Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
01/27/2025
Applicant:
Caroline Ortman
Description:
Amazon Grocery Tenant Improvement

Permit Reviews

Permit Number - TC-COM-0125-00169
Permit Status: Complete
Permit Description: Amazon Grocery Tenant Improvement
Start Date Submittal Complete Date Status  
12/04/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 12/05/2025 APPROVED Review Details
01/31/2025 COMMERCIAL REVIEW - FULL v.1 02/24/2025 REQUIRES RESUBMIT Review Details
03/05/2025 COMMERCIAL REVIEW - FULL v.2 03/06/2025 REQUIRES RESUBMIT Review Details
03/21/2025 RESTAMP - COMMERCIAL v.1 03/27/2025 APPROVED Review Details
03/19/2025 COMMERCIAL REVIEW - FULL v.3 03/21/2025 APPROVED Review Details
09/17/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 09/18/2025 APPROVED Review Details

Conditions

Permit Number - TC-COM-0125-00169
Permit Status: Complete
Permit Description: Amazon Grocery Tenant Improvement
Date Description Comments
03/21/2025 Applies to All: Deferred submittal documents must be submitted and approved prior to installation of construction elements included in deferred submittal documents.
03/27/2025 The Contractor you have added to your permit cannot be verified. Please contact staff to have the ROC number added to the account.
01/31/2025 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
12/04/2025 COUNTY HEALTH INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED.
03/21/2025 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
03/21/2025 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
03/21/2025 SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED.
01/31/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-0125-00169
Permite Description: Amazon Grocery Tenant Improvement
Total Outstanding Inspections - 6
Last Inspection Date Description Inspector Results Comments
05/02/2025 COT - HCBU - Excavation/Rebar/Zoning N/A Partial Pass 4-25-25, preslab, excavation & reinforcement for filling in 3 dock levelers verified per plans. Okay to pour concrete
5/2/25: Infill section approved, ok to grout.
05/28/2025 COT - HCPL - Plumbing Intermediate N/A Partial Pass 5-28-25, underground plumbing at freezer pad verified under test and per plans. Okay to backfill progress areas.
06/09/2025 COT - HCPL - Rough Soil N/A Partial Pass Grid line E6-7 underground sewer approved. Okay to backfill progress areas. Shading required. 6/9/2025
09/09/2025 COT - HCEL - Electrical Above Ceiling N/A Partial Pass 9-9-25: courtesy inspection -Area D-verified grounding/bonding of equipment to include, ATS, MTS, transformer, panels. New generator for grocery store in place & feeders are torqued to specifications.
12/05/2025 COT - BULD - SWG Clearance N/A Not Applicable
09/10/2025 BULD - Electrical Clearance N/A Partial Pass Tcom11 verbalbal clearance to TEP INCR

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-0125-00169
Permit Description: Amazon Grocery Tenant Improvement
Total Completed Inspections - 21
Date Description Inspector Results Comments
06/16/2025 COT - HCBU - Preslab Passed 6/16/2025 all saw cuts reinforcements and clearances from earth approved. Okay for concrete placement.
11/18/2025 COT - FCON - Alarm - Final Passed
11/18/2025 COT - FCON - Sprinkler - Final Passed
11/18/2025 COT - FCON - Fire - Final Passed
11/20/2025 COT - HCBU - Framing Passed
11/20/2025 COT - HCBU - Excavation/Rebar/Zoning Passed
11/25/2025 TRSP - ROW - Final/Close-Out Passed Work completed outside of right of way
12/05/2025 COT - HCEL - Electrical Intermediate Passed
12/05/2025 COT - HCEL - Electrical Underground Passed
12/05/2025 COT - HCME - Mechanical Above Ceiling Passed
12/05/2025 COT - HCME - Mechanical Intermediate Passed
12/05/2025 COT - HCPL - Plumbing Intermediate Passed
12/05/2025 COT - HCPL - Rough Soil Passed
12/05/2025 COT - HCEL - Electrical Above Ceiling Passed
12/05/2025 COT - HCPL - Plumbing Above Ceiling Passed
12/18/2025 COT - HCBU - Building Final Passed
12/18/2025 COT - HCBU - TCO Passed
12/18/2025 COT - HCEL - Electrical Final Passed
12/18/2025 COT - HCME - Mechanical Final Passed
12/18/2025 COT - HCPL - Plumbing Final Passed
12/19/2025 ENGR Engineering Final Passed