Permit: TC-COM-0224-00271
Permit Details
Status:
Inspections
Type:
Commercial Building
Address:
6175 S MIDVALE PARK RD BLDG 3
Address NEW:
6175 S MIDVALE PARK RD BLDG 3
Apply Date:
02/08/2024
Applicant:
Carlos Navarro
Description:
BLDG C SEE PERMIT APPLICATION NUMBER TC-COM-0124-00215 - The proposed project consists of 64 units of rental apartments in (4) 2-Story buildingS. The tenants will be served by a single-story community center located on the site, as well as on-site resident amenities such as BBQ and gathering areas, and children’s play areas. The site will be accessed from a formal entry ON SOUTH BUFKIN DRIVE. Site circulation is comprised of double and single loaded parking aisles, with an even distribution of accessible spaces. Refuse and recycle collection areas are distributed throughout the site for ease of access.
Permit Reviews
Permit Number - TC-COM-0224-00271
Permit Status: Inspections
Permit Description: BLDG C SEE PERMIT APPLICATION NUMBER TC-COM-0124-00215 - The proposed project consists of 64 units of rental apartments in (4) 2-Story buildingS. The tenants will be served by a single-story community center located on the site, as well as on-site resident amenities such as BBQ and gathering areas, and children’s play areas.
The site will be accessed from a formal entry ON SOUTH BUFKIN DRIVE. Site circulation is comprised of double and single loaded parking aisles, with an even distribution of accessible spaces. Refuse and recycle collection areas are distributed throughout the site for ease of access.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/09/2024 | COMMERCIAL REVIEW - FULL v.2 | 05/08/2024 | REQUIRES RESUBMIT |
| 02/03/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/03/2025 | REQUIRES RESUBMIT |
| 10/31/2024 | COMMERCIAL REVIEW - FULL v.1 | 11/26/2024 | APPROVED |
| 06/25/2024 | COMMERCIAL REVIEW - FULL v.3 | 07/08/2024 | REQUIRES RESUBMIT |
| 04/21/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/21/2025 | REQUIRES RESUBMIT |
| 07/11/2024 | COMMERCIAL REVIEW - FULL v.4 | 07/11/2024 | APPROVED |
| 02/24/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 02/25/2025 | APPROVED |
| 02/08/2024 | COMMERCIAL REVIEW - FULL v.1 | 03/18/2024 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TC-COM-0224-00271
Permit Status: Inspections
Permit Description: BLDG C SEE PERMIT APPLICATION NUMBER TC-COM-0124-00215 - The proposed project consists of 64 units of rental apartments in (4) 2-Story buildingS. The tenants will be served by a single-story community center located on the site, as well as on-site resident amenities such as BBQ and gathering areas, and children’s play areas.
The site will be accessed from a formal entry ON SOUTH BUFKIN DRIVE. Site circulation is comprised of double and single loaded parking aisles, with an even distribution of accessible spaces. Refuse and recycle collection areas are distributed throughout the site for ease of access.
Total Outstanding Activity Conditions - 9
| Date | Name |
|---|---|
| 07/01/2024 | Applies to All: Deferred submittal documents must be submitted and approved prior to installation of construction elements included in deferred submittal documents. |
| 07/01/2024 | Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents. |
| 07/01/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 07/01/2024 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. |
| 07/01/2024 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. |
| 07/01/2024 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. |
| 07/01/2024 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
| 07/01/2024 | Post-Tension Inspection Report is required. |
| 07/01/2024 | SPECIAL INSPECTION FOR WELDING IS REQUIRED. |
Conditions
Permit Number - TC-COM-0224-00271
Permit Status: Inspections
Permit Description: BLDG C SEE PERMIT APPLICATION NUMBER TC-COM-0124-00215 - The proposed project consists of 64 units of rental apartments in (4) 2-Story buildingS. The tenants will be served by a single-story community center located on the site, as well as on-site resident amenities such as BBQ and gathering areas, and children’s play areas.
