Permit: TC-COM-0424-00645

Parcel: 21114007C

Inspection Status: Passed

Inspection History: COT - CSOL - Grounding/Bonding Solar Project

Date Description Inspector Results Comments
03/24/2025 COT - CSOL - Grounding/Bonding Solar Project Passed
06/20/2024 COT - CSOL - Grounding/Bonding Solar Project Partial Pass Partial approval for the grounding at Inverter #1 - #4 and Combiner #1, okay to backfill progress areas
06/24/2024 COT - CSOL - Grounding/Bonding Solar Project Partial Pass Partial approval for the grounding at Inverter #5- #8 and Combiner #2, okay to shade fill progress areas
06/28/2024 COT - CSOL - Grounding/Bonding Solar Project Partial Pass Partial pass for grounding present at Inverters 9 - 12 and Combiner3
07/03/2024 COT - CSOL - Grounding/Bonding Solar Project Partial Pass Partial approval for the ground rods at Inverter #13- #16 and Combiner #4, okay to shade fill progress areas
07/09/2024 COT - CSOL - Grounding/Bonding Solar Project Partial Pass Partial approval for the ground rods at Inverter #21- #26 and Combiner #6 and #7, okay to shade fill progress areas
07/12/2024 COT - CSOL - Grounding/Bonding Solar Project Partial Pass Partial approval for the ground rods at Inverter #17- #20and Combiner #5, okay to shade fill progress areas
07/16/2024 COT - CSOL - Grounding/Bonding Solar Project Partial Pass Partial approval for ground rods and grounding at transformer T01 and T02 locations, okay to backfill progress areas
07/23/2024 COT - CSOL - Grounding/Bonding Solar Project Partial Pass Partial approval for the ground rods at Inverter #51 - #58, and at Combiner #14 and #15, okay to shade fill progress areas
07/26/2024 COT - CSOL - Grounding/Bonding Solar Project Canceled
08/02/2024 COT - CSOL - Grounding/Bonding Solar Project Partial Pass Partial approval for the ground rods at Inverter #50 - #49, and at Combiner #13, okay to shade fill progress areas
08/06/2024 COT - CSOL - Grounding/Bonding Solar Project Partial Pass Partial approval for the ground rods at Transformer #4 , Inverters #43 - #48, and at Combiner #12, okay to shade fill progress areas
08/08/2024 COT - CSOL - Grounding/Bonding Solar Project Partial Pass Partial approval for the ground rods at Inverters #39 - #42, and at Combiner panel #11, okay to shade fill progress areas
08/16/2024 COT - CSOL - Grounding/Bonding Solar Project Passed Partial approval for the ground rods at Inverters #35 - #38 from Transformer #3 and at Combiner panel #10, okay to shade fill progress areas
08/22/2024 COT - CSOL - Grounding/Bonding Solar Project Partial Pass Partial approval for the ground rods at Inverters #31- #34, and at Combiner panel #9, okay to shade fill progress areas
08/28/2024 COT - CSOL - Grounding/Bonding Solar Project Partial Pass Partial approval for the ground rods at Inverters #27- #30, and at Combiner panel #8, okay to shade fill progress areas