Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
In Review
Type:
Commercial Building
Apply Date:
03/11/2026
Applicant:
Andres Herrera
Description:
Remodel existing office to provide new restrooms

Permit Reviews

Permit Number - TC-COM-0326-00352
Permit Status: In review
Permit Description: Remodel existing office to provide new restrooms
Start Date Submittal Complete Date Status  
03/16/2026 COMMERCIAL REVIEW - FULL v.1 04/08/2026 REQUIRES RESUBMIT Review Details
08/13/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.1 N/A IN REVIEW Review Details
04/29/2026 RESTAMP - COMMERCIAL v.1 05/14/2026 APPROVED Review Details
04/21/2026 COMMERCIAL REVIEW - FULL v.2 04/29/2026 APPROVED Review Details

Conditions

Permit Number - TC-COM-0326-00352
Permit Status: In review
Permit Description: Remodel existing office to provide new restrooms
Date Description Comments
03/16/2026 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
03/16/2026 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
08/14/2026 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: In Review
Permit Number: TC-COM-0326-00352
Permite Description: Remodel existing office to provide new restrooms
Total Outstanding Inspections - 6
Last Inspection Date Description Inspector Results Comments
07/07/2026 COT - BULD - SWG Clearance N/A Not Applicable
07/07/2026 BULD - Electrical Clearance N/A Not Applicable
08/11/2026 COT - HCPL - Plumbing Final N/A Re-inspection required 8-11-26: insulate hot copper line at water heater, provide supports for tankless water heater and label switch " water heater disconnect." Provide knee covers underneath all lavatories, provide distance clarification to center of water closet at men's restroom, install toilet paper/ napkin dispensers at each restroom together with restroom doors & ADA restroom signs, upload water sterilization report to the city for review.
08/14/2026 COT - HCBU - Building Final N/A Partial Pass 8-14-26: pending engineer letter/load calcs/final panel schedules. Water sterilization report submitted to the city-pending approval. Air balance report to be submitted-okay to apply for a Level 4 TCO.
08/14/2026 COT - HCBU - CofO N/A Partial Pass 8-14-26: pending engineer letter/load calcs/final panel schedules. Water sterilization report submitted to the city-pending approval. Air balance report to be submitted-okay to apply for a Level 4 TCO.
08/11/2026 COT - HCEL - Electrical Final N/A Re-inspection required 8-11-26: have architect or engineer of record submit updated panels schedules & load calcs. on each panel that was used for new construction to the city for review/approval.

Completed Inspections

Permit Status: In Review
Permit Number: TC-COM-0326-00352
Permit Description: Remodel existing office to provide new restrooms
Total Completed Inspections - 14
Date Description Inspector Results Comments
07/01/2026 COT - HCBU - Building Above Ceiling Passed 7-1-26: intermediates at room's 103, 104, 105 approved. Okay to continue with TI at progress areas.
07/07/2026 COT - HCBU - Framing Passed
08/05/2026 COT - HCEL - Electrical Intermediate Passed
08/07/2026 COT - FCON - Alarm - Final Passed
08/07/2026 COT - HCPL - Plumbing Intermediate Passed 8-7-26: plumbing intermediate approved.
08/07/2026 COT - HCME - Mechanical Above Ceiling Passed 8-7-26: mechanical above ceiling approved.
08/07/2026 COT - HCPL - Plumbing Above Ceiling Passed 8-7-26: plumbing above ceiling approved.
08/07/2026 COT - HCEL - Electrical Above Ceiling Passed 8-7-26: electrical above ceiling approved.
08/07/2026 COT - HCME - Mechanical Final Passed 8-7-26: mechanical Building final approved.
08/10/2026 TRSP - ROW - Final/Close-Out Passed phone call with Nathan, confirmed entirety of project was tenant improvements inside existing building with no impact or restoration to right of way easement
08/11/2026 ENGR Engineering Final Passed Site is complete in accordance with approved plans.
08/12/2026 COT - FCON - Sprinkler - Final Passed
08/13/2026 COT - FCON - Fire - Final Passed
08/13/2026 COT - HCPL - Plumbing Final Passed 8-13-26: any pending ADA requirements will be noted at the building final. Plumbing final approved.
Note: contractor has submitted a water sterilization report to the city for review & has a copy of report if needed.

Documents

File Name Document Type  
2_RAH - SUNDT TI - BUILDING 2 PERMIT RESPONSE_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD (SSRS).PDF DOCUMENTS VIEW
CONS-2_RAH - SUNDT TI - BUILDING 2 CDS_V2.PDF DOCUMENTS VIEW