Inspection Status: Passed
Inspection History: COT - HCBU - Building Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 04/20/2026 |
COT - HCBU - Building Progress |
|
Passed |
4-20-26: approved. |
| 10/07/2025 |
COT - HCBU - Building Progress |
|
Partial Pass |
Underground plumbing for restroom and break room. |
| 11/03/2025 |
COT - HCBU - Building Progress |
|
Partial Pass |
11-3-25: drywall nailing inspection for demising wall at north side of suite 2130 approved. Okay to tape & texture progress areas. |
| 11/13/2025 |
COT - HCBU - Building Progress |
|
Partial Pass |
11-13-25: partial pass of north & south drywall inspection. Approximately 10' near roof deck not complete. Will check prior to tape & texture. Rest of walls are okay for continue with construction. |
| 12/01/2025 |
COT - HCBU - Building Progress |
|
Not Ready |
12-1-25: not ready. |
| 12/04/2025 |
COT - HCBU - Building Progress |
|
Partial Pass |
12-4-25: drywall screw inspection for office on warehouse side approved. Okay to tape & texture progress areas. |