Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - CSOL - Electrical Underground Solar Project
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/20/2024 | COT - CSOL - Electrical Underground Solar Project | Partial Pass | Partial approval for the direct burial cables at Inverter #1 - #4 and Combiner #1, okay to shade fill progress areas | |
| 06/24/2024 | COT - CSOL - Electrical Underground Solar Project | Partial Pass | Partial approval for the direct burial cables at Inverter #5- #8 and Combiner #2, okay to shade fill progress areas | |
| 06/28/2024 | COT - CSOL - Electrical Underground Solar Project | Partial Pass | Underground conduits for Inverters 9 - 12 and Combiner 3 ok to backfill. | |
| 07/03/2024 | COT - CSOL - Electrical Underground Solar Project | Partial Pass | Partial approval for the direct buried conductors at Inverter #13- #16 and Combiner #4, okay to shade fill progress areas | |
| 07/09/2024 | COT - CSOL - Electrical Underground Solar Project | Partial Pass | Partial approval for the direct buried conductors at Inverter #21- #26 and Combiner #6 and #7, okay to shade fill progress areas | |
| 07/12/2024 | COT - CSOL - Electrical Underground Solar Project | Partial Pass | Partial approval for the direct buried conductors at Inverter #17- #20 and Combiner #5, okay to shade fill progress areas | |
| 07/16/2024 | COT - CSOL - Electrical Underground Solar Project | Partial Pass | Partial approval for the direct buried conductors at motor #2, #3 to the gear rack, also motor #4, #5, and #6 to the gear rack, okay to shade fill progress areas. Partial approval for underground conduit risers at transformer T01 and T02 locations, okay to backfill progress areas | |
| 07/19/2024 | COT - CSOL - Electrical Underground Solar Project | Partial Pass | Partial for the risers at the equipment rack, okay to backfill progress areas | |
| 07/23/2024 | COT - CSOL - Electrical Underground Solar Project | Partial Pass | Partial approval for the direct buried conductors at Inverter #51 - #58, and at Combiner #14 and #15, and at Motors #5 and #6, okay to shade fill progress areas | |
| 07/26/2024 | COT - CSOL - Electrical Underground Solar Project | Canceled | ||
| 08/02/2024 | COT - CSOL - Electrical Underground Solar Project | Partial Pass | Partial approval for the direct buried conductors at Inverter #50 - #49, and at Combiner #13, okay to shade fill progress areas | |
| 08/06/2024 | COT - CSOL - Electrical Underground Solar Project | Partial Pass | Partial approval for the direct buried conductors at Transformer #4 to Inverter #43 - #48, and at Combiner #12, okay to shade fill progress areas | |
| 08/08/2024 | COT - CSOL - Electrical Underground Solar Project | Partial Pass | Partial approval for the direct buried conductors at Inverters #39 - #42, and at Combiner panel #11, and to Motor control #4, okay to shade fill progress areas | |
| 08/16/2024 | COT - CSOL - Electrical Underground Solar Project | Partial Pass | Partial approval for the direct buried conductors at Inverters #35 - #38 from Transformer #3 and at Combiner panel #10, okay to shade fill progress areas | |
| 08/22/2024 | COT - CSOL - Electrical Underground Solar Project | Partial Pass | Partial approval for the direct buried conductors at Inverters #31- #34, and at Combiner panel #9, okay to shade fill progress areas | |
| 08/28/2024 | COT - CSOL - Electrical Underground Solar Project | Partial Pass | Partial approval for the underground direct buried conductors at Inverters #27- #30, and at Combiner panel #8, okay to shade fill progress areas | |
| 10/31/2024 | COT - CSOL - Electrical Underground Solar Project | Partial Pass | Partial approval for underground conduits from Combiner panel #1 to Transformer #2, okay to shade fill progress areas | |
| 11/01/2024 | COT - CSOL - Electrical Underground Solar Project | Partial Pass | Partial approval for underground conduits from Transformer #1 to Transformer #4, okay to shade fill progress areas | |
| 11/07/2024 | COT - CSOL - Electrical Underground Solar Project | Partial Pass | Partial approval for underground direct buried conductors from Transformer #1 to Transformer #2 , okay to shade fill progress areas | |
| 11/12/2024 | COT - CSOL - Electrical Underground Solar Project | Partial Pass | Partial approval for the direct buried conductors starting at Transformer #1 to Inverters #19-#26 and at Combiner panels #5, #6, #7, #16, okay to shade fill progress areas Also, Partial approval for the direct buried conductors starting at Transformer #3 to Inverters #27-#33 and at Combiner panels #8, #9, okay to shade fill progress areas |
|
| 11/14/2024 | COT - CSOL - Electrical Underground Solar Project | Partial Pass | Partial approval for underground direct buried conductors from Combiner panel #12 to Transformer #4, okay to shade fill progress areas | |
| 11/20/2024 | COT - CSOL - Electrical Underground Solar Project | Partial Pass | Partial approval for underground direct buried conductors from Combiner panel #11 to Transformer #3 also from Transformer #3 to Transformer #4, okay to shade fill progress areas | |
| 11/25/2024 | COT - CSOL - Electrical Underground Solar Project | Partial Pass | Partial approval for underground direct buried conductors from Combiner panel #14 and #15 to Transformer #4, also from Transformer #2 to Combiner panel #4, also conduits and risers the medium voltage AC gear location. Okay for concrete placement and shade fill all progress areas | |
| 12/12/2024 | COT - CSOL - Electrical Underground Solar Project | Passed | Approved and complete underground inspections for direct buried conductors, around site and back to SES location , okay to backfill all areas |