Permit: TC-COM-0325-00540
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
2717 E CORONA RD UNIT 140
Address NEW:
2717 E CORONA RD UNIT 140
Apply Date:
03/18/2025
Applicant:
Avinash Karnati
Description:
Commercial tenant improvement for exiting shell building
Permit Reviews
Permit Number - TC-COM-0325-00540
Permit Status: Complete
Permit Description: Commercial tenant improvement for exiting shell building
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/14/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/21/2026 | APPROVED |
| 05/20/2025 | COMMERCIAL REVIEW - FULL v.3 | 05/20/2025 | APPROVED |
| 03/20/2025 | COMMERCIAL REVIEW - FULL v.1 | 04/16/2025 | REQUIRES RESUBMIT |
| 10/29/2025 | COMMERCIAL REVIEW - FULL REVISION v.1 | 11/24/2025 | APPROVED |
| 12/03/2025 | COMMERCIAL REVIEW - FULL REVISION v.1 | 12/29/2025 | APPROVED |
| 05/20/2025 | RESTAMP - COMMERCIAL v.1 | 05/28/2025 | APPROVED |
| 09/02/2025 | COMMERCIAL REVIEW - FULL REVISION v.1 | 09/29/2025 | APPROVED |
| 04/23/2025 | COMMERCIAL REVIEW - FULL v.2 | 05/13/2025 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-COM-0325-00540
Permit Status: Complete
Permit Description: Commercial tenant improvement for exiting shell building
| Date | Description | Comments |
|---|---|---|
| 03/20/2025 | UNIT IDENTIFICATION | |
| 03/20/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 03/20/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 05/20/2025 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. | |
| 05/20/2025 | SPECIAL INSPECTION FOR WELDING IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0325-00540
Permite Description: Commercial tenant improvement for exiting shell building
Total Outstanding Inspections - 8
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/30/2025 | COT - HCBU - Building Progress | N/A | Partial Pass | 10/30/25 framing per plan, ok to proceed in suite |
| 12/04/2025 | COT - HCEL - Electrical Above Ceiling | N/A | Partial Pass | 12-4-25: label junction boxes. |
| 12/16/2025 | COT - HCEL - Electrical Intermediate | N/A | Partial Pass | 12-16-25: will check HVAC receptacles on rooftop at finals. |
| 01/14/2026 | COT - FCON - Alarm - Final | N/A | Not Applicable | |
| 01/15/2026 | COT - HCBU - Building Final | N/A | Re-inspection required | 1-15-26: install bollard to protect water heater-architect to submit a letter with details for review, water chlorination test in progress-unable to check water, lower restroom mirror at office area to 40" to reflective surface, install locking mechanism at same restroom, paint exterior roof drain plastic, provide pictures of junction boxes with labeling at warehouse side. |
| 01/15/2026 | COT - HCME - Mechanical Final | N/A | Re-inspection required | 1-15-26: install bollard to protect water heater-architect to submit a letter with details for review, water chlorination test in progress-unable to check water, lower restroom mirror at office area to 40" to reflective surface, install locking mechanism at same restroom, paint exterior roof drain plastic, provide pictures of junction boxes with labeling at warehouse side. |
| 01/15/2026 | COT - HCPL - Plumbing Final | N/A | Re-inspection required | 1-15-26: install bollard to protect water heater-architect to submit a letter with details for review, water chlorination test in progress-unable to check water, lower restroom mirror at office area to 40" to reflective surface, install locking mechanism at same restroom, paint exterior roof drain plastic, provide pictures of junction boxes with labeling at warehouse side. |
| 01/21/2026 | COT - BULD - SWG Clearance | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0325-00540
Permit Description: Commercial tenant improvement for exiting shell building
Total Completed Inspections - 17
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/20/2025 | BULD - Electrical Clearance | Passed | 11-20-25: okay to energize Suite 140.ECO clearance issued to TEP. | |
| 12/04/2025 | COT - HCBU - Building Progress | Passed | 12-4-25: approved. Framing at demising wall between suite 110 & 140 approved. | |
| 12/04/2025 | COT - HCEL - Electrical Progress | Passed | 12-4-25: approved. | |
| 12/04/2025 | COT - HCME - Mechanical Intermediate | Passed | 12-4-25: approved. | |
| 12/04/2025 | COT - HCME - Mechanical Progress | Passed | 12-4-25: approved. | |
| 12/04/2025 | COT - HCPL - Plumbing Intermediate | Passed | 12-4-25: plumbing intermedites approved. | |
| 12/04/2025 | COT - HCPL - Plumbing Progress | Passed | 12-4-25: plumbing progress approved. | |
| 01/08/2026 | COT - HCEL - Electrical Above Ceiling | Passed | 1-8-26: approved. | |
| 01/08/2026 | COT - HCEL - Electrical Intermediate | Passed | 1-8-26: electrical intermediate approved. | |
| 01/14/2026 | COT - FCON - Fire - Final | Passed | ||
| 01/14/2026 | ENGR Engineering Final | Passed | 1/14/25 - unit 140 exterior is complete and safe | |
| 01/14/2026 | TRSP - ROW - Final/Close-Out | Passed | ||
| 01/14/2026 | COT - FCON - Sprinkler - Final | Passed | Approved on 1/5/26 on permit TF-FCP-0925-00712 | |
| 01/15/2026 | COT - HCEL - Electrical Final | Passed | 1-15-26: approved. | |
| 01/20/2026 | COT - HCBU - Building Final | Passed | 1-20-26: building final approved. | |
| 01/20/2026 | COT - HCME - Mechanical Final | Passed | 1-20-26: mechanical final approved. | |
| 01/20/2026 | COT - HCPL - Plumbing Final | Passed | 1-20-26: plumbing final approved. |