Permit: TC-COM-0524-00902
Permit Details
Status:
Issued
Type:
Commercial Building
Address:
8750 E GOLF LINKS RD
Address NEW:
8750 E GOLF LINKS RD
Apply Date:
05/09/2024
Applicant:
Kevin Barrington
Description:
(1) three story climate controlled self-storage building with site work, MEP and Structural
Permit Reviews
Permit Number - TC-COM-0524-00902
Permit Status: Issued
Permit Description: (1) three story climate controlled self-storage building with site work, MEP and Structural
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/14/2024 | COMMERCIAL REVIEW - FULL v.1 | 06/17/2024 | REQUIRES RESUBMIT |
| 08/05/2026 | COMMERCIAL REVIEW - FULL v.1 | 09/02/2026 | REQUIRES RESUBMIT |
| 10/19/2026 | COMMERCIAL REVIEW - FULL v.2 | N/A | IN REVIEW |
| 07/31/2024 | RESTAMP - COMMERCIAL v.1 | 08/06/2024 | APPROVED |
| 07/08/2025 | RESTAMP - COMMERCIAL v.1 | 07/11/2025 | APPROVED |
| 10/19/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/20/2026 | APPROVED |
| 06/26/2024 | COMMERCIAL REVIEW - FULL v.2 | 07/31/2024 | APPROVED |
| 06/16/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/17/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-COM-0524-00902
Permit Status: Issued
Permit Description: (1) three story climate controlled self-storage building with site work, MEP and Structural
Total Outstanding Activity Conditions - 8
| Date | Name |
|---|---|
| 07/05/2024 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. |
| 07/05/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
| 07/05/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 07/05/2024 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. |
| 07/05/2024 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. |
| 07/05/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
| 07/05/2024 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. |
| 07/05/2024 | SPECIAL INSPECTION FOR WELDING IS REQUIRED. |
Conditions
Permit Number - TC-COM-0524-00902
Permit Status: Issued
Permit Description: (1) three story climate controlled self-storage building with site work, MEP and Structural
| Date | Description | Comments |
|---|---|---|
| 05/14/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 05/14/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 07/05/2024 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. | |
| 10/13/2026 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-COM-0524-00902
Permite Description: (1) three story climate controlled self-storage building with site work, MEP and Structural
Total Outstanding Inspections - 21
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/21/2025 | COT - HCBU - Framing | N/A | Not Ready | Wanted pre-grout |
| 04/09/2026 | COT - HCPL - Sewer | N/A | Partial Pass | Main tap |
| 12/03/2025 | COT - HCBU - Exterior Clips/Sheathing | N/A | Partial Pass | |
| 08/11/2025 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | 8-11-25: reinforcement on the exterior continuous footers stemming from detail's-WF1, MW2, & 4-C2/F2 columns verified per plans. Okay for concrete placement at progress areas. |
| 08/07/2025 | COT - HCEL - Electrical Underground | N/A | Partial Pass | Conduits at electric room. |
| 08/18/2025 | BULD - Electrical Clearance | N/A | Partial Pass | 8-18-25: okay to energize panel-temp power(TMPP)clearance issued to TEP. |
| 08/28/2025 | COT - HCEL - Grounding/Bonding | N/A | Partial Pass | Ufer connection to rebar. |
| 05/07/2026 | COT - HCPL - Plumbing Intermediate | N/A | Re-inspection required | Provide test for water piping |
| 09/01/2026 | COT - HCME - Mechanical Underground | N/A | Not Applicable | |
| 04/16/2026 | COT - HCBU - Sustainability | N/A | Partial Pass | Starting dens glass |
| 10/14/2026 | COT - HCME - Mechanical Final | N/A | Re-inspection required | 10/14/26: Heat-kit has to be marked on label if installed to verify proper fuses. (Only walked 1st floor) |
| 07/24/2025 | COT - HCEL - Electrical Intermediate | N/A | Re-inspection required | Pre con meeting. 7/24/2025 |
