Permit: TC-COM-0525-00986
Permit Details
Apply Date:
05/13/2025
Applicant:
Kelly Rehm
Description:
Parking Canopy - P1 - The NEWPORT BELVEDERE TERRACE 303.81kW Photovoltaic system will consist of 582 Silfab modules [427 530W & 155 500W] and 7 grid-tied inverters. Eighty modules will be roof-mounted, the remainder on 4 new steel parking canopies in existing paved parking areas.
Permit Reviews
Permit Number - TC-COM-0525-00986
Permit Status: Complete
Permit Description: Parking Canopy - P1 - The NEWPORT BELVEDERE TERRACE 303.81kW Photovoltaic system will consist of 582 Silfab modules [427 530W & 155 500W] and 7 grid-tied inverters. Eighty modules will be roof-mounted, the remainder on 4 new steel parking canopies in existing paved parking areas.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/09/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/12/2025 | APPROVED |
| 05/13/2025 | COMMERCIAL REVIEW - FULL v.1 | 06/10/2025 | APPROVED |
| 09/09/2025 | COMMERCIAL REVIEW - FULL REVISION v.1 | 10/06/2025 | APPROVED |
Conditions
Permit Number - TC-COM-0525-00986
Permit Status: Complete
Permit Description: Parking Canopy - P1 - The NEWPORT BELVEDERE TERRACE 303.81kW Photovoltaic system will consist of 582 Silfab modules [427 530W & 155 500W] and 7 grid-tied inverters. Eighty modules will be roof-mounted, the remainder on 4 new steel parking canopies in existing paved parking areas.
| Date | Description | Comments |
|---|---|---|
| 09/26/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0525-00986
Permite Description: Parking Canopy - P1 - The NEWPORT BELVEDERE TERRACE 303.81kW Photovoltaic system will consist of 582 Silfab modules [427 530W & 155 500W] and 7 grid-tied inverters. Eighty modules will be roof-mounted, the remainder on 4 new steel parking canopies in existing paved parking areas.
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/16/2025 | BULD - Electrical Clearance | N/A | Not Applicable | one meter sent on another permit. |
| 12/16/2025 | ENGR Engineering Final | N/A | Not Ready | 12/16/25 Canopy height not to plan. It is lower than 16'-7" dimension in revised plan. Concrete Piers are not at finished above grade with slope away from column per plan. As is columns are submerged in the side of the basin. Correct or provide letter from EOR that clearance and piers are acceptable. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0525-00986
Permit Description: Parking Canopy - P1 - The NEWPORT BELVEDERE TERRACE 303.81kW Photovoltaic system will consist of 582 Silfab modules [427 530W & 155 500W] and 7 grid-tied inverters. Eighty modules will be roof-mounted, the remainder on 4 new steel parking canopies in existing paved parking areas.
Total Completed Inspections - 7
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/16/2025 | COT - CSOL - Electrical Final Solar Project | Passed | per approved plans | |
| 12/16/2025 | COT - LCBU - Building Final | Passed | All work per approved plans. | |
| 12/16/2025 | COT - LCEL - Electrical Final | Passed | All work per approved plans. | |
| 12/16/2025 | TRSP - ROW - Final/Close-Out | Passed | ||
| 12/16/2025 | COT - CSOL - Electrical Underground Solar Project | Passed | ||
| 12/16/2025 | COT - LCBU - Building Progress | Passed | ||
| 01/22/2026 | ENGR Engineering Final | Passed |