Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
04/14/2025
Applicant:
Amy Cotner
Description:
Speculative TI buildout in unoccupied Shell under separate permit.

Permit Reviews

Permit Number - TC-COM-0425-00742
Permit Status: Complete
Permit Description: Speculative TI buildout in unoccupied Shell under separate permit.
Start Date Submittal Complete Date Status  
04/16/2025 COMMERCIAL REVIEW - FULL v.1 05/08/2025 REQUIRES RESUBMIT Review Details
06/06/2025 COMMERCIAL REVIEW - FULL v.2 06/11/2025 APPROVED Review Details
05/04/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.1 05/11/2026 APPROVED Review Details
03/24/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.1 04/06/2026 APPROVED Review Details

Conditions

Permit Number - TC-COM-0425-00742
Permit Status: Complete
Permit Description: Speculative TI buildout in unoccupied Shell under separate permit.
Date Description Comments
04/16/2025 BLDG 2 UNIT 2130 Needs to be added to cover sheet as part of the address to reflect this permit application.
04/16/2025 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
04/16/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-0425-00742
Permite Description: Speculative TI buildout in unoccupied Shell under separate permit.
Total Outstanding Inspections - 5
Last Inspection Date Description Inspector Results Comments
11/13/2025 COT - HCBU - Framing N/A Partial Pass 11-13-25: partial pass on metal framing for suite 2130-pending interior framing. Okay to one side with drywall.
11/13/2025 COT - HCPL - Plumbing Progress N/A Partial Pass 11-13-25: partial pass on in wall plumbing.
12/01/2025 COT - HCME - Mechanical Progress N/A Partial Pass 12-1-25: verified mechanical above ceiling pookie joints. Okay to continue with construction at progress areas.
04/09/2026 COT - BULD - SWG Clearance N/A Not Applicable 4-9-26: not applicable.
12/04/2025 COT - HCBU - Building Progress N/A Partial Pass 12-4-25: drywall screw inspection for office on warehouse side approved. Okay to tape & texture progress areas.

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-0425-00742
Permit Description: Speculative TI buildout in unoccupied Shell under separate permit.
Total Completed Inspections - 23
Date Description Inspector Results Comments
03/04/2026 COT - HCBU - Framing Passed 3-4-26: framing approved.
03/04/2026 COT - HCEL - Electrical Intermediate Passed 3-4-26: MEP's approved.
03/04/2026 COT - HCME - Mechanical Intermediate Passed 3-4-26: MEP's /above ceiling approved.
03/04/2026 COT - HCME - Mechanical Above Ceiling Passed 3-4-26: MEP's approved.
03/04/2026 COT - HCPL - Plumbing Above Ceiling Passed 3-4-26: MEP's /above ceiling approved.
03/04/2026 COT - HCPL - Plumbing Intermediate Passed 3-4-26: MEP's approved.
03/23/2026 BULD - Electrical Clearance Passed 3-23-26: okay to energize suite 2130-panel#2. ECO clearance issued to TEP.
03/24/2026 COT - HCPL - Plumbing Progress Passed 3-24-26: plumbing progress approved.
03/24/2026 COT - HCME - Mechanical Progress Passed 3-24-26: approved.
03/24/2026 COT - HCEL - Electrical Above Ceiling Passed 3-24-26: electrical above ceiling approved.
03/24/2026 COT - HCEL - Electrical Progress Passed 3-24-26: electrical progress approved.
04/20/2026 COT - HCBU - Building Above Ceiling Passed 4-20-26: approved.
04/20/2026 COT - FCON - Fire - Final Passed
04/20/2026 ENGR Engineering Final Passed Site is complete in accordance with approved plans.
04/20/2026 TRSP - ROW - Final/Close-Out Passed
04/20/2026 COT - FCON - Alarm - Final Passed
04/20/2026 COT - HCME - Mechanical Final Passed 4-20-26: approved.
04/20/2026 COT - HCBU - Building Progress Passed 4-20-26: approved.
04/23/2026 COT - HCEL - Electrical Final Passed 4-23-26: electrical final approved.
04/23/2026 COT - HCPL - Plumbing Final Passed 4-23-26: plumbing final approved.
04/23/2026 COT - FCON - Sprinkler - Final Passed
05/07/2026 COT - HCBU - CofO Passed 5-7-26: building final approved & all conditions have been satisfied. Okay to apply for C of O.
05/07/2026 COT - HCBU - Building Final Passed 5-7-26: building final approved & all conditions have been satisfied. Okay to apply for C of O.

Documents

File Name Document Type  
COFO_FINALCOFO_COMMERCIAL (SSRS).PDF DOCUMENTS VIEW
26C0512_1 TURNER 03 20 2026 1235-2026-04-28_V1.PDF DOCUMENTS VIEW
DREXEL COMMERCE CENTER SUITE 2130 - TAB REPORT_V1.PDF DOCUMENTS VIEW
DREXEL TORQUE03232026_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
20240616 BLDG 2 PLAN CHECK COMMENTS - ROUND 1_V1.PDF DOCUMENTS VIEW
COMCHECK-SUITE 2130 - VLMK SIGNED_V2.PDF DOCUMENTS VIEW
CONS-DREXEL CC TI BUILDING 2 - SUITE 2130_V2.PDF DOCUMENTS VIEW
DREXEL CC TI STRUCTURAL CALCULATIONS_SEALED_V2.PDF DOCUMENTS VIEW