Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-COM-0123-00463
Permit Details
Apply Date:
01/12/2023
Applicant:
Jackie Grogan
Description:
In response to UPS needs at existing facility, install new above ground fuel storage tank skid with dispensers and new concrete pad to be connected to existing infrastructure
Permit Reviews
Permit Number - TC-COM-0123-00463
Permit Status: Complete
Permit Description: In response to UPS needs at existing facility, install new above ground fuel storage tank skid with dispensers and new concrete pad to be connected to existing infrastructure
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/08/2023 | COMMERCIAL REVIEW - FULL v.2 | 03/13/2023 | REQUIRES RESUBMIT |
09/01/2023 | COMMERCIAL REVIEW - FULL v.5 | 10/09/2023 | APPROVED |
02/04/2023 | COMMERCIAL REVIEW - FULL v.1 | 03/07/2023 | REQUIRES RESUBMIT |
10/09/2023 | RESTAMP - COMMERCIAL v.1 | 10/10/2023 | APPROVED |
05/26/2023 | COMMERCIAL REVIEW - FULL v.3 | 05/26/2023 | REQUIRES RESUBMIT |
06/07/2023 | COMMERCIAL REVIEW - FULL v.4 | 06/22/2023 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-COM-0123-00463
Permit Status: Complete
Permit Description: In response to UPS needs at existing facility, install new above ground fuel storage tank skid with dispensers and new concrete pad to be connected to existing infrastructure
Date | Description | Comments |
---|---|---|
06/12/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0123-00463
Permite Description: In response to UPS needs at existing facility, install new above ground fuel storage tank skid with dispensers and new concrete pad to be connected to existing infrastructure
Total Outstanding Inspections - 4
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/09/2024 | BULD - Electrical Clearance | N/A | Not Applicable | |
02/09/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
02/09/2024 | COT - HCBU - Building Final | N/A | Partial Pass | 2/9/24: partial pass. Pending fire final and engineering final |
02/09/2024 | ENGR Engineering Final | N/A | Partial Pass | Will need verification of 6” bollards footings, concrete pad, and fence post footings, 3rd party engineering testing and inspection reports prior to recall of Engineering Final. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0123-00463
Permit Description: In response to UPS needs at existing facility, install new above ground fuel storage tank skid with dispensers and new concrete pad to be connected to existing infrastructure
Total Completed Inspections - 7
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/06/2024 | COT - HCBU - Building Progress | Passed | ||
02/06/2024 | COT - HCEL - Electrical Intermediate | Passed | 2/6/24: electrical conduits from building to fuel depending tank per plan (rough-in complete) | |
02/06/2024 | COT - HCEL - Electrical Progress | Passed | ||
01/31/2024 | TRSP - ROW - Final/Close-Out | Passed | ||
03/25/2024 | COT - FCON - Fire - Final | Passed | Passed on condition that a NFPA Diamond and "Unleaded Fuel" Label be installed on tank. | |
03/26/2024 | COT - HCBU - Building Final | Passed | ||
03/26/2024 | ENGR Engineering Final | Passed | Fire Department has signed off on fuel tank inspection. |