| 03/24/2025 |
COT - CSOL - Grounding/Bonding Solar Project |
|
Passed |
|
| 06/20/2024 |
COT - CSOL - Grounding/Bonding Solar Project |
|
Partial Pass |
Partial approval for the grounding at Inverter #1 - #4 and Combiner #1, okay to backfill progress areas |
| 06/24/2024 |
COT - CSOL - Grounding/Bonding Solar Project |
|
Partial Pass |
Partial approval for the grounding at Inverter #5- #8 and Combiner #2, okay to shade fill progress areas |
| 06/28/2024 |
COT - CSOL - Grounding/Bonding Solar Project |
|
Partial Pass |
Partial pass for grounding present at Inverters 9 - 12 and Combiner3 |
| 07/03/2024 |
COT - CSOL - Grounding/Bonding Solar Project |
|
Partial Pass |
Partial approval for the ground rods at Inverter #13- #16 and Combiner #4, okay to shade fill progress areas |
| 07/09/2024 |
COT - CSOL - Grounding/Bonding Solar Project |
|
Partial Pass |
Partial approval for the ground rods at Inverter #21- #26 and Combiner #6 and #7, okay to shade fill progress areas |
| 07/12/2024 |
COT - CSOL - Grounding/Bonding Solar Project |
|
Partial Pass |
Partial approval for the ground rods at Inverter #17- #20and Combiner #5, okay to shade fill progress areas |
| 07/16/2024 |
COT - CSOL - Grounding/Bonding Solar Project |
|
Partial Pass |
Partial approval for ground rods and grounding at transformer T01 and T02 locations, okay to backfill progress areas |
| 07/23/2024 |
COT - CSOL - Grounding/Bonding Solar Project |
|
Partial Pass |
Partial approval for the ground rods at Inverter #51 - #58, and at Combiner #14 and #15, okay to shade fill progress areas |
| 07/26/2024 |
COT - CSOL - Grounding/Bonding Solar Project |
|
Canceled |
|
| 08/02/2024 |
COT - CSOL - Grounding/Bonding Solar Project |
|
Partial Pass |
Partial approval for the ground rods at Inverter #50 - #49, and at Combiner #13, okay to shade fill progress areas |
| 08/06/2024 |
COT - CSOL - Grounding/Bonding Solar Project |
|
Partial Pass |
Partial approval for the ground rods at Transformer #4 , Inverters #43 - #48, and at Combiner #12, okay to shade fill progress areas |
| 08/08/2024 |
COT - CSOL - Grounding/Bonding Solar Project |
|
Partial Pass |
Partial approval for the ground rods at Inverters #39 - #42, and at Combiner panel #11, okay to shade fill progress areas |
| 08/16/2024 |
COT - CSOL - Grounding/Bonding Solar Project |
|
Passed |
Partial approval for the ground rods at Inverters #35 - #38 from Transformer #3 and at Combiner panel #10, okay to shade fill progress areas |
| 08/22/2024 |
COT - CSOL - Grounding/Bonding Solar Project |
|
Partial Pass |
Partial approval for the ground rods at Inverters #31- #34, and at Combiner panel #9, okay to shade fill progress areas |
| 08/28/2024 |
COT - CSOL - Grounding/Bonding Solar Project |
|
Partial Pass |
Partial approval for the ground rods at Inverters #27- #30, and at Combiner panel #8, okay to shade fill progress areas |