Permit Details

Status:
Complete
Type:
Commercial Building
Address NEW:
10071 E OLD VAIL RD
Apply Date:
06/27/2023
Applicant:
Catherine Atchley
Description:
New construction Salad and Go drive-thru only restaurant/snack back with trash enclosure

Permit Reviews

Permit Number - TC-COM-0623-01588
Permit Status: Complete
Permit Description: New construction Salad and Go drive-thru only restaurant/snack back with trash enclosure
Start Date Submittal Complete Date Status  
06/29/2023 COMMERCIAL REVIEW - FULL v.1 07/27/2023 REQUIRES RESUBMIT Review Details
10/20/2023 COMMERCIAL REVIEW - FULL v.4 11/07/2023 REQUIRES RESUBMIT Review Details
05/13/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.2 05/15/2024 APPROVED Review Details
08/15/2023 COMMERCIAL REVIEW - FULL v.3 09/14/2023 REQUIRES RESUBMIT Review Details
11/06/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 11/06/2024 APPROVED Review Details
02/12/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 02/13/2024 APPROVED Review Details
11/26/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 11/26/2024 APPROVED Review Details
08/14/2023 COMMERCIAL REVIEW - FULL v.2 08/14/2023 REQUIRES RESUBMIT Review Details
03/21/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 03/24/2025 APPROVED Review Details
05/07/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 05/07/2024 REQUIRES RESUBMIT Review Details
05/16/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 05/17/2024 APPROVED Review Details
01/05/2024 COMMERCIAL REVIEW - FULL v.5 01/31/2024 APPROVED Review Details
01/31/2024 RESTAMP - COMMERCIAL v.1 02/01/2024 APPROVED Review Details

Conditions

Permit Number - TC-COM-0623-01588
Permit Status: Complete
Permit Description: New construction Salad and Go drive-thru only restaurant/snack back with trash enclosure
Date Description Comments
04/24/2024 AIR BALANCING REPORT IS REQUIRED.
04/24/2024 SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED.
04/24/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
04/24/2024 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
04/24/2024 COUNTY HEALTH INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED.
04/24/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
04/24/2024 SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED.
04/24/2024 Separate submittal to PC Industrial Wastewater Control is required for new interceptors and separators. Contact Lucinda.Hyatt@pima.gov for review and assessment..
04/24/2024 SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED.
01/09/2024 Please submit a separate sign permit for an signs associated with this projet.
04/24/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
04/24/2024 SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED.
04/24/2024 WATER STERILIZATION REPORT IS REQUIRED.
04/24/2024 SPECIAL INSPECTION FOR WELDING IS REQUIRED.
04/24/2024 SPECIAL INSPECTION FOR WOOD FRAMED DIAPHRAGMS AND SHEAR WALLS IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-0623-01588
Permite Description: New construction Salad and Go drive-thru only restaurant/snack back with trash enclosure
Total Outstanding Inspections - 8
Last Inspection Date Description Inspector Results Comments
04/08/2024 COT - HCEL - Electrical Above Ceiling N/A Re-inspection required Ducts must be strapped and properly supported throughout. Cannot rest on pex lines and other mechanical equipment., registers and lighting fixtures must be strapped and secured by seismic wire, fire caulk needed at wall penetrations at bathroom, loose duct above ceiling wall dividing bathroom and refrigerator.
04/08/2024 COT - HCME - Mechanical Above Ceiling N/A Re-inspection required Ducts must be strapped and properly supported throughout. Cannot rest on pex lines and other mechanical equipment., registers and lighting fixtures must be strapped and secured by seismic wire, fire caulk needed at wall penetrations at bathroom, loose duct above ceiling wall dividing bathroom and refrigerator.
05/14/2024 COT - HCBU - Masonry Pregrout N/A Not Applicable
05/14/2024 COT - HCBU - Sustainability N/A Not Applicable
05/14/2024 COT - HCME - Venting N/A Not Applicable
PDSD Heavy Commercial Building Division Pre-Construction Meeting N/A Requested
05/14/2024 BULD - Electrical Clearance N/A Not Applicable Duplicate inspection
04/25/2024 COT - BULD - SWG Clearance N/A Not Ready 2nd clearance inspection requested by TEP.

