Permit: TC-COM-0123-00509
Permit Details
Apply Date:
01/19/2023
Applicant:
Bill Clayton
Description:
New, Ground Up, Commercial Building for storage. Pre Fabricated metal building. Please reference DP22-0156 for approved development plan.
Permit Reviews
Permit Number - TC-COM-0123-00509
Permit Status: Complete
Permit Description: New, Ground Up, Commercial Building for storage. Pre Fabricated metal building. Please reference DP22-0156 for approved development plan.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/03/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.3 | 10/03/2025 | REQUIRES RESUBMIT |
| 02/08/2023 | COMMERCIAL REVIEW - FULL v.1 | 03/09/2023 | REQUIRES RESUBMIT |
| 05/05/2023 | RESTAMP - COMMERCIAL v.3 | 05/18/2023 | APPROVED |
| 04/28/2023 | RESTAMP - COMMERCIAL v.1 | 05/01/2023 | REQUIRES RESUBMIT |
| 06/20/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/23/2025 | APPROVED |
| 10/22/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.4 | 10/23/2025 | APPROVED |
| 04/07/2023 | COMMERCIAL REVIEW - FULL v.2 | 04/28/2023 | APPROVED |
| 09/18/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/18/2025 | REQUIRES RESUBMIT |
| 05/03/2023 | RESTAMP - COMMERCIAL v.2 | 05/04/2023 | REQUIRES RESUBMIT |
| 05/18/2023 | RESTAMP - COMMERCIAL v.1 | 05/18/2023 | APPROVED |
| 09/24/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 09/25/2025 | REQUIRES RESUBMIT |
| 06/09/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/09/2025 | APPROVED |
Conditions
Permit Number - TC-COM-0123-00509
Permit Status: Complete
Permit Description: New, Ground Up, Commercial Building for storage. Pre Fabricated metal building. Please reference DP22-0156 for approved development plan.
| Date | Description | Comments |
|---|---|---|
| 06/09/2025 | AIR BALANCING REPORT IS REQUIRED. | |
| 06/09/2025 | COMMISSIONING REPORT IS REQUIRED. | |
| 06/09/2025 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 04/07/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. | |
| 06/09/2025 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 06/09/2025 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
| 06/09/2025 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
| 06/09/2025 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
| 06/09/2025 | Masonry Inspection Report submittal review is required. | |
| 04/14/2023 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0123-00509
Permite Description: New, Ground Up, Commercial Building for storage. Pre Fabricated metal building. Please reference DP22-0156 for approved development plan.
Total Outstanding Inspections - 11
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/07/2023 | COT - HCPL - Plumbing Progress | N/A | Partial Pass | Plumbing underneath the slab per plan. Okay to backfill. Shading required. 6/7/2023 |
| 01/17/2025 | COT - HCEL - Electrical Above Ceiling | N/A | Not Ready | |
| 08/13/2024 | COT - HCEL - Electrical Intermediate | N/A | Not Ready | |
| 01/31/2025 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 01/31/2025 | COT - HCBU - Building Above Ceiling | N/A | Not Applicable | |
| 01/31/2025 | COT - HCEL - Electrical Underground | N/A | Not Applicable | |
| 01/31/2025 | COT - HCME - Mechanical Above Ceiling | N/A | Not Applicable | |
| 01/31/2025 | COT - HCME - Mechanical Intermediate | N/A | Re-inspection required | 1-Install exhaust fans per plans. 2-Finish ductwork. |
| 02/10/2025 | COT - HCME - Mechanical Final | N/A | Not Ready | Pass intermediate first. |
| 01/31/2025 | COT - HCBU - Building Final | N/A | Not Ready | work incomplete |
| 08/29/2025 | ENGR Engineering Final | N/A | Not Ready | 12’ Address numbers need to fixed to top of wall facing Halron CT. Okay for TCO level 4. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0123-00509
Permit Description: New, Ground Up, Commercial Building for storage. Pre Fabricated metal building. Please reference DP22-0156 for approved development plan.
Total Completed Inspections - 27