Permit: TC-COM-0323-00766
Permit Details
Apply Date:
03/07/2023
Applicant:
Christian Bowen
Description:
NEW 5,893 S.F. SERVICE BAY ADDITION TO EXISTING PORSCHE SERVICE BAY AND WAITING RM/ ADMIN. BUILDING.
Permit Reviews
Permit Number - TC-COM-0323-00766
Permit Status: Complete
Permit Description: NEW 5,893 S.F. SERVICE BAY ADDITION TO EXISTING PORSCHE
SERVICE BAY AND WAITING RM/ ADMIN. BUILDING.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/12/2023 | COMMERCIAL REVIEW - FULL v.2 | 06/27/2023 | APPROVED |
06/17/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/20/2024 | REQUIRES RESUBMIT |
08/02/2023 | COMMERCIAL REVIEW - FULL v.2 | 08/03/2023 | APPROVED |
06/21/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 06/24/2024 | APPROVED |
03/14/2023 | COMMERCIAL REVIEW - FULL v.1 | 04/10/2023 | REQUIRES RESUBMIT |
07/07/2023 | COMMERCIAL REVIEW - FULL v.1 | 07/26/2023 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-COM-0323-00766
Permit Status: Complete
Permit Description: NEW 5,893 S.F. SERVICE BAY ADDITION TO EXISTING PORSCHE
SERVICE BAY AND WAITING RM/ ADMIN. BUILDING.
Date | Description | Comments |
---|---|---|
06/20/2024 | AIR BALANCING REPORT IS REQUIRED. | |
06/17/2024 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
06/17/2024 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
06/17/2024 | Masonry Inspection Report submittal review is required. | |
06/17/2024 | Post-Installed Anchor Inspection Report is required. | |
06/17/2024 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. | |
06/17/2024 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. | |
06/17/2024 | SPECIAL INSPECTION FOR WELDING IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0323-00766
Permite Description: NEW 5,893 S.F. SERVICE BAY ADDITION TO EXISTING PORSCHE
SERVICE BAY AND WAITING RM/ ADMIN. BUILDING.
Total Outstanding Inspections - 10
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/03/2023 | COT - HCPL - Plumbing Progress | N/A | Deferred | |
11/22/2023 | COT - HCBU - Masonry Pregrout | N/A | Partial Pass | 4th lift. |
05/07/2024 | BULD - Electrical Clearance | N/A | Not Applicable | |
05/07/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
11/20/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | N/A | Partial Pass | 11/20/23: firewall at north west of building reinforcement per plans ok proceed. @16' feet, topping out at 17'4". |
02/02/2024 | COT - HCBU - Framing | N/A | Partial Pass | 2/2/24 ok to one side and please recall framing with intermediate inspection |
11/20/2023 | COT - HCPL - Plumbing Roof Drains | N/A | Partial Pass | 10/3/23: 2 roof drains under new addition ok to cover. 11-13-26: 6 each Roof and overflow drains are at 10' inside of CMU BLOCK wall. Okay to proceed with block walls. 11/20/23: 8 roof drains added at south CMU block wall at 16'. Ok to proceed. |
01/04/2024 | COT - HCBU - Building Progress | N/A | Partial Pass | 11/20/23: 4th lift at 16' reinforcement per plan ok to proceed. Firewall reinforcement per plan ok to proceed (@16' going up to 17'4"), 8 roof drains installed per plan ok to proceed. 1/4/24: 36" steel cold-formed steel @ 4' O.C being installed. Will verify proper installation at roof nailing. |
05/14/2024 | COT - HCPL - Plumbing Final | N/A | Re-inspection required | 1-Flush valve in one restroom is on the wrong side. 2-Need under sink protection for both lavs. |
COT - FCON - Alarm - Final | N/A | Not Ready | Alarm contractor shall submit as builts and request inspection |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0323-00766
Permit Description: NEW 5,893 S.F. SERVICE BAY ADDITION TO EXISTING PORSCHE
SERVICE BAY AND WAITING RM/ ADMIN. BUILDING.
Total Completed Inspections - 30
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/11/2023 | COT - HCBU - Excavation/Rebar/Zoning | Passed | ||
10/11/2023 | COT - HCBU - Preslab | Passed | ||
10/11/2023 | COT - HCPL - Rough Soil | Passed | ||
11/16/2023 | COT - HCEL - Electrical Progress | Passed | ||
11/27/2023 | COT - HCBU - Masonry Pregrout | Passed | 23’6 6th lift final lift. Rebar per plan. okay for top out all around. 11/27/2023 | |
01/17/2024 | COT - HCBU - Roof Nailing | Passed | ||
01/24/2024 | COT - LCPL - Sewer | Passed | Completed connection of 4" sewer from HCS to building, okay to backfill | |
02/14/2024 | COT - HCPL - Plumbing Intermediate | Passed | Plumbing rough-in is complete for staff restrooms, water supply line is under 50# of air pressure and holding without any leaks, and gas line to heating units on roof is under 20# of air pressure without any leaks. Okay to drywall both sides of walls. | |
02/22/2024 | COT - HCME - Mechanical Above Ceiling | Passed | ||
05/07/2024 | COT - HCBU - Building Above Ceiling | Passed | ||
05/07/2024 | PDSD Heavy Commercial Building Division Pre-Construction Meeting | Passed | ||
05/07/2024 | COT - HCBU - Firewall/Fire Barrier/Firestop | Passed | ||
05/07/2024 | COT - HCBU - Framing | Passed | ||
05/07/2024 | COT - HCEL - Electrical Above Ceiling | Passed | ||
05/07/2024 | COT - HCEL - Electrical Intermediate | Passed | ||
05/07/2024 | COT - HCME - Mechanical Intermediate | Passed | ||
05/07/2024 | COT - HCME - Mechanical Progress | Passed | ||
05/07/2024 | COT - HCPL - Plumbing Above Ceiling | Passed | ||
05/07/2024 | COT - HCPL - Plumbing Roof Drains | Passed | ||
05/07/2024 | COT - HCBU - Building Progress | Passed | ||
05/24/2024 | COT - HCME - Mechanical Final | Passed | ||
05/24/2024 | COT - HCPL - Plumbing Final | Passed | ||
06/04/2024 | COT - HCEL - Electrical Final | Passed | ||
06/05/2024 | ENGR Engineering Final | Passed | ||
06/13/2024 | COT - FCON - Fire - Final | Passed | ||
06/14/2024 | COT - HCBU - Building Final | Passed | ||
06/17/2024 | COT - FCON - Alarm - Final | Passed | ||
06/17/2024 | COT - FCON - Sprinkler - Final | Passed | ||
06/17/2024 | COT - HCBU - CofO | Passed | ||
06/18/2024 | TRSP - ROW - Final/Close-Out | Passed |