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-0623-01588
Permit Description: New construction Salad and Go drive-thru only restaurant/snack back with trash enclosure
Total Completed Inspections - 34
Date Description Inspector Results Comments
02/15/2024 COT - HCPL - Sewer Passed
02/15/2024 COT - HCPL - Yard Water Line Passed
02/16/2024 COT - HCEL - Electrical Underground Passed
02/23/2024 COT - HCEL - Grounding/Bonding Passed
03/08/2024 COT - HCBU - Framing Passed Exterior & Interior walls are properly framed, fire blocking is installed at the 8' level completely on all walls. Shear wall hold downs are installed and properly secured to sole plate and screwed to studs per manufacturer's specifications.
03/08/2024 COT - HCBU - Roof Nailing Passed Roof is properly nailed down, H2.5 clips are properly installed on each rafters, truss calcs are onsite. Okay to proceed with roofing material application.
03/08/2024 COT - HCBU - Interior Shear Bracing Passed Plywood for interior shear wall is properly installed and secured with nails per plans.
03/15/2024 COT - HCPL - Plumbing Intermediate Passed 3/15/24: Plumbing rough-in is complete. Okay to proceed with installation of insulation and drywall.
03/15/2024 COT - HCME - Mechanical Intermediate Passed 3/15/24: Mechanical rough-in is complete. Okay to proceed with installation of insulation and drywall.
03/15/2024 COT - HCEL - Electrical Intermediate Passed 3/15/24: Electrical rough-in is complete. Okay to proceed with installation of insulation and drywall.
03/15/2024 COT - HCPL - Plumbing Roof Drains Passed Roof drains are complete and under a water test with no leaks.
03/20/2024 COT - HCBU - Exterior Clips/Sheathing Passed
04/08/2024 COT - HCPL - Plumbing Above Ceiling Passed
04/10/2024 COT - LCBU - Excavation/Rebar/Zoning Passed
04/10/2024 COT - HCEL - Electrical Above Ceiling Passed
04/10/2024 COT - HCME - Mechanical Above Ceiling Passed
04/22/2024 TRSP - ROW - Final/Close-Out Passed
05/07/2024 COT - HCBU - Building Progress Passed
05/07/2024 COT - HCEL - Outdoor Lighting Passed
05/07/2024 COT - FCON - Fire - Final Passed
05/10/2024 COT - HCEL - Electrical Final Passed
05/10/2024 COT - HCME - Mechanical Final Passed
05/13/2024 COT - HCPL - Plumbing Final Passed 5/13/24: Missing faucets have been installed and are working properly.
05/14/2024 COT - HCBU - Excavation/Rebar/Zoning Passed Duplicate inspection
05/14/2024 COT - HCEL - Electrical Progress Passed Duplicate inspection
05/14/2024 COT - HCPL - Plumbing Progress Passed Duplicate inspection
05/14/2024 COT - HCBU - Building Above Ceiling Passed Duplicate inspection
05/14/2024 COT - HCPL - Rough Soil Passed Duplicate inspection
05/14/2024 COT - HCBU - Building Final Passed
05/14/2024 COT - HCBU - CofO Passed
05/14/2024 COT - HCBU - Preslab Passed Duplicate inspection
05/14/2024 COT - HCME - Mechanical Progress Passed Duplicate inspection
05/14/2024 COT - HCBU - TCO Passed 5/14/24: level 4 TCO
10/30/2024 ENGR Engineering Final Passed Landscape approved by David Roberts 10/03/2024. Last comments satisfied - Passed. JG

Documents

File Name Document Type  
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
SPECIAL INSPECTION - BOLTS_V1.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
T-B REPORT.SALAD AND GO VAIL TAB REPORT_V1.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
FINAL REPORT 2405-094 WATER STERILIZATION-2024-05-16_V1.PDF DOCUMENTS VIEW
SALAD AND GO 1184 SPECIAL INSPECTIONS FINAL_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-23-0152 1184 HOUGHTON - OLD VAIL RD - TUCSON, AZ- ASMEP_V4.PDF DOCUMENTS VIEW
23-0152 - HOUGHTON - OLD VAIL RD - TUCSON, AZ - SITE_UTILITY PLAN_V1_V2.PDF DOCUMENTS VIEW
23-0152 - HOUGHTON - OLD VAIL TUCSON, AZ - CRL_V2.PDF DOCUMENTS VIEW
23-0152 - HOUGHTON - OLD VAIL RD - TUSCON, AZ - ELECTRICAL COMCHECK_V1.PDF DOCUMENTS VIEW
23-0152 - HOUGHTON - OLD VAIL RD - TUSCON, AZ - ENVELOPE COMCHECK_V1.PDF DOCUMENTS VIEW
23-0152 - HOUGHTON - OLD VAIL RD - TUSCON, AZ - MECHANICAL COMCHECK_V1.PDF DOCUMENTS VIEW
23-0152 - HOUGHTON - OLD VAIL RD - TUSCON, AZ - STRUCTURAL CALCULATIONS_V1.PDF DOCUMENTS VIEW
23-0152 1184 HOUGHTON - OLD VAIL RD - TUCSON, AZ - SITE PLAN_V1.PDF DOCUMENTS VIEW
COMMERCIAL_SUBMITTAL_REQUIREMENTS CHECKLIST_V1.PDF DOCUMENTS VIEW
CONS-23-0152 - HOUGHTON - OLD VAIL RD - TUSCON, AZ - ASMEP SET_V1.PDF DOCUMENTS VIEW