Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Excavation/Rebar/Zoning
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/15/2026 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Fuel canopy footings. | |
| 02/20/2026 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 2.20.26 Kiosk prefab footings Approved Also inspected and approved by state inspector due to pre fab going on footings Ok to Proceed and to pour |
|
| 02/27/2026 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 2/27/26 partial pass for north stem wall, ok to pour flooring and first lift | |
| 03/06/2026 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Partial for NW stem wall, W stem wall, and trash enclosure | |
| 03/11/2026 | COT - HCBU - Excavation/Rebar/Zoning | Passed |