Inspection History Details
Inspection Status: Re-inspection required
Inspection History: COT - HCBU - Building Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| COT - HCBU - Building Final | Re-inspection required | 4-20-26: install ADA restroom signs-must contain braille. Adjust door pressure at restrooms to 5 pounds, add R3 insulation to hot water side at water heater, provide subpanel schedule. Note: Roof drains covers will be verified at TCO Inspection. Covers had been installed but were stolen after the shell finals occurred. |
||
| 04/23/2026 | COT - HCBU - Building Final | Partial Pass | 4-23-26: Pending ADA restroom signs. | |
| 05/07/2026 | COT - HCBU - Building Final | Passed | 5-7-26: building final approved & all conditions have been satisfied. Okay to apply for C of O. |