Permit: TC-COM-0223-00675
Permit Details
Apply Date:
02/21/2023
Applicant:
Lisa Bowers
Description:
New single story coffee shop with drive thru REV1_Changes to the plans include, but are not limited too: 1. Revised drive through lane configuration and equipment 2. Revised interior wall configuration 3. Revised patio trellis/cover system (footprint remains the same) 4. Revised interior finish system 5. Revised ceiling elements, lighting, and finishes 6. Revised roof layout to blend better with interior layout. 7. Revised exterior finish systems and signage (signage to be a deferred submittal) 8. Revised equipment package for a Black Rifle Coffee Company store 9. Revised structural system to support new exterior design and roof EQ placement 10. Revised interior plumbing plans to match to the new interior EQ layout. 11. Revised mechanical EQ locations to match the interior layout of the store. 12. Revised electrical plans to compliment the change of interior EQ and lighting.
Permit Reviews
Permit Number - TC-COM-0223-00675
Permit Status: Issued
Permit Description: New single story coffee shop with drive thru
REV1_Changes to the plans include, but are not limited too:
1. Revised drive through lane configuration and equipment
2. Revised interior wall configuration
3. Revised patio trellis/cover system (footprint remains the same)
4. Revised interior finish system
5. Revised ceiling elements, lighting, and finishes
6. Revised roof layout to blend better with interior layout.
7. Revised exterior finish systems and signage (signage to be a deferred submittal)
8. Revised equipment package for a Black Rifle Coffee Company store
9. Revised structural system to support new exterior design and roof EQ placement
10. Revised interior plumbing plans to match to the new interior EQ layout.
11. Revised mechanical EQ locations to match the interior layout of the store.
12. Revised electrical plans to compliment the change of interior EQ and lighting.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/17/2023 | RESTAMP - COMMERCIAL v.1 | 05/18/2023 | APPROVED |
| 05/30/2025 | COMMERCIAL REVIEW - FULL v.2 | 06/05/2025 | APPROVED |
| 03/06/2023 | COMMERCIAL REVIEW - FULL v.1 | 03/29/2023 | REQUIRES RESUBMIT |
| 09/24/2025 | RESTAMP - COMMERCIAL v.1 | 09/25/2025 | APPROVED |
| 05/01/2023 | COMMERCIAL REVIEW - FULL v.2 | 05/17/2023 | APPROVED |
| 04/16/2025 | COMMERCIAL REVIEW - FULL v.1 | 05/21/2025 | REQUIRES RESUBMIT |
| 06/05/2025 | RESTAMP - COMMERCIAL v.1 | 06/09/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-COM-0223-00675
Permit Status: Issued
Permit Description: New single story coffee shop with drive thru
REV1_Changes to the plans include, but are not limited too:
1. Revised drive through lane configuration and equipment
2. Revised interior wall configuration
3. Revised patio trellis/cover system (footprint remains the same)
4. Revised interior finish system
5. Revised ceiling elements, lighting, and finishes
6. Revised roof layout to blend better with interior layout.
7. Revised exterior finish systems and signage (signage to be a deferred submittal)
8. Revised equipment package for a Black Rifle Coffee Company store
9. Revised structural system to support new exterior design and roof EQ placement
10. Revised interior plumbing plans to match to the new interior EQ layout.
11. Revised mechanical EQ locations to match the interior layout of the store.
12. Revised electrical plans to compliment the change of interior EQ and lighting.
Total Outstanding Activity Conditions - 4
| Date | Name |
|---|---|
| 05/12/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
| 05/12/2023 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. |
| 05/12/2023 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. |
| 05/12/2023 | SPECIAL INSPECTION FOR WELD REINF STEEL IS REQUIRED. |
Conditions
Permit Number - TC-COM-0223-00675
Permit Status: Issued
Permit Description: New single story coffee shop with drive thru
REV1_Changes to the plans include, but are not limited too:
1. Revised drive through lane configuration and equipment
2. Revised interior wall configuration
3. Revised patio trellis/cover system (footprint remains the same)
4. Revised interior finish system
5. Revised ceiling elements, lighting, and finishes
6. Revised roof layout to blend better with interior layout.
7. Revised exterior finish systems and signage (signage to be a deferred submittal)
8. Revised equipment package for a Black Rifle Coffee Company store
9. Revised structural system to support new exterior design and roof EQ placement
10. Revised interior plumbing plans to match to the new interior EQ layout.
11. Revised mechanical EQ locations to match the interior layout of the store.
12. Revised electrical plans to compliment the change of interior EQ and lighting.
| Date | Description | Comments |
|---|---|---|
| 05/12/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. | |
| 05/18/2023 | Prior to Issuance of Revision: This project requires issuance of a Development Package (DP) permit prior to issuance of this permit. Prior to TCO/Final: This project requires full completion of a Development Package (DP) permit prior to Temporary C of O and/or final completion this permit. | |
| 01/07/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-COM-0223-00675
Permite Description: New single story coffee shop with drive thru
REV1_Changes to the plans include, but are not limited too:
