Permit Details

Status:
Issued
Type:
Commercial Building
Address:
2524 S WILMOT RD
Address NEW:
2524 S WILMOT RD
Apply Date:
05/22/2025
Applicant:
Description:
This project is a proposed fuel center. The fuel center will include a 43' X 88' prefab fuel canopy, a 233 SF kiosk, 5 fuel dispensers and two underground storage tanks. The Site plan is approved through: TD-DEV-0724-00193 The Civil Plans are in review through: TD-DEV-0525-00139 We provided the civil plans as reference in this submittal

Permit Reviews

Permit Number - TC-COM-0525-01046
Permit Status: Issued
Permit Description: This project is a proposed fuel center. The fuel center will include a 43' X 88' prefab fuel canopy, a 233 SF kiosk, 5 fuel dispensers and two underground storage tanks. The Site plan is approved through: TD-DEV-0724-00193 The Civil Plans are in review through: TD-DEV-0525-00139 We provided the civil plans as reference in this submittal
Start Date Submittal Complete Date Status  
05/23/2025 COMMERCIAL REVIEW - FULL v.1 05/23/2025 REQUIRES RESUBMIT Review Details
12/16/2025 ADMINISTRATIVE v.2 12/16/2025 APPROVED Review Details
09/18/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.2 10/01/2025 REQUIRES RESUBMIT Review Details
05/23/2025 COMMERCIAL REVIEW - FULL v.1 05/23/2025 IN REVIEW Review Details
10/15/2025 ADMINISTRATIVE v.1 10/15/2025 REQUIRES RESUBMIT Review Details
09/17/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 09/17/2025 REQUIRES RESUBMIT Review Details
10/13/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.3 10/15/2025 APPROVED Review Details
06/23/2025 COMMERCIAL REVIEW - FULL v.3 07/14/2025 APPROVED Review Details
05/27/2025 COMMERCIAL REVIEW - FULL v.2 06/20/2025 REQUIRES RESUBMIT Review Details
06/01/2026 SPECIAL INSPECTION REVIEW v.1 06/01/2026 APPROVED Review Details
07/14/2025 RESTAMP - COMMERCIAL v.1 07/15/2025 APPROVED Review Details
06/04/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.1 06/08/2026 APPROVED Review Details

Conditions

Permit Number - TC-COM-0525-01046
Permit Status: Issued
Permit Description: This project is a proposed fuel center. The fuel center will include a 43' X 88' prefab fuel canopy, a 233 SF kiosk, 5 fuel dispensers and two underground storage tanks. The Site plan is approved through: TD-DEV-0724-00193 The Civil Plans are in review through: TD-DEV-0525-00139 We provided the civil plans as reference in this submittal
Date Description Comments
06/01/2026 AIR BALANCING REPORT IS REQUIRED.
06/10/2025 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
05/27/2025 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
05/27/2025 Plan review applications expire 180 days from date of submittal unless the permit has been issued. Permits expire 180 days after issuance or last approved inspection.
06/10/2025 SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED.
05/27/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
06/10/2025 A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit.
06/01/2026 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: Issued
Permit Number: TC-COM-0525-01046
Permite Description: This project is a proposed fuel center. The fuel center will include a 43' X 88' prefab fuel canopy, a 233 SF kiosk, 5 fuel dispensers and two underground storage tanks. The Site plan is approved through: TD-DEV-0724-00193 The Civil Plans are in review through: TD-DEV-0525-00139 We provided the civil plans as reference in this submittal
Total Outstanding Inspections - 13
Last Inspection Date Description Inspector Results Comments
03/19/2026 COT - HCPL - Sewer N/A Canceled
04/07/2026 PDSD Building Division - Sign Footing and Excavation N/A Not Applicable N.A.
04/06/2026 COT - HCBU - Preslab N/A Partial Pass 4/6/26
Partial pass; Ok to pour in canopy, still pending rebar inspection around the kiosk perimeter.
03/18/2026 COT - HCEL - Electrical Underground N/A Partial Pass Underground to kiosk and fuel piping.
03/18/2026 COT - HCEL - Grounding/Bonding N/A Partial Pass Light pole footings.
03/18/2026 COT - HCEL - Electrical Progress N/A Partial Pass Underground to kiosk and fuel piping.
05/13/2026 COT - HCBU - Building Above Ceiling N/A Not Applicable
05/13/2026 COT - HCEL - Electrical Above Ceiling N/A Not Applicable
05/13/2026 COT - HCME - Mechanical Intermediate N/A Not Applicable
05/21/2026 COT - BULD - SWG Clearance N/A Not Applicable
05/21/2026 COT - HCBU - TCO N/A Canceled
06/01/2026 COT - HCBU - Building Final N/A Partial Pass 6/1/26: OKAY TO APPLY FOR LEVEL 4 TCO. PENDING S.I.C
06/01/2026 COT - HCBU - CofO N/A Partial Pass 6/1/26: OKAY TO APPLY FOR LEVEL 4 TCO. PENDING S.I.C

Completed Inspections

Permit Status: Issued
Permit Number: TC-COM-0525-01046
Permit Description: This project is a proposed fuel center. The fuel center will include a 43' X 88' prefab fuel canopy, a 233 SF kiosk, 5 fuel dispensers and two underground storage tanks. The Site plan is approved through: TD-DEV-0724-00193 The Civil Plans are in review through: TD-DEV-0525-00139 We provided the civil plans as reference in this submittal
Total Completed Inspections - 24
Date Description Inspector Results Comments
01/23/2026 COT - HCBU - Building Progress Passed
01/23/2026 COT - HCBU - Exterior Clips/Sheathing Passed
01/23/2026 COT - HCBU - Roof Nailing Passed
03/11/2026 COT - HCPL - Plumbing Intermediate Passed
03/11/2026 COT - HCBU - Excavation/Rebar/Zoning Passed
03/19/2026 COT - HCPL - Plumbing Progress Passed
03/19/2026 COT - HCPL - Plumbing Above Ceiling Passed
03/25/2026 COT - HCPL - Sewer Passed 3/25/26 passed
03/27/2026 COT - HCPL - Rough Soil Passed Passed
04/13/2026 COT - HCBU - Preslab Passed 4/13/26
Final pour around kiosk perimeter.
04/13/2026 COT - HCEL - Electrical Underground Passed
04/17/2026 COT - HCEL - Electrical Intermediate Passed
05/06/2026 BULD - Electrical Clearance Passed meter already set
05/06/2026 COT - HCEL - Grounding/Bonding Passed Passed
05/06/2026 COT - HCEL - Electrical Progress Passed Passed
05/13/2026 COT - HCBU - Framing Passed
05/13/2026 COT - HCME - Mechanical Final Passed
05/13/2026 COT - HCPL - Plumbing Final Passed
05/13/2026 COT - HCPL - Plumbing Roof Drains Passed
05/28/2026 TRSP - ROW - Final/Close-Out Passed all connections to existing right of way completed, traffic control devices removed from site. Power wash scheduled for next week.
05/20/2026 COT - HCEL - Electrical Final Passed
05/20/2026 COT - HCEL - Outdoor Lighting Passed
05/27/2026 COT - FCON - Fire - Final Passed Ok for TCO level 4
05/27/2026 ENGR Engineering Final Passed