Inspection Status: Partial Pass
Inspection History: COT - HCBU - Building Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 10/13/2025 |
COT - HCBU - Building Progress |
|
Partial Pass |
Sheet rock nailing in Northwest portion of the structure. |
| 10/23/2025 |
COT - HCBU - Building Progress |
|
Re-inspection required |
10-23-25: missing screws along base of drywall at several locations. |
| 10/30/2025 |
COT - HCBU - Building Progress |
|
Partial Pass |
10/30/25 framing per plan, ok to proceed in suite |
| 11/06/2025 |
COT - HCBU - Building Progress |
|
Partial Pass |
11-6-25: partial pass on MEP's. |
| 11/10/2025 |
COT - HCBU - Building Progress |
|
Partial Pass |
11-10-25: drywall nailing approved-okay to tape texture . |
| 12/01/2025 |
COT - HCBU - Building Progress |
|
Partial Pass |
12-1-25: partial pass on demising wall separating Suite 110 & 140. Obtain clarification from architect on whether bracing is required. Okay to drywall one side up 3' below roof deck. |
| 12/04/2025 |
COT - HCBU - Building Progress |
|
Passed |
12-4-25: approved. Framing at demising wall between suite 110 & 140 approved. |