Permit: TC-COM-0423-00974
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
7355 S WILMOT RD BLDG 18
Address NEW:
7355 S WILMOT RD BLDG 18
Apply Date:
04/06/2023
Applicant:
HSLCS Permits
Description:
Building 18 Maintenance (plan set under TC-COM-0323-00830)
Permit Reviews
Permit Number - TC-COM-0423-00974
Permit Status: Complete
Permit Description: Building 18 Maintenance (plan set under TC-COM-0323-00830)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/19/2024 | COMMERCIAL REVIEW - FULL v.3 | 01/30/2024 | APPROVED |
| 10/09/2023 | COMMERCIAL REVIEW - FULL v.1 | 11/02/2023 | REQUIRES RESUBMIT |
| 02/21/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/24/2025 | REQUIRES RESUBMIT |
| 12/12/2023 | COMMERCIAL REVIEW - FULL v.2 | 12/18/2023 | REQUIRES RESUBMIT |
| 02/01/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/05/2024 | APPROVED |
| 03/12/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 03/14/2025 | APPROVED |
| 05/30/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/30/2025 | APPROVED |
| 05/21/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/22/2025 | APPROVED |
| 06/27/2023 | COMMERCIAL REVIEW - FULL v.2 | 07/05/2023 | APPROVED |
| 04/18/2023 | COMMERCIAL REVIEW - FULL v.1 | 05/12/2023 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-COM-0423-00974
Permit Status: Complete
Permit Description: Building 18 Maintenance (plan set under TC-COM-0323-00830)
| Date | Description | Comments |
|---|---|---|
| 04/18/2023 | Please contact Pima County Addressing to resolve your addressing issue related to FILL IN THIS SPACE. Addressing@pima.gov or 520-724-9512 | |
| 05/22/2025 | AIR BALANCING REPORT IS REQUIRED. | |
| 09/16/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 09/16/2024 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
| 05/30/2025 | WATER STERILIZATION REPORT IS REQUIRED. | |
| 09/16/2024 | SPECIAL INSPECTION FOR WELD REINF STEEL IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0423-00974
Permite Description: Building 18 Maintenance (plan set under TC-COM-0323-00830)
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/25/2024 | COT - HCBU - Exterior Clips/Sheathing | N/A | Re-inspection required | Provide anchor bolts that are out of the center third of the bottom plates. Add anchor bolts at breaks. Missing throughout. 7/25/2024 |
| 10/03/2023 | COT - HCBU - Building Progress | N/A | Partial Pass |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0423-00974
Permit Description: Building 18 Maintenance (plan set under TC-COM-0323-00830)
Total Completed Inspections - 31
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/22/2024 | COT - HCPL - Rough Soil | Passed | 4/22/24: Plumbing per plan ok to backfill. Shading required. | |
| 05/14/2024 | COT - HCBU - Excavation/Rebar/Zoning | Passed | 5/8/24: not ready 5/14/24: Preslab at maintenance building passed. |
|
| 05/14/2024 | COT - HCBU - Preslab | Passed | 5/8/24: not ready 5/14/24: Preslab at maintenance building passed. |
|
| 07/16/2024 | COT - HCBU - Roof Nailing | Passed | ||
| 07/25/2024 | COT - HCBU - Framing | Passed | ||
| 10/07/2024 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
| 10/07/2024 | COT - HCPL - Plumbing Progress | Passed | ||
| 10/07/2024 | COT - HCEL - Grounding/Bonding | Passed | ||
| 10/07/2024 | COT - HCEL - Electrical Progress | Passed | ||
| 10/07/2024 | COT - BULD - SWG Clearance | Passed | ||
| 10/07/2024 | COT - HCME - Mechanical Intermediate | Passed | ||
| 10/07/2024 | COT - HCME - Mechanical Progress | Passed | ||
| 10/07/2024 | COT - HCPL - Plumbing Above Ceiling | Passed | ||
| 10/07/2024 | COT - HCPL - Plumbing Intermediate | Passed | ||
| 10/07/2024 | COT - HCPL - Plumbing Roof Drains | Passed | ||
| 10/07/2024 | COT - HCPL - Sewer | Passed | ||
| 10/07/2024 | COT - HCBU - Building Progress | Passed | ||
| 10/08/2024 | COT - HCEL - Electrical Intermediate | Passed | All corrections were made. 10/8/2024 | |
| 10/08/2024 | COT - HCEL - Electrical Above Ceiling | Passed | All corrections were made. 10/8/2024 | |
| 10/08/2024 | COT - HCBU - Building Above Ceiling | Passed | All corrections were made. 10/8/2024 | |
| 10/29/2024 | COT - HCBU - Interior Shear Bracing | Passed | ||
| 12/27/2024 | BULD - Electrical Clearance | Passed | Passed 12/27/24 CLEARANCE ECO | |
| 05/15/2025 | COT - FCON - Fire - Final | Passed | ||
| 05/15/2025 | COT - FCON - Sprinkler - Final | Passed | ||
| 05/27/2025 | COT - HCBU - Building Final | Passed | 5-27-25, all corrections made. Building final approved. | |
| 05/27/2025 | COT - HCEL - Electrical Final | Passed | 5-27-25, all corrections made. Plumbing, electrical & mechanical final approved. | |
| 05/27/2025 | COT - HCME - Mechanical Final | Passed | 5-27-25, all corrections made. Plumbing, electrical & mechanical final approved. | |
| 05/27/2025 | COT - HCPL - Plumbing Final | Passed | 5-27-25, all corrections made. Plumbing & mechanical final approved. | |
| 06/03/2025 | ENGR Engineering Final | Passed | CO Ready | |
| 06/03/2025 | TRSP - ROW - Final/Close-Out | Passed | ||
| 06/03/2025 | COT - HCBU - CofO | Passed | 6-3-25: all finals for Building 18 have been approved, and there are no pending conditions. Okay to issue C of O. |