Permit Details

Status:
Issued
Type:
Commercial Building
Address:
2920 S PARK AV
Address NEW:
2920 S PARK AV
Apply Date:
05/24/2024
Applicant:
Jeffrey Lloyd
Description:
New commercial building for Valvoline gas station REV1: Scope of Revision Owner requested exterior and electrical changes.

Permit Reviews

Permit Number - TC-COM-0524-01012
Permit Status: Issued
Permit Description: New commercial building for Valvoline gas station REV1: Scope of Revision Owner requested exterior and electrical changes.
Start Date Submittal Complete Date Status  
08/14/2024 COMMERCIAL REVIEW - FULL v.3 08/23/2024 REQUIRES RESUBMIT Review Details
04/08/2025 COMMERCIAL REVIEW - FULL v.1 04/08/2025 APPROVED Review Details
08/28/2024 COMMERCIAL REVIEW - FULL v.4 09/26/2024 APPROVED Review Details
09/26/2024 RESTAMP - COMMERCIAL v.1 09/30/2024 APPROVED Review Details
07/22/2024 COMMERCIAL REVIEW - FULL v.2 08/14/2024 REQUIRES RESUBMIT Review Details
05/15/2025 COMMERCIAL REVIEW - FULL v.1 06/09/2025 APPROVED Review Details
05/30/2024 COMMERCIAL REVIEW - FULL v.1 07/01/2024 REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TC-COM-0524-01012
Permit Status: Issued
Permit Description: New commercial building for Valvoline gas station REV1: Scope of Revision Owner requested exterior and electrical changes.
Total Outstanding Activity Conditions - 12
Date Name
06/25/2024 Please submit a separate sign permit for an signs associated with this projet.
06/26/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
06/26/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
06/26/2024 SPECIAL INSPECTION FOR SPECIAL MOMENT RESISTING STEEL FRAMES IS REQUIRED.
06/26/2024 SPECIAL INSPECTION FOR WELDING IS REQUIRED.
06/27/2024 SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED.
06/27/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
07/01/2024 AIR BALANCING REPORT IS REQUIRED.
07/01/2024 WATER STERILIZATION REPORT IS REQUIRED.
08/21/2024 Prior to project being finalized applicant must provide an approved lot consolidation request from the Pima County Assessor's Office.
09/27/2024 SPECIAL INSPECTION FOR INSULATING COLD-FORMED STEEL DECK IS REQUIRED.
09/27/2024 SPECIAL INSPECTION FOR STEEL CONSTRUCTION IS REQUIRED.

Conditions

Permit Number - TC-COM-0524-01012
Permit Status: Issued
Permit Description: New commercial building for Valvoline gas station REV1: Scope of Revision Owner requested exterior and electrical changes.
Date Description Comments
05/30/2024 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
06/26/2024 Separate submittal to PC Industrial Wastewater Control is required for new interceptors and separators. Contact Lucinda.Hyatt@pima.gov for review and assessment of the proposed grease interceptor. Submit approval prior to issuance of building permit.
06/26/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
04/08/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
06/26/2024 A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit.

Outstanding Inspections

Permit Status: Issued
Permit Number: TC-COM-0524-01012
Permite Description: New commercial building for Valvoline gas station REV1: Scope of Revision Owner requested exterior and electrical changes.
Total Outstanding Inspections - 13
Last Inspection Date Description Inspector Results Comments
05/15/2025 LCBU - Preslab and Floodplain Inspection N/A Partial Pass Information only for basement inspections. Will reschedule for slab rebar inspections.
08/20/2025 COT - LCBU - Framing N/A Partial Pass 8-20-25: partial pass-pending overhang together with fascia on south side of building. Okay to dry-in roof.
11/06/2025 COT - BULD - SWG Clearance N/A Not Applicable
09/09/2025 COT - LCPL - Rough Soil N/A Re-inspection required 9-9-25: coupling at main 1.5" water line has leak. Contractor will change out and reschedule both sewer/ water line when ready.
06/24/2025 COT - LCEL - Electrical Progress N/A Partial Pass 6/24/25: UFER inspected as well as sleeves put in for site power/lighting circuits.
09/18/2025 COT - LCBU - Stem Wall/Retaining Wall N/A Partial Pass Interior slab for trash enclosure; rebar in place with apron to be constructed later.
10/07/2025 COT - LCEL - Electrical Underground N/A Partial Pass Partial pass, from northeast to northwest.
06/26/2025 COT - LCBU - Excavation/Rebar/Zoning N/A Partial Pass Lower level slab with rebar reinforcement in place. Ok to place concrete in progress areas.
TRSP - ROW - Final/Close-Out N/A Scheduled
COT - LCBU - Building Final N/A Scheduled
COT - LCME - Mechanical Final N/A Scheduled
COT - LCEL - Electrical Final N/A Scheduled
COT - FCON - Fire - Final N/A Not Ready Need to address the following items before CofO.
1. 15in Address Numbers on Exterior.
2. Remove exit sign above roll up door.
3. Mount extinguishers.
4. Add NFPA 704 sign to exterior door.

Completed Inspections

Permit Status: Issued
Permit Number: TC-COM-0524-01012
Permit Description: New commercial building for Valvoline gas station REV1: Scope of Revision Owner requested exterior and electrical changes.
Total Completed Inspections - 17
Date Description Inspector Results Comments
09/17/2025 COT - LCEL - Electrical Intermediate Passed In wall electric. Ok to cover interior walls.
09/17/2025 COT - LCEL - Electrical Above Ceiling Passed
09/17/2025 COT - LCPL - Plumbing Intermediate Passed In wall plumbing. Ok to cover interior walls.
09/17/2025 COT - LCBU - Framing Passed
11/03/2025 COT - LCPL - Sewer Passed
11/06/2025 PDSD Building Division SIte Consultation Passed
11/06/2025 COT - LCBU - Preslab Passed
11/06/2025 COT - LCPL - Rough Soil Passed
11/06/2025 COT - LCEL - Electrical Progress Passed
11/06/2025 COT - LCME - Mechanical Intermediate Passed
11/13/2025 COT - LCEL - Outdoor Lighting Passed Light pole caissons (5) and cages in place; Ok to place concrete in progress areas.
11/13/2025 COT - LCPL - Yard Water Line Passed Moved domestic water line (1 1/4”) from East<side to North side .
11/18/2025 COT - LCBU - Stem Wall/Retaining Wall Passed
11/18/2025 COT - LCEL - Electrical Underground Passed
11/18/2025 COT - LCBU - Excavation/Rebar/Zoning Passed
12/02/2025 BULD - Electrical Clearance Passed New commercial service. Ok to set meter and begin,service.
12/02/2025 COT - LCEL - Grounding/Bonding Passed

Scheduled Inspections

Scheduled Inspections - TC-COM-0524-01012
Status: Issued
Description: New commercial building for Valvoline gas station REV1: Scope of Revision Owner requested exterior and electrical changes.
Scheduled Date Description Entered By Entered Date
12/10/2025 TRSP - ROW - Final/Close-Out Scheduled
12/05/2025 COT - LCME - Mechanical Final Scheduled
12/05/2025 COT - LCEL - Electrical Final Scheduled
12/05/2025 COT - LCBU - Building Final Scheduled
For information about today’s scheduled inspections please refer to the PDSD Daily Inspections Dashboards (Desktop) PDSD Daily Inspections Dashboards (Mobile) .

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
REV NARRATIVE_V1.PDF DOCUMENTS VIEW
REV1_1_PLAN SET_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
SPECIAL INSPECTION CERTIFICATE 4-7-25-2025-04-07_V1.PDF DOCUMENTS VIEW