Inspection Status: Partial Pass
Inspection History: COT - HCBU - Framing
| Date |
Description |
Inspector |
Results |
Comments |
| 09/03/2025 |
COT - HCBU - Framing |
|
Partial Pass |
9-3-25: preslab for west patio approved-okay to pour. |
| 09/05/2025 |
COT - HCBU - Framing |
|
Partial Pass |
9-5-25: drywall nail inspection at north service wall approved. Okay to tape and texture at progress areas. |
| 09/23/2025 |
COT - HCBU - Framing |
|
Re-inspection required |
9-23-25: add nails/screws to exterior sheathing per schedule, add shot pins at marked locations-Shot pins are required within 12" at the end of a plate and every 24" o.c... Submit a revision for interior soffit framing. Most current plans from 4/4/25 do not show soffit layout with dimensions. It appears current layout of installed soffits were used using the plans from 2023 and those details are conflicting. |
| 09/25/2025 |
COT - HCBU - Framing |
|
Partial Pass |
9-25-25: exterior clips/sheathing approved. Okay to continue with construction at progress areas. |
| 10/07/2025 |
COT - HCBU - Framing |
|
Passed |
Sheet rock nailing; OK to tape throughout building. |