Inspection History Details
Inspection Status: Re-inspection required
Inspection History: COT - HCPL - Plumbing Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/11/2026 | COT - HCPL - Plumbing Final | Re-inspection required | 8-11-26: insulate hot copper line at water heater, provide supports for tankless water heater and label switch " water heater disconnect." Provide knee covers underneath all lavatories, provide distance clarification to center of water closet at men's restroom, install toilet paper/ napkin dispensers at each restroom together with restroom doors & ADA restroom signs, upload water sterilization report to the city for review. | |
| 08/13/2026 | COT - HCPL - Plumbing Final | Passed | 8-13-26: any pending ADA requirements will be noted at the building final. Plumbing final approved. Note: contractor has submitted a water sterilization report to the city for review & has a copy of report if needed. |