Permit Details

Status:
Issued
Type:
Commercial Building
Address:
2920 S PARK AV
Address NEW:
2920 S PARK AV
Apply Date:
05/24/2024
Applicant:
John Mills
Description:
New commercial building for Valvoline gas station REV1: Scope of Revision Owner requested exterior and electrical changes.

Permit Reviews

Permit Number - TC-COM-0524-01012
Permit Status: Issued
Permit Description: New commercial building for Valvoline gas station REV1: Scope of Revision Owner requested exterior and electrical changes.
Start Date Submittal Complete Date Status  
08/14/2024 COMMERCIAL REVIEW - FULL v.3 08/23/2024 REQUIRES RESUBMIT Review Details
04/08/2025 COMMERCIAL REVIEW - FULL v.1 04/08/2025 APPROVED Review Details
08/28/2024 COMMERCIAL REVIEW - FULL v.4 09/26/2024 APPROVED Review Details
09/26/2024 RESTAMP - COMMERCIAL v.1 09/30/2024 APPROVED Review Details
12/10/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 12/10/2025 APPROVED Review Details
07/22/2024 COMMERCIAL REVIEW - FULL v.2 08/14/2024 REQUIRES RESUBMIT Review Details
05/15/2025 COMMERCIAL REVIEW - FULL v.1 06/09/2025 APPROVED Review Details
05/30/2024 COMMERCIAL REVIEW - FULL v.1 07/01/2024 REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TC-COM-0524-01012
Permit Status: Issued
Permit Description: New commercial building for Valvoline gas station REV1: Scope of Revision Owner requested exterior and electrical changes.
Total Outstanding Activity Conditions - 11
Date Name
06/25/2024 Please submit a separate sign permit for an signs associated with this projet.
06/26/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
06/26/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
06/26/2024 SPECIAL INSPECTION FOR SPECIAL MOMENT RESISTING STEEL FRAMES IS REQUIRED.
06/26/2024 SPECIAL INSPECTION FOR WELDING IS REQUIRED.
06/27/2024 SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED.
06/27/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
07/01/2024 AIR BALANCING REPORT IS REQUIRED.
08/21/2024 Prior to project being finalized applicant must provide an approved lot consolidation request from the Pima County Assessor's Office.
09/27/2024 SPECIAL INSPECTION FOR INSULATING COLD-FORMED STEEL DECK IS REQUIRED.
09/27/2024 SPECIAL INSPECTION FOR STEEL CONSTRUCTION IS REQUIRED.

Conditions

Permit Number - TC-COM-0524-01012
Permit Status: Issued
Permit Description: New commercial building for Valvoline gas station REV1: Scope of Revision Owner requested exterior and electrical changes.
Date Description Comments
05/30/2024 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
06/26/2024 Separate submittal to PC Industrial Wastewater Control is required for new interceptors and separators. Contact Lucinda.Hyatt@pima.gov for review and assessment of the proposed grease interceptor. Submit approval prior to issuance of building permit.
06/26/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
04/08/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
06/26/2024 A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit.
07/01/2024 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: Issued
Permit Number: TC-COM-0524-01012
Permite Description: New commercial building for Valvoline gas station REV1: Scope of Revision Owner requested exterior and electrical changes.
Total Outstanding Inspections - 12
Last Inspection Date Description Inspector Results Comments
05/15/2025 LCBU - Preslab and Floodplain Inspection N/A Partial Pass Information only for basement inspections. Will reschedule for slab rebar inspections.
08/20/2025 COT - LCBU - Framing N/A Partial Pass 8-20-25: partial pass-pending overhang together with fascia on south side of building. Okay to dry-in roof.
11/06/2025 COT - BULD - SWG Clearance N/A Not Applicable
09/09/2025 COT - LCPL - Rough Soil N/A Re-inspection required 9-9-25: coupling at main 1.5" water line has leak. Contractor will change out and reschedule both sewer/ water line when ready.
06/24/2025 COT - LCEL - Electrical Progress N/A Partial Pass 6/24/25: UFER inspected as well as sleeves put in for site power/lighting circuits.
09/18/2025 COT - LCBU - Stem Wall/Retaining Wall N/A Partial Pass Interior slab for trash enclosure; rebar in place with apron to be constructed later.
10/07/2025 COT - LCEL - Electrical Underground N/A Partial Pass Partial pass, from northeast to northwest.
06/26/2025 COT - LCBU - Excavation/Rebar/Zoning N/A Partial Pass Lower level slab with rebar reinforcement in place. Ok to place concrete in progress areas.
12/10/2025 ENGR Engineering Final N/A Partial Pass Okay for level 4 TCO
12/10/2025 COT - LCBU - Building Final N/A Partial Pass 12/10/25: OKAY FOR LEVEL 4 TCO (air balance report required for full CofO)
12/05/2025 COT - LCME - Mechanical Final N/A Not Ready 12-5-25: not ready.
12/10/2025 COT - LCEL - Electrical Final N/A Partial Pass 12/10/25: OKAY FOR LEVEL 4 TCO (air balance report required for full CofO)

Completed Inspections

Permit Status: Issued
Permit Number: TC-COM-0524-01012
Permit Description: New commercial building for Valvoline gas station REV1: Scope of Revision Owner requested exterior and electrical changes.
Total Completed Inspections - 21
Date Description Inspector Results Comments
09/17/2025 COT - LCEL - Electrical Intermediate Passed In wall electric. Ok to cover interior walls.
09/17/2025 COT - LCEL - Electrical Above Ceiling Passed
09/17/2025 COT - LCPL - Plumbing Intermediate Passed In wall plumbing. Ok to cover interior walls.
09/17/2025 COT - LCBU - Framing Passed
11/03/2025 COT - LCPL - Sewer Passed
11/06/2025 PDSD Building Division SIte Consultation Passed
11/06/2025 COT - LCBU - Preslab Passed
11/06/2025 COT - LCPL - Rough Soil Passed
11/06/2025 COT - LCEL - Electrical Progress Passed
11/06/2025 COT - LCME - Mechanical Intermediate Passed
11/13/2025 COT - LCEL - Outdoor Lighting Passed Light pole caissons (5) and cages in place; Ok to place concrete in progress areas.
11/13/2025 COT - LCPL - Yard Water Line Passed Moved domestic water line (1 1/4”) from East<side to North side .
11/18/2025 COT - LCBU - Stem Wall/Retaining Wall Passed
11/18/2025 COT - LCEL - Electrical Underground Passed
11/18/2025 COT - LCBU - Excavation/Rebar/Zoning Passed
12/02/2025 BULD - Electrical Clearance Passed New commercial service. Ok to set meter and begin,service.
12/02/2025 COT - LCEL - Grounding/Bonding Passed
12/10/2025 TRSP - ROW - Final/Close-Out Passed
12/09/2025 COT - FCON - Fire - Final Passed
12/09/2025 COT - LCME - Mechanical Final Passed
12/09/2025 COT - LCPL - Plumbing Final Passed

Documents

File Name Document Type  
COFO_TEMPORARYCOFO (SSRS).PDF DOCUMENTS VIEW
WATER-2025-12-10_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
REV NARRATIVE_V1.PDF DOCUMENTS VIEW
REV1_1_PLAN SET_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW