Permit: T98CM03109
Permit Details
Apply Date:
07/20/1998
Applicant:
BAGLEY WALTER G & SUSAN M JT/RS
Description:
ADDITION:OFFICE & BATHROOM & LAUNDRY
Outstanding Inspections
Permit Status: Expired
Permit Number: T98CM03109
Permite Description: ADDITION:OFFICE & BATHROOM & LAUNDRY
Total Outstanding Inspections - 8
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
PLUMBING - SEWER HCS CONNECT | N/A | Not Inspected | ||
PERMIT FINALED | N/A | Not Inspected | ||
03/03/2000 | BUILDING - FINAL | N/A | Correction Required | ADDTL COMMS - DENIED - 1. PROVIDE LETTER FROM LICENSED PLUMBING INSTALLER THAT ALL ROUGH AND INTERMEDIATE PLUMBING WAS ACCOMPLISHED PER CODE AND THAT THEY ARE RESPONSIBLE FOR THE WORK. CITY OF TUCSON IS NOT TO BE HELD RESPONSIBLE FOR WORK NOT INSPECTED. THE LETTER MUST BE PLACED ON FILE WITH DEVELOPMENT SERVICES AND A COPY RETURNED FOR INSPECTORS VARIFICATION. THE LETTER MUST HAVE PLAN CHECK STAMP. 2. A/C DISCONNECT IS NOT PROPERLY MOUNTED. SECURE FROM ROTATION. 3. A/C WEATHER TIGHT CONNECTORS ARE LOOSE. 4. PAINT A.B.S. PLUMBING ON ROOF WITH LATEX PAINT. |
03/03/2000 | ELECTRIC - FINAL | N/A | Denied | IVRS - Inspection 0999* |
03/03/2000 | PLUMBING - INTERMEDIATE | N/A | Denied | IVRS - Inspection 0999* |
03/03/2000 | PLUMBING - FINAL | N/A | Denied | IVRS - Inspection 0999* |
03/03/2000 | MECHANICAL - FINAL | N/A | Denied | IVRS - Inspection 0999* |
09/14/1998 | PLUMBING - ROUGH, SOIL | N/A | Denied | DENIED |
Completed Inspections
Permit Status: Expired
Permit Number: T98CM03109
Permit Description: ADDITION:OFFICE & BATHROOM & LAUNDRY
Total Completed Inspections - 6
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/01/1998 | MECHANICAL - INTERMEDIATE | MCAPISTR | Approved | DENIED |
09/01/1998 | MECHANICAL - INTERMEDIATE | MCAPISTR | Approved | ADDTL COMMS - 1. PROVIDE 3RD BLOCK / SUPPORT OF AIR REGISTERE HOUSING. PLUMBING: 1. EXPOSE SEWER CONNECTION- NEW BATH AND LAUNDRY DRAINS. 2. PROVIDE ISOMETRIC OF DWV PIPING. 3. PROVIDE LETTER FROM PLUMBING CONTRACTOR INDEMNIFYING CITY HAVE TI RECORDED. MUST BEAR RECORDERS SEAL. |
09/01/1998 | ELECTRIC - INTERMEDIATE | MCAPISTR | Approved | DENIED |
09/01/1998 | ELECTRIC - INTERMEDIATE | MCAPISTR | Approved | ADDTL COMMS - 1. HAVE TEP DISTRICT REP INSPECT METER / MAIN / LOAD CENTER. PROVIDE WRITTEN APPROVAL OF LOCATION, HEIGHT, ETC ( BY TEP). 2. PROVIDE SIZE AND TYPE OF MAIN SERVICE CONDUCTORS. |
09/14/1998 | FRAMING | MCAPISTR | Approved | DENIED |
09/14/1998 | FRAMING | MCAPISTR | Approved | ADDTL COMMS - 1. INSULATE THE COPPER PIPE AT ALL LOCATIONS WHERE IT MIGHT COME IN CONTACT WITH GALVANIZED STEEL FRAMING. PLASTIC BUSHING POORLY INSTALLED AT BATH SINK ( TOP PLATE). ON IS MELTED. 2. I AM CONCERNED THAT THE 2X6 RAFTERS WILL BE OVERLOADED WHEN A/C HEATING UNIT IS MTD ON ROOF. DOUBLE UP ON RAFTERS OR PROVIDE ENGINEERS DATA APPROVEING EXISTING ARRANGEMENT. 3. PROVIDE RECORDED INDEMNIFICATION FOR PLUMBING AND SLAB ON CLOSER EXAM IT APPEARS NO FOOTINGS WERE ADDED FOR THE 6 OF NEW SLAB. |