Permit: TC-COM-0224-00317
Permit Details
Apply Date:
02/19/2024
Applicant:
Description:
Remodel bathroom structure at existing Pueblo Gardens Park(
Permit Reviews
Permit Number - TC-COM-0224-00317
Permit Status: Complete
Permit Description: Remodel bathroom structure at existing Pueblo Gardens Park(
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/26/2024 | COMMERCIAL REVIEW - LIMITED v.1 | 02/26/2024 | REQUIRES RESUBMIT |
| 04/08/2024 | COMMERCIAL REVIEW - LIMITED v.3 | 04/23/2024 | APPROVED |
| 02/28/2024 | COMMERCIAL REVIEW - LIMITED v.2 | 03/19/2024 | REQUIRES RESUBMIT |
| 01/16/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/27/2026 | APPROVED |
| 04/23/2024 | RESTAMP - COMMERCIAL v.1 | 04/24/2024 | APPROVED |
Conditions
Permit Number - TC-COM-0224-00317
Permit Status: Complete
Permit Description: Remodel bathroom structure at existing Pueblo Gardens Park(
| Date | Description | Comments |
|---|---|---|
| 02/26/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 03/19/2024 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0224-00317
Permite Description: Remodel bathroom structure at existing Pueblo Gardens Park(
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/06/2024 | COT - LCEL - Electrical Intermediate | N/A | Partial Pass | Pod cast rooms, fitness room, restrooms, E-lounge (Northwest portion of building). Ok to insulate and cover walls. |
| 11/07/2024 | COT - LCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | 1 light pole base approved. Proper depth along with the rebar schedule and ground. Okay for concrete placement. 11/7/2024 |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0224-00317
Permit Description: Remodel bathroom structure at existing Pueblo Gardens Park(
Total Completed Inspections - 17
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/27/2024 | COT - LCPL - Sewer | Passed | 9/27/24: plumbing underground passed, sewer connection passed. | |
| 10/01/2024 | COT - LCBU - Framing | Passed | Ok to cover walls. | |
| 11/06/2024 | COT - LCEL - Outdoor Lighting | Passed | ||
| 11/06/2024 | COT - LCEL - Electrical Underground | Passed | ||
| 12/05/2024 | COT - LCBU - Preslab | Passed | Okay for concrete placement in pad. 12/5/2024 | |
| 01/14/2026 | COT - LCPL - Yard Water Line | Passed | ||
| 01/14/2026 | COT - LCEL - Grounding/Bonding | Passed | ||
| 01/14/2026 | COT - LCPL - Rough Soil | Passed | ||
| 01/14/2026 | COT - LCEL - Electrical Intermediate | Passed | ||
| 01/14/2026 | COT - LCBU - Roof Nailing | Passed | ||
| 01/14/2026 | COT - LCEL - Electrical Above Ceiling | Passed | ||
| 01/14/2026 | COT - LCPL - Plumbing Final | Passed | ||
| 01/14/2026 | COT - LCME - Mechanical Final | Passed | ||
| 01/14/2026 | COT - LCEL - Electrical Final | Passed | ||
| 01/14/2026 | COT - LCBU - Excavation/Rebar/Zoning | Passed | ||
| 01/14/2026 | COT - LCBU - Building Final | Passed | ||
| 01/14/2026 | BULD - Electrical Clearance | Passed |