Inspection Status: Partial Pass

Inspection History: COT - HCBU - Excavation/Rebar/Zoning 

Permit Number - TC-COM-0125-00169

Inspection Description - COT - HCBU - Excavation/Rebar/Zoning 

Inspection Status - Partial Pass

Date Description Inspector Results Comments
04/25/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 4-25-25, preslab, excavation & reinforcement for filling in 3 dock levelers verified per plans. Okay to pour concrete
05/02/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 4-25-25, preslab, excavation & reinforcement for filling in 3 dock levelers verified per plans. Okay to pour concrete
5/2/25: Infill section approved, ok to grout.
05/15/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 4-25-25, preslab, excavation & reinforcement for filling in 3 dock levelers verified per plans. Okay to pour concrete
5/2/25: Infill section approved, ok to grout.
5/15/25: ok to pour last dock pit. Reinforcement per plans
05/29/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 4-25-25, preslab, excavation & reinforcement for filling in 3 dock levelers verified per plans. Okay to pour concrete
5/2/25: Infill section approved, ok to grout.
5/15/25: ok to pour last dock pit. Reinforcement per plans
5/29/25: inspection was for plumbing underground at GL D.5-E.5/6. Ok to backfill progress areas.
06/05/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 6-5-25: reinforcement/excavation at grid E5, E6, and at freezer pad verified per plans. Okay to pour concrete.
06/26/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Generator pad. Reinforcement per plan. Conduit in place okay for concrete placement. 6/26/2025
07/01/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 7/1/2025 Refrigerator pad outside building okay for concrete placement.
08/04/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 4-25-25, preslab, excavation & reinforcement for filling in 3 dock levelers verified per plans. Okay to pour concrete
5/2/25: Infill section approved, ok to grout.
5/15/25: ok to pour last dock pit. Reinforcement per plans
5/29/25: inspection was for plumbing underground at GL D.5-E.5/6. Ok to backfill progress areas.
6-5-25: reinforcement/excavation at grid E5, E6, and at freezer pad verified per plans. Okay to pour concrete.

Generator pad. Reinforcement per plan. Conduit in place okay for concrete placement. 6/26/2025

7/1/2025 Refrigerator pad outside building okay for concrete placement.
8/4/25: Dock leveler pit slab per plans ok to proceed with concrete placement.
08/06/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 8-6-25: reinforcement verified per detail S3.01 -5 on Dock Leveler #110. Okay for concrete placement.
11/20/2025 COT - HCBU - Excavation/Rebar/Zoning  Passed