Permit Details

Status:
Inspections Complete
Type:
Commercial Building
Address NEW:
2094 N DRAGOON ST
Apply Date:
04/05/2024
Applicant:
Anthony Duplantis
Description:
Installation of 19.27 kwDC roof mounted photovoltaic system REV 1: New plans reflect a lineside tap in the external service disconnect. REV 2: Plans show the correct connector (Piercing tap) being used. REV3: Plans were revised to include a note that 'CHAIR LUGS' are to be installed on the line side of the PV AC disconnect.

Permit Reviews

Permit Number - TC-COM-0424-00611
Permit Status: Inspections complete
Permit Description: Installation of 19.27 kwDC roof mounted photovoltaic system REV 1: New plans reflect a lineside tap in the external service disconnect. REV 2: Plans show the correct connector (Piercing tap) being used. REV3: Plans were revised to include a note that 'CHAIR LUGS' are to be installed on the line side of the PV AC disconnect.
Start Date Submittal Complete Date Status  
04/08/2024 COMMERCIAL REVIEW - FULL v.1 05/07/2024 REQUIRES RESUBMIT Review Details
06/13/2024 COMMERCIAL REVIEW - FULL v.2 06/21/2024 APPROVED Review Details
01/08/2025 COMMERCIAL REVIEW - FULL REVISION v.2 01/24/2025 APPROVED Review Details
10/30/2024 COMMERCIAL REVIEW - FULL v.1 11/13/2024 REQUIRES RESUBMIT Review Details
01/29/2026 COMMERCIAL REVIEW - FULL REVISION v.1 02/23/2026 APPROVED Review Details
11/20/2024 COMMERCIAL REVIEW - FULL v.2 12/03/2024 APPROVED Review Details
06/21/2024 RESTAMP - COMMERCIAL v.1 06/21/2024 APPROVED Review Details
12/16/2024 COMMERCIAL REVIEW - FULL REVISION v.1 12/31/2024 REQUIRES RESUBMIT Review Details

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-COM-0424-00611
Permite Description: Installation of 19.27 kwDC roof mounted photovoltaic system REV 1: New plans reflect a lineside tap in the external service disconnect. REV 2: Plans show the correct connector (Piercing tap) being used. REV3: Plans were revised to include a note that 'CHAIR LUGS' are to be installed on the line side of the PV AC disconnect.
Total Outstanding Inspections - 7
Last Inspection Date Description Inspector Results Comments
10/25/2024 ENGR Engineering Final N/A Not Applicable NO Exterior work was completed
12/10/2024 COT - CSOL - Electrical Progress Solar Project N/A Not Applicable
12/10/2024 COT - CSOL - Electrical Final Solar Project N/A Re-inspection required Revised plans must submitted and approved to provide optional line-side tap connector used
12/10/2024 COT - CSOL - Grounding/Bonding Solar Project N/A Not Ready
12/10/2024 COT - LCEL - Electrical Final N/A Re-inspection required Revised plans must submitted and approved to provide optional line-side tap connector used
12/10/2024 COT - LCBU - Building Final N/A Re-inspection required Revised plans must submitted and approved to provide optional line-side tap connector used
12/10/2024 BULD - Electrical Clearance N/A Not Ready

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-COM-0424-00611
Permit Description: Installation of 19.27 kwDC roof mounted photovoltaic system REV 1: New plans reflect a lineside tap in the external service disconnect. REV 2: Plans show the correct connector (Piercing tap) being used. REV3: Plans were revised to include a note that 'CHAIR LUGS' are to be installed on the line side of the PV AC disconnect.
Total Completed Inspections - 6
Date Description Inspector Results Comments
10/25/2024 TRSP - ROW - Final/Close-Out Passed
01/31/2025 COT - CSOL - Electrical Final Solar Project Passed
01/31/2025 COT - CSOL - Grounding/Bonding Solar Project Passed
04/06/2026 COT - LCEL - Electrical Final Passed
04/06/2026 COT - LCBU - Building Final Passed
04/06/2026 BULD - Electrical Clearance Passed Verbal clearance to TEP DGL. (Line side tap)
Final clearances for TEP DGC/DGL 4/6/2026