Inspection Status: Partial Pass
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 02/26/2025 |
ENGR Engineering Final
|
|
Partial Pass |
Contractors good for a level three TCO. Need to complete the landscaping in the back with DG and plants. Also need to sign address for the building. |
| 03/07/2025 |
ENGR Engineering Final
|
|
Not Ready |
Not ready at this time for a TCO of any kind |
| 03/12/2025 |
ENGR Engineering Final
|
|
Partial Pass |
Contractor continues to work on the landscaping needs to connect the irrigation line. |
| 03/17/2025 |
ENGR Engineering Final
|
|
Passed |
|