The site will be accessed from a formal entry ON SOUTH BUFKIN DRIVE. Site circulation is comprised of double and single loaded parking aisles, with an even distribution of accessible spaces. Refuse and recycle collection areas are distributed throughout the site for ease of access.
| Date | Description | Comments |
|---|---|---|
| 02/08/2024 | Please contact Pima County Addressing to resolve issue. Addressing@pima.gov or 520-724-9512 | |
| 02/08/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 07/11/2024 | Prior to Issuance: This project requires issuance of a Development Package (DP) TD-DEV-0124-00025 permit prior to issuance of this permit. Prior to TCO/Final: This project requires full completion of a Development Package (DP) permit prior to Temporary C of O and/or final completion this permit. | |
| 02/08/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 07/01/2024 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TC-COM-0224-00271
Permite Description: BLDG C SEE PERMIT APPLICATION NUMBER TC-COM-0124-00215 - The proposed project consists of 64 units of rental apartments in (4) 2-Story buildingS. The tenants will be served by a single-story community center located on the site, as well as on-site resident amenities such as BBQ and gathering areas, and children’s play areas.
The site will be accessed from a formal entry ON SOUTH BUFKIN DRIVE. Site circulation is comprised of double and single loaded parking aisles, with an even distribution of accessible spaces. Refuse and recycle collection areas are distributed throughout the site for ease of access.
Total Outstanding Inspections - 11
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/06/2025 | COT - HCBU - Building Progress | N/A | Partial Pass | 3-6-25, nailing on roof decking for building 3 on second floor approved. Okay to proceed to with construction. |
| 04/16/2025 | COT - HCBU - Roof Nailing | N/A | Partial Pass | 4-16-25, nailing for roof decking on Building C approved. Okay to continue with construction at progress areas. |
| 04/25/2025 | COT - HCBU - Interior Shear Bracing | N/A | Partial Pass | 4/24/25: First floor sheathing fastened per plan, (Hold down spacing not per shear-wall schedule, shot pins spacing not per shear wall schedule, HTT4 MISSING ON FIRST FLOOR, Holddown location not per plan at shear walls that are 9' in length. 4/25/24: corrections made ok to proceed. |
| 07/28/2025 | COT - HCBU - Building Above Ceiling | N/A | Not Ready | |
| 07/30/2025 | COT - HCPL - Plumbing Intermediate | N/A | Partial Pass | 7-30-25: plumbing intermediate in Building C verified per plans. Okay to continue with construction at progress areas. |
| 07/30/2025 | COT - HCEL - Electrical Above Ceiling | N/A | Partial Pass | 7-30-25: electrical above ceiling for Building C verified per plans. Okay to continue with construction at progress areas. |
| 07/30/2025 | COT - HCME - Mechanical Above Ceiling | N/A | Partial Pass | 7-30-25: mechanical above ceiling inspection on Building C verified per plans. Okay to continue with construction at progress areas. |
| 07/30/2025 | COT - HCEL - Electrical Intermediate | N/A | Partial Pass | 7-30-25: electrical intermediates on Building C verified per plans. Okay to continue with construction at progress areas. |
| 07/30/2025 | COT - HCPL - Plumbing Above Ceiling | N/A | Partial Pass | 7-30-25: plumbing above ceiling in Building C verified per plans. Okay to continue with construction at progress areas. |
| 07/30/2025 | COT - HCME - Mechanical Intermediate | N/A | Partial Pass | 7-30-25: mechanical intermediate inspection on Building C verified per plans. Okay to continue with construction at progress areas. |
| 11/15/2024 | COT - HCPL - Plumbing Progress | N/A | Partial Pass | 11/15/24: plumbing underground per plans ok to proceed with backfill. |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-COM-0224-00271
Permit Description: BLDG C SEE PERMIT APPLICATION NUMBER TC-COM-0124-00215 - The proposed project consists of 64 units of rental apartments in (4) 2-Story buildingS. The tenants will be served by a single-story community center located on the site, as well as on-site resident amenities such as BBQ and gathering areas, and children’s play areas.
The site will be accessed from a formal entry ON SOUTH BUFKIN DRIVE. Site circulation is comprised of double and single loaded parking aisles, with an even distribution of accessible spaces. Refuse and recycle collection areas are distributed throughout the site for ease of access.
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/28/2025 | COT - HCBU - Preslab | Passed | ||
| 08/08/2025 | COT - HCME - Mechanical Intermediate | Passed | 7-30-25: mechanical intermediate inspection on Building C verified per plans. Okay to continue with construction at progress areas. 8/7/25: Hood range duct at kitchen, 2nd floor building C, 8 units. |
|
| 09/24/2025 | BULD - Electrical Clearance | Passed | 9-24-25: okay to energize Building 3 unit's, 3203, 3201, 3103, 3101, 3102, 3104, 3202, 3204, House panel, 3208, 3108, 3106, 3206, 3107, 3205, 3105, 3205. ECO clearance issued to TEP. |