| 10/14/2026 | COT - FCON - Alarm - Final | N/A | Partial Pass | Tested FACP Smoke, Pull Station, Water Flow and Tamper. All reported to panel and central station. Awaiting elevator test completion to verify elevator recall. |
| COT - FCON - Sprinkler - Final | N/A | Not Ready | Underground fire line permit shall be applied for. | |
| 09/01/2026 | COT - HCME - Mechanical Intermediate | N/A | Canceled | |
| 10/14/2026 | COT - FCON - Fire - Final | N/A | Partial Pass | Tested FACP Smoke, Pull Station, Water Flow and Tamper. All reported to panel and central station. Awaiting elevator test completion to verify elevator recall. Ok for Level 3 TCO for First Floor. |
| 10/14/2026 | COT - HCPL - Plumbing Final | N/A | Re-inspection required | 10/14/26: Heat-kit has to be marked on label if installed to verify proper fuses. (Only walked 1st floor), ADA requirements at break room (receptacles must be surface mounted to meet reach range), ada signage required at bathrooms, lobby area counter space for ADA required. (1st floor walked only) |
| 10/21/2026 | ENGR Engineering Final | N/A | Partial Pass | Okay to apply for Level 3 TCO - 1st Floor Only |
| 10/22/2026 | COT - HCBU - Building Final | N/A | Partial Pass | 10.22.26-2nd floor walked; okay for level 3 TCO please block off elevators until certified. |
| 10/23/2026 | COT - HCEL - Electrical Final | N/A | Partial Pass | 10/23/26 3rd floor walked, okay for level 3 TCO, Elevators must remain blocked off until certified. |
| 10/30/2026 | COT - HCBU - CofO | N/A | Canceled |
Completed Inspections
Permit Status: Issued
Permit Number: TC-COM-0524-00902
Permit Description: (1) three story climate controlled self-storage building with site work, MEP and Structural
Total Completed Inspections - 29
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/29/2025 | COT - HCPL - Rough Soil | Passed | Underground plumbing per plan, ok to backfill | |
| 12/12/2025 | COT - HCBU - Masonry Pregrout | Passed | 12/12/25 complete | |
| 02/26/2026 | COT - HCBU - Preslab | Passed | ||
| 04/09/2026 | COT - HCBU - Framing | Passed | Levels Two and Three | |
| 04/14/2026 | COT - HCPL - Sewer | Passed | ||
| 04/17/2026 | COT - HCPL - Yard Water Line | Passed | ||
| 04/29/2026 | COT - HCBU - Roof Nailing | Passed | Passed 4/28/26 | |
| 05/07/2026 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
| 05/11/2026 | COT - HCPL - Plumbing Progress | Passed | Passed 5/11/26, pressure tested | |
| 05/12/2026 | COT - HCBU - Excavation/Rebar/Zoning | Passed | Trash enclosure; instructed contractor to schedule Engineering inspection for location. | |
| 05/13/2026 | COT - HCEL - Electrical Underground | Passed | ||
| 06/10/2026 | BULD - Electrical Clearance | Passed | 6.10.26 TEP CLEARANCE: ECO |
|
| 08/14/2026 | COT - HCBU - Building Above Ceiling | Passed | ||
| 08/13/2026 | COT - HCEL - Electrical Progress | Passed | ||
| 08/14/2026 | COT - HCBU - Building Progress | Passed | ||
| 08/14/2026 | COT - HCME - Mechanical Above Ceiling | Passed | ||
| 08/14/2026 | COT - HCEL - Grounding/Bonding | Passed | ||
| 08/14/2026 | COT - HCPL - Plumbing Intermediate | Passed | ||
| 08/27/2026 | COT - HCME - Mechanical Progress | Passed | Duct sealing. | |
| 10/13/2026 | COT - HCPL - Backwater Valve | Passed | ||
| 10/14/2026 | COT - HCBU - Sustainability | Passed | ||
| 10/14/2026 | COT - HCEL - Electrical Intermediate | Passed | ||
| 10/14/2026 | COT - HCEL - Electrical Above Ceiling | Passed | ||
| 10/14/2026 | TRSP - ROW - Notice of Completion | Passed | Work completed outside of the city right of way | |
| 10/14/2026 | COT - HCME - Mechanical Intermediate | Passed | ||
| 10/14/2026 | COT - HCBU - Firewall/Fire Barrier/Firestop | Passed | ||
| 10/14/2026 | COT - HCEL - Outdoor Lighting | Passed | ||
| 10/14/2026 | COT - HCPL - Plumbing Roof Drains | Passed | ||
| 10/14/2026 | COT - HCPL - Plumbing Above Ceiling | Passed |