Permit: TC-COM-0424-00645
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
14025 W MILE WIDE RD
Address NEW:
14025 W MILE WIDE RD
Apply Date:
04/10/2024
Applicant:
Cary Broschat
Description:
Install ground mount solar tracker project (8.75 MW DC) 8751.06 KW dc 7248 KWac
Permit Reviews
Permit Number - TC-COM-0424-00645
Permit Status: Complete
Permit Description: Install ground mount solar tracker project (8.75 MW DC)
8751.06 KW dc
7248 KWac
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/10/2024 | COMMERCIAL REVIEW - FULL v.1 | 04/10/2024 | REQUIRES RESUBMIT |
| 04/16/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/17/2025 | APPROVED |
| 05/06/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/06/2024 | APPROVED |
| 04/12/2024 | COMMERCIAL REVIEW - FULL v.2 | 05/02/2024 | APPROVED |
Conditions
Permit Number - TC-COM-0424-00645
Permit Status: Complete
Permit Description: Install ground mount solar tracker project (8.75 MW DC)
8751.06 KW dc
7248 KWac
| Date | Description | Comments |
|---|---|---|
| 05/01/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 05/02/2024 | SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED. | |
| 05/01/2024 | SPECIAL INSPECTION FOR PILING, DRILLED PIERS AND CAISSONS IS REQUIRED. | |
| 05/02/2024 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. | |
| 05/02/2024 | SPECIAL INSPECTION FOR SPECIAL MOMENT RESISTING STEEL FRAMES IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0424-00645
Permite Description: Install ground mount solar tracker project (8.75 MW DC)
8751.06 KW dc
7248 KWac
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/27/2024 | COT - CSOL - Outdoor Lighting Solar Project | N/A | Not Applicable | |
| 11/01/2024 | COT - CSOL - Electrical Progress Solar Project | N/A | Not Applicable | |
| 08/02/2024 | COT - CSOL - Electrical Underground Solar Project | N/A | Partial Pass | Partial approval for the direct buried conductors at Inverter #50 - #49, and at Combiner #13, okay to shade fill progress areas |
| 08/02/2024 | COT - CSOL - Grounding/Bonding Solar Project | N/A | Partial Pass | Partial approval for the ground rods at Inverter #50 - #49, and at Combiner #13, okay to shade fill progress areas |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0424-00645
Permit Description: Install ground mount solar tracker project (8.75 MW DC)
8751.06 KW dc
7248 KWac
Total Completed Inspections - 9
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/27/2024 | TRSP - ROW - Notice of Completion | Passed | it’s not in city jurisdiction | |
| 11/01/2024 | COT - CSOL - Electrical Intermediate Solar Project | Passed | Approved electrical rack | |
| 12/12/2024 | COT - CSOL - Electrical Underground Solar Project | Passed | Approved and complete underground inspections for direct buried conductors, around site and back to SES location , okay to backfill all areas | |
| 03/24/2025 | COT - CSOL - Grounding/Bonding Solar Project | Passed | ||
| 03/24/2025 | COT - CSOL - Electrical Final Solar Project | Passed | Approved solar - DGC Clearance to TRICO is required for the solar meter | |
| 03/24/2025 | COT - LCBU - Building Final | Passed | ||
| 03/24/2025 | COT - LCEL - Electrical Final | Passed | ||
| 03/24/2025 | ENGR Engineering Final | Passed | ||
| 03/24/2025 | BULD - Electrical Clearance | Passed | Approved solar - DGC Clearance to TRICO is required for the solar meter |