1. Revised drive through lane configuration and equipment
2. Revised interior wall configuration
3. Revised patio trellis/cover system (footprint remains the same)
4. Revised interior finish system
5. Revised ceiling elements, lighting, and finishes
6. Revised roof layout to blend better with interior layout.
7. Revised exterior finish systems and signage (signage to be a deferred submittal)
8. Revised equipment package for a Black Rifle Coffee Company store
9. Revised structural system to support new exterior design and roof EQ placement
10. Revised interior plumbing plans to match to the new interior EQ layout.
11. Revised mechanical EQ locations to match the interior layout of the store.
12. Revised electrical plans to compliment the change of interior EQ and lighting.
Total Outstanding Inspections - 7
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/04/2025 | BULD - Electrical Clearance | N/A | Partial Pass | 9/4/25: TMPP TEP CLEARANCE FOR 3450 S KINO PKWY |
| 09/05/2025 | COT - HCBU - Building Progress | N/A | Partial Pass | 9-5-25: drywall nail inspection at north service wall approved. Okay to tape/ texture and continue with construction at progress areas |
| 09/23/2025 | COT - HCBU - Framing | N/A | Re-inspection required | 9-23-25: add nails/screws to exterior sheathing per schedule, add shot pins at marked locations-Shot pins are required within 12" at the end of a plate and every 24" o.c... Submit a revision for interior soffit framing. Most current plans from 4/4/25 do not show soffit layout with dimensions. It appears current layout of installed soffits were used using the plans from 2023 and those details are conflicting. |
| 10/17/2025 | COT - HCEL - Electrical Above Ceiling | N/A | Partial Pass | 10-17-25: partial pass-pending electrical at rooftop. Electrical above ceiling at exterior of building verified per plans-Okay to continue with construction at progress areas. |
| 10/31/2025 | COT - HCEL - Electrical Underground | N/A | Partial Pass | 10-31-25: verified electrical schedule 40 conduits & 20' of #4GRD at each light pole cage. Slab on grade for west patio approved-okay for concrete placement (columns located against the wall at west patio have been omitted from original plans-revision has been submitted). Pergola framing & hardware approved-pergola was extended 3' out on north end (revision has been submitted). Okay to continue with construction at progress areas. |
| 11/12/2025 | COT - HCPL - Plumbing Intermediate | N/A | Partial Pass | House side of gas line extended to new location on trash enclosure. Ok to.cover progress area. |
| 11/24/2025 | COT - HCPL - Plumbing Progress | N/A | Partial Pass | 11/24/2025 partial pass. Main water line from backflow up to new riser location. On test with tracer wire. Ensure blue tape is in place after first lift of compaction. Okay to backfill progress areas. Shading required. |
Completed Inspections
Permit Status: Issued
Permit Number: TC-COM-0223-00675
Permit Description: New single story coffee shop with drive thru
REV1_Changes to the plans include, but are not limited too:
1. Revised drive through lane configuration and equipment
2. Revised interior wall configuration
3. Revised patio trellis/cover system (footprint remains the same)
4. Revised interior finish system
5. Revised ceiling elements, lighting, and finishes
6. Revised roof layout to blend better with interior layout.
7. Revised exterior finish systems and signage (signage to be a deferred submittal)
8. Revised equipment package for a Black Rifle Coffee Company store
9. Revised structural system to support new exterior design and roof EQ placement
10. Revised interior plumbing plans to match to the new interior EQ layout.
11. Revised mechanical EQ locations to match the interior layout of the store.
12. Revised electrical plans to compliment the change of interior EQ and lighting.
Total Completed Inspections - 10
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/16/2025 | COT - HCBU - Excavation/Rebar/Zoning | Passed | Ensure footings are free of water before placing concrete. | |
| 07/18/2025 | COT - HCEL - Grounding/Bonding | Passed | ||
| 07/28/2025 | COT - HCPL - Sewer | Passed | Waste and vent lines at 2” - 3” under slab area. Sewer line connected to main sewer line. OK to cover progress areas. | |
| 08/01/2025 | COT - HCPL - Rough Soil | Passed | 8-1-25: previously inspected & approved by J. Burge. | |
| 08/06/2025 | COT - HCBU - Preslab | Passed | OK to place concrete in progress areas. | |
| 08/22/2025 | COT - HCBU - Exterior Clips/Sheathing | Passed | Ok to cover exterior walls. | |
| 09/04/2025 | COT - HCPL - Plumbing Roof Drains | Passed | ||
| 09/19/2025 | COT - HCBU - Building Above Ceiling | Passed | ||
| 09/19/2025 | COT - HCEL - Electrical Intermediate | Passed | Ok to insulate and sheet rock throughout. | |
| 10/07/2025 | COT - HCBU - Framing | Passed | Sheet rock nailing; OK to tape throughout building. |