Inspection Status: Re-inspection required
Inspection History: COT - HCEL - Electrical Above Ceiling
| Date |
Description |
Inspector |
Results |
Comments |
| 06/30/2026 |
COT - HCEL - Electrical Above Ceiling |
|
Re-inspection required |
6-30-26: per NEC 300.11, MC Cabling must be independently supported from from the t-grid/ceiling grid. Remove Mc cables from grid at all restrooms & add knockouts for 2 above ceiling junction boxes. |
| 08/07/2026 |
COT - HCEL - Electrical Above Ceiling |
|
Passed |
8-7-26: electrical above ceiling approved. |