Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Stop Work Order
Type:
Commercial Building
Apply Date:
04/21/2025
Applicant:
Brian Liwski
Description:
SCOPE OF WORK INCLUDES AN ~1800 SF BUILD OUT IN AN EXISTING SHELL WAREHOUSE BUILDING. NO MODIFICATIONS PROPOSED TO EFFECT EXITING OR THE EXISTING BUILDING ENVELOPE. SCOPE OF WORK IS LIMITED TO NEW LIGHTING, HVAC AND RESTROOMS AS REQUIRED FOR BUILDING CODE AND OCCUPANCY OF SPACE. ASSOCIATED MECHANICAL, PLUMBING AND ELECTRICAL WORK INCLUDED WITH THIS CONSTRUCTION DOCUMENT SET.

Permit Reviews

Permit Number - TC-COM-0425-00797
Permit Status: Stop work order
Permit Description: SCOPE OF WORK INCLUDES AN ~1800 SF BUILD OUT IN AN EXISTING SHELL WAREHOUSE BUILDING. NO MODIFICATIONS PROPOSED TO EFFECT EXITING OR THE EXISTING BUILDING ENVELOPE. SCOPE OF WORK IS LIMITED TO NEW LIGHTING, HVAC AND RESTROOMS AS REQUIRED FOR BUILDING CODE AND OCCUPANCY OF SPACE. ASSOCIATED MECHANICAL, PLUMBING AND ELECTRICAL WORK INCLUDED WITH THIS CONSTRUCTION DOCUMENT SET.
Start Date Submittal Complete Date Status  
06/25/2025 RESTAMP - COMMERCIAL v.1 06/26/2025 REQUIRES RESUBMIT Review Details
04/23/2025 COMMERCIAL REVIEW - FULL v.1 05/19/2025 REQUIRES RESUBMIT Review Details
06/16/2025 COMMERCIAL REVIEW - FULL v.3 06/25/2025 APPROVED Review Details
07/01/2025 COMMERCIAL REVIEW - LIMITED v.1 07/17/2025 APPROVED Review Details
05/19/2025 COMMERCIAL REVIEW - FULL v.2 05/19/2025 REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TC-COM-0425-00797
Permit Status: Stop work order
Permit Description: SCOPE OF WORK INCLUDES AN ~1800 SF BUILD OUT IN AN EXISTING SHELL WAREHOUSE BUILDING. NO MODIFICATIONS PROPOSED TO EFFECT EXITING OR THE EXISTING BUILDING ENVELOPE. SCOPE OF WORK IS LIMITED TO NEW LIGHTING, HVAC AND RESTROOMS AS REQUIRED FOR BUILDING CODE AND OCCUPANCY OF SPACE. ASSOCIATED MECHANICAL, PLUMBING AND ELECTRICAL WORK INCLUDED WITH THIS CONSTRUCTION DOCUMENT SET.
Total Outstanding Activity Conditions - 3
Date Name
11/07/2025 A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit.
11/07/2025 SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED.
11/07/2025 SPECIAL INSPECTION FOR WELDING IS REQUIRED.

Conditions

Permit Number - TC-COM-0425-00797
Permit Status: Stop work order
Permit Description: SCOPE OF WORK INCLUDES AN ~1800 SF BUILD OUT IN AN EXISTING SHELL WAREHOUSE BUILDING. NO MODIFICATIONS PROPOSED TO EFFECT EXITING OR THE EXISTING BUILDING ENVELOPE. SCOPE OF WORK IS LIMITED TO NEW LIGHTING, HVAC AND RESTROOMS AS REQUIRED FOR BUILDING CODE AND OCCUPANCY OF SPACE. ASSOCIATED MECHANICAL, PLUMBING AND ELECTRICAL WORK INCLUDED WITH THIS CONSTRUCTION DOCUMENT SET.
Date Description Comments
07/29/2025 The Contractor you have added to your permit cannot be verified. Please contact staff to have the ROC number added to the account.
04/23/2025 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
07/01/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.

Outstanding Inspections

Permit Status: Stop Work Order
Permit Number: TC-COM-0425-00797
Permite Description: SCOPE OF WORK INCLUDES AN ~1800 SF BUILD OUT IN AN EXISTING SHELL WAREHOUSE BUILDING. NO MODIFICATIONS PROPOSED TO EFFECT EXITING OR THE EXISTING BUILDING ENVELOPE. SCOPE OF WORK IS LIMITED TO NEW LIGHTING, HVAC AND RESTROOMS AS REQUIRED FOR BUILDING CODE AND OCCUPANCY OF SPACE. ASSOCIATED MECHANICAL, PLUMBING AND ELECTRICAL WORK INCLUDED WITH THIS CONSTRUCTION DOCUMENT SET.
Total Outstanding Inspections - 7
Last Inspection Date Description Inspector Results Comments
11/10/2025 COT - BULD - SWG Clearance N/A Not Applicable 11-10-25: not applicable
COT - FCON - Sprinkler - Final N/A Not Ready
11/12/2025 ENGR Engineering Final N/A Not Ready 11/12/25
Sidewalk scupper to the west of bldg. is not built to the PAG Standard Detail spec.
The ADA parking to the east of the bldg. is over 2% in the east half of both spaces and the access aisle. These need to be rebuilt.
11/10/2025 COT - HCBU - Building Final N/A Re-inspection required 11-10-25: add R3 insulation to hot leg of water heater, lower all mirrors at restrooms to 40" to reflective surface, label junction boxes at warehouse side, missing ADA signs at restrooms (braile), missing electric over underneath sink at kitchen, warehouse bathroom fans not working, adjust min doors to 5 pounds of pressure.
11/24/2025 COT - HCBU - CofO N/A Partial Pass 11-24-25: partial pass-okay for Level 1 TCO. Pending conditions, fire, and engineering inspections.
COT - FCON - Alarm - Final N/A Requested
COT - FCON - Fire - Final N/A Requested

Completed Inspections

Permit Status: Stop Work Order
Permit Number: TC-COM-0425-00797
Permit Description: SCOPE OF WORK INCLUDES AN ~1800 SF BUILD OUT IN AN EXISTING SHELL WAREHOUSE BUILDING. NO MODIFICATIONS PROPOSED TO EFFECT EXITING OR THE EXISTING BUILDING ENVELOPE. SCOPE OF WORK IS LIMITED TO NEW LIGHTING, HVAC AND RESTROOMS AS REQUIRED FOR BUILDING CODE AND OCCUPANCY OF SPACE. ASSOCIATED MECHANICAL, PLUMBING AND ELECTRICAL WORK INCLUDED WITH THIS CONSTRUCTION DOCUMENT SET.
Total Completed Inspections - 18
Date Description Inspector Results Comments
10/21/2025 BULD - Electrical Clearance Passed 10-21-25: okay to energize SES-B on Building 3. ECO clearance issued to TEP.
10/30/2025 COT - HCBU - Building Above Ceiling Passed
10/30/2025 COT - HCBU - Building Progress Passed
10/30/2025 COT - HCBU - Framing Passed
10/30/2025 COT - HCEL - Electrical Above Ceiling Passed
10/30/2025 COT - HCEL - Electrical Intermediate Passed
10/30/2025 COT - HCEL - Electrical Progress Passed
10/30/2025 COT - HCME - Mechanical Above Ceiling Passed
10/30/2025 COT - HCME - Mechanical Intermediate Passed
10/30/2025 COT - HCME - Mechanical Progress Passed
10/30/2025 COT - HCPL - Plumbing Above Ceiling Passed
10/30/2025 COT - HCPL - Plumbing Intermediate Passed
10/30/2025 COT - HCPL - Plumbing Progress Passed
11/10/2025 TRSP - ROW - Final/Close-Out Passed All work within the right of way has been competed
11/24/2025 COT - HCBU - Building Final Passed 11-24-25:Building final approved.
Note: See pending conditions.
11/24/2025 COT - HCEL - Electrical Final Passed 11-24-25: corrections made. Electric final approved.
11/24/2025 COT - HCME - Mechanical Final Passed 11-24-25: Mechanical final approved.
11/24/2025 COT - HCPL - Plumbing Final Passed 11-24-25: corrections made. Plumbing final approved.

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-25-100 I-10 SPEC- BLDG 3- DELTA 1- SEALED PLANS 06-27-25_V3.PDF DOCUMENTS VIEW
25-0341 (25-0341.1) I-10 SPEC- BLDG 3- DELTA 1- SEALED STRUCT'L CALCS 06-09-25_V2.PDF DOCUMENTS VIEW