
| 12/20/2024 | COT - LCBU - Preslab | Passed | ||
| 01/10/2025 | COT - LCEL - Electrical Intermediate | Passed | ||
| 02/26/2025 | COT - LCBU - Building Final | Passed | ||
| 02/25/2025 | TRSP - ROW - Final/Close-Out | Passed | ||
| 03/07/2025 | COT - LCEL - Electrical Final | Passed | 3-7-25, electrical final approved. | |
| 03/12/2025 | COT - LCEL - Outdoor Lighting | Passed | ||
| 03/17/2025 | ENGR Engineering Final | Passed |