Inspection Status: Passed
Inspection History: COT - HCEL - Electrical Underground
| Date |
Description |
Inspector |
Results |
Comments |
| 01/23/2026 |
COT - HCEL - Electrical Underground |
|
Passed |
|
| 08/01/2025 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
8-1-25: verified Schedule 40 conduits per plans on 2-1" for kitchen and 5-3/4" for secondary conduits all under slab. Okay to continue with construction at progress areas. |
| 08/11/2025 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
Partial pass. X2 4” Primaries from transformer to new panel location. 8/11/2025 |
| 08/12/2025 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
Electric conduits at 1” - 1 1/2” to menu board and light pole (Northeast corner). Ok to cover progress areas. |
| 08/15/2025 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
8-15-25: verified 2-3/4" secondary electrical conduits for light poles west to southeast. Okay to backfill approximately 60' of open trench. |
| 08/19/2025 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
8-19-25: verified trench depth 1-3/4" Schedule 40 conduit for south-southeast light pole. Okay to backfill approximately 60' of trench. |
| 10/31/2025 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
10-31-25: verified electrical schedule 40 conduits & 20' of #4GRD at each light pole cage. Slab on grade for west patio approved-okay for concrete placement (columns located against the wall at west patio have been omitted from original plans-revision has been submitted). Pergola framing & hardware approved-pergola was extended 3' out on north end (revision has been submitted). Okay to continue with construction at progress